HomeMy WebLinkAboutRatify - HA35160 - CO1 and CO2 - Parking Lot Imprvmnt at Las SerenasREQUEST:
SUBMITTED BY:
DATE:
CONTENTS:
Recommendation
CONTRACT NO. HA35160
PALM DESERT HOUSING AUTHORITY
STAFF REPORT
RATIFICATION OF EXECUTIVE DIRECTOR'S APPROVAL OF
CHANGE ORDERS NO. 1 AND 2 TO WESTCON
CONSTRUCTION FOR THE PARKING LOT IMPROVEMENTS AT
LAS SERENAS APARTMENTS
Veronica Tapia, Senior Management Analyst
October 13, 2016
Change Orders No. 1 and 2
Westcon Proposals
By Minute Motion, that the Authority Board ratify Executive
Director's approval of Change Order No. 1 in an amount not to exceed
$3,237 and Change Order No. 2 in an amount not to exceed $18,350 to
Westcon Construction related to the Parking Lot Improvements at Las
Serenas Apartments.
Funds are available in contingency and will be paid from the
Housing Authority Replacement Reserve Fund
Executive Summary
Westcon Construction was awarded the contract for Parking Lot Improvements in May,
2016. The Authority Board also authorized the Executive Director to approve any
change order requests within the contingency amount. During construction some
unanticipated conditions were identified that needed to be remedied, including
transitions from existing asphalt to concrete and overlays around carport post supports.
Background
The Authority solicited proposals from contractors to complete the necessary parking lot
improvements at Las Serenas Apartments. The primary goals of the project were to
remediate areas that had been damaged due to extensive water corrosion, restripe, and
improve the sustainability of the surfaces for long-term success.
Westcon Construction was awarded the bid in May, 2016 with work scheduled to begin
in July, 2016. At that time, the Authority Board authorized the Executive Director to
approve change orders up to the contingency amount of $25,799 to ensure the project
was completed timely. During the construction, a few unanticipated factors were
identified that needed solutions in order to proceed with the scheduling of the project, as
well as the needs of the senior community.
The first issue identified occurred with the transition from asphalt to concrete in all of the
carport areas. While removing the asphalt, it was discovered that the footings in the
carport areas were not set as deep as had been expected. In order to ensure that the
Staff Report
Ratifying Change Orders No. 1 and 2 — Las Serenas Parking Lot Improvements
October 13, 2016
Page 2 of 2
integrity of the carports was not disturbed, Westcon suggested to cut around the
footings, clean the remaining asphalt sections, fill gaps, and place an overlay around
the posts to protect the surface while maintaining the aesthetic of the concrete
improvements. As this was not identified in the original plans, it resulted in additional
labor, materials and costs. With approximately 156 posts at $20.75/post, the change
order request amounted to $3,237.
Once the work was nearly complete, City staff, RPM Company staff, and Westcon did a
walk-through and identified a few other areas that required additional attention due to
the water damage that occurred from the old irrigation system. During the walk-through
it was apparent that the curb painting needed to be updated throughout the property as
the contractor was only required to update the areas affected by new construction,
leaving many places with grossly deteriorated curb paint. Next, while originally staff
believed that the seal coat would be sufficient for the driveways of the development,
upon completion of seal coating, it revealed that the erosion created by the old irrigation
system had extended past the carport areas in some spots where the seal coat was not
adhering well and would have resulted in uneven areas. Consequently, a second
change order was requested for the curb painting at $4,430, as well as, the asphalt
upgrades that were proposed at $13,920 by Westcon. The total change order request
was $18,350, which was well within the Executive Director's authority and was
approved.
Therefore, staff recommends that the Authority Board ratify the Executive Director's
approval of Change Order No. 1 and Change Order No. 2 with Westcon Construction in
a combined amount not to exceed $21,587 to complete the Parking Lot Improvement
Project at Las Serenas Apartments.
Fiscal Impact
The fiscal impact is the cost of the change orders which will be paid from the Housing
Authority's Replacement Reserve Fund.
Submitted by:
Reviewed:
Veronica Tapia, Senior Management Analyst Janet ' oore, Di -ctor ,r Finance
Approval:
Lauri AyFaian, Executive— rector
VAT:tbm
gigs -I) BY HOUSG AUTH
ON 1 b--1 -Re)
VERIFIED BY: W 0.1^4 ,
Original on file with City Olerk's OffiCo
G.\RDA\VERONICA TAPIA\WORD FILES\PDHA\LAS SERENAS ASPHALT\SR-LS PARKING LOT IMPS - RATIFY CO NO. 1 AND 2 10-13-16 DOC
PALM DESERT HOUSING AUTHORITY
INTEROFFICE MEMORANDUM
TO: Justin McCarthy, Interim Executive Director
FROM: Veronica Tapia, Senior Management Analyst
DATE: July 21, 2016
SUBJECT: Change Order Request No. 1 — Las Serenas Parking Improvements
The Las Serenas Parking Lot Improvements construction began July 11, 2016. While
removing the layers of asphalt, the Contractor quickly discovered that the posts of the
carports were supported by small concrete footings.
Upon some consideration, and rather than interrupt the integrity of the carports and potentially
incur damages, a solution was planned out between City staff and the Contractor to remove
the surrounding asphalt, clean up the footings a bit, use felt to create a barrier around the
footings, fill the felted areas with some sort of filler/sealant and then pour the concrete around
the area with joints in between.
There are 156 posts that would require this treatment. Since this solution was thought up in
the field, City staff asked the Contractor to do one post and then we would make our final
determination. Attached is the successful and dramatic result.
On May 12, 2016, the Authority Board authorized the Executive Director to review and
approve written requests for the use of the contingency in the amount of $25,799 for
unforeseen conditions on this project. Therefore, staff requests approval of the $3,237
change order and believes the minimal costs will allow the project to be completed in an
efficient and uniformed manner at this affordable senior community.
Review and Concur:
ltrysti McCarthy, Interim Execut+�e Director
VAT:t m
(1 iAa \'crunisa !VIA \\'urd 1- es 1'1)11 \ I at Serenas Asphalt PRVJI C 1111.P 1.45 \crrnas I'ni kinf Ion Stab Rcpolts \Inuo to 1\1 le ('a, pum'-_ I It• do,.
CITY OF PALM DESERT
CONSTRUCTION CHANGE ORDER
Contract Purpose
Consultant s Name
Address
Las Serenas Parking Improvements
Westcon Construction
81-149 Indio Blvd.. Indio. CA 92201
Contract » % P 0 #
Change Order No
Contingency
Account No
Project No
Vendor No
HA 35160 l
1
YES X NO
87186404400100
You are hereby requested to comply with the following changes from the contract plans and specifications
DESCRIPTION OF CHANGES
(Supplemental Plans, Specifications and Directives dated
Clean. patch grout carport bases
JUSTIFICATION
TOTAL BUDGET FOR PROJECT:
Less Expend & Encumb To Date
Less This Change Order Amount
BALANCE OF BUDGET
REMAINING FOR PROJECT
Attached)
TOTALS:
NET CHANGE IN CONTRACT PRICE:
+ 283.789.00
3,237.00
280.552.00
DECREASE
In Contract Price
CONTINGENCY:
Amount Approved by Council
Less Prior Change Order(s)
Less This Change Order
Balance Remaining of Contingency
INC REASE
In Contract Price
3 237 00
3 237 00
3 237 00
+ 25 799 00
3,237 00
22,562 00
The amount of the Contract will be (Decreased) Increased by the Sum of: Three Thousand Two Hundred and
Thirtv-Seven Dollars ($3,237.00).
G ,'Ca'Verornca Tac,a°Aorc F. es\PDHA,Las Sore -as PR0JEC' F,_F. '_as Sere -as Pa'' -y _ .. [es ^3r-e J•ce• _ 1-s• _� h:
See reverse
Contract HA 35160 Change Order No. 1 Continued from front
This Change Order covers changes to the subject contract as described herein The Contractor shall construct, furnish
equipment and materials. and perform all work as necessary or required to complete the Change Order items for a
lump sum price agreed upon between the Contractor and the City of Palm Desert. otherwise referred to as Owner
Contract Time Extension
-0- Days
Revised Contract Total $261 227 00
The undersigned Contractor approves the foregoing Change Order # 1 as to the changes. if any in the contract
price specified for each item including any and all superv!sion costs and other miscellaneous costs relating to the
change in work. and as to the extension of time allowed, if any. for completion of the entire work on account of said
Change Order # 1 The Contractor agrees to furnish all labor and materials and perform all other necessary work.
inclusive of that directly or indirectly related to the approved time extension. required to complete the Change Order
items This document will become a supplement of the contract and all provisions will apply hereto It is understood
that the Change Order shall be effective when approved by the Owner
Execution of this Change Order by the Contractor constibjtes a binding accord and satisfaction that fully satisfies
waives, and releases the Owner from all claims. demands, costs and liabilities, in contract law or equity arising out of
or related to the subject of the Change Order, whether known or unknown. including but not limited to direct and
indirect costs and/or damages for delay disruption, acceleration, loss of productivity, and stacking of trades. as well as
any and all consequential damages.
This document will become a supplement to the Contract and all provisions will apply hereto all items included above
must have required signatures as per the purchase resolution
1 REQUESTED BY
3 CERTIFIED
FUNDS AVAILABLE
/ 7 4Z
2
ACCEPTED BY 4 7/6
DEPARTMENT HEAD CON ip-�ACT0h Date Acceptea
4 APPROVED BY
'
FINANCE DIRECTOR EXECUTIVE DIRECTOR
NOTE: No payments will be made prior
to City Manager and Council approval
-Date App-oved
G roa'vero'.ca-aoa::crc = .es Serer ' : RC . _ . .a
See reverse
7/21/2016
Change Order Proposal
Las Serenas Parking Lot Improvements
prepared for
City of Palm Desert
WESTE011
Item Description Quantity Unit Unit Price Total
1 Clean, patch, grout carport bases 156 EA $ 20.75 $ 3,237.00
TOTAL BID $ 3,237.00
Special Conditions:
Work to be performed per mock-up (photo attached).
Parking stall striping to be rescheduled as needed to allow work at bases to be completed first. This may
require cars to be relocated a second time for a short period (less than a day). We will coordinate with on -site
staff.
PAYMENT 1 of 1 Revised: 7/21/2016 @ 11:53 AM
TO:
FROM:
DATE:
SUBJECT:
PALM DESERT HOUSING AUTHORITY
MEMORANDUM
Justin McCarthy, Interim Executive Director
Veronica Tapia, Management Analyst
September 7, 2016
Change Order No. 2 — Las Serenas Parking Lot Improvements
The parking lot improvements project at Las Serenas are nearing completion. On Tuesday,
August 30, City Staff, along with RPM Management, the Contractor and the Sub -Contractor
did a walk-through of the job to determine what issues remain outstanding.
A punch list of items that needed to be completed was developed along with the discussion
of items that were either unknown prior to mobilization or thought to be part of the project. A
couple of major items that stood out and agreed upon as change order items included:
1. Curb Painting throughout the facility (only areas that were required by code had been
updated leaving the rest of the development aged and unidentifiable in some areas.
2. Asphalt Repairs. The seal coat was thought to be sufficient for rehabbing the
driveways of the development. However upon completion, it revealed that there were
areas that seal coat was not enough.
a. In the roundabout at the rear of the development, there is substantial
deterioration in the inner circle immediate adjacent to the roundabout creating
a Health and Safety issue.
b. Also, while the carports were identified as having the most erosion from
faulty/outdated irrigation and landscaping and were replaced with concrete,
some areas extended past the carports and also create a Health and Safety
issue.
Therefore, staff is requesting Change Order No. 2 be approved in order to remediate these
issues and complete the project at Las Serenas.
The Executive Director has been given the authorization to approve change orders in an
amount not to exceed the approved contingency. This request stays within those
constraints.
Approval
J . ti McCarthy
nterin Executive Di
,Attaef ments (as noted)
G.\RDA\VERONICA TAPIA\WORD FILES\PDHA\LAS SERENAS ASPHALT\ PROJECT FILE LAS SERENAS PARKING LOTINVOICES\CO#2 MEMO TO ED.DOC
CITY OF PALM DESERT
CONSTRUCTION CHANGE ORDER
Contract Purpose
Consultant's Name
Address
Las Serenas Parking Improvements
Westcon Construction
81-149 Indio Blvd., Indio, CA 92201
Contract # / P.O. # HA 35160
Change Order No 2
Contingency* I YES X I NO
Account No. 87186404400100
Project No
Vendor No 1
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES
(Supplemental Plans, Specifications, and Directives dated
Prep and Paint Curb Throughout
Asphalt Repairs (including R&R of approx 175'x4' @ roundabout inside
curb and 20'x4' near parking stall 121, patch pothole near valley gutter
at Bldg M, fill approx 75 LF of joint between AC and gutter near Bldg M)
JUSTIFICATION:
TOTAL BUDGET FOR PROJECT:
Less: Expend. & Encumb. To Date:
Less: This Change Order Amount:
BALANCE OF BUDGET
REMAINING FOR PROJECT
DECREASE
Attached) In Contract Price
TOTALS:
NET CHANGE IN CONTRACT PRICE:
283,789.00
260, 305.00
18,350.00
5,134.00
CONTINGENCY:
Amount Approved by Council:
Less: Prior Change Order(s):
Less: This Change Order.
Balance Remaining of Contingency.
INCREASE
In Contract Price
4,430.00
13,920 00
18,350.00
18,350.00
+ 25,799.00
3,237.00
18,350.00
4,212.00
The amount of the Contract will be (Decreased) Increased by the Sum of: Eighteen Thousand Three Hundred
and Fifty- Dollars ($18,350.00).
G \rda\Veronica Tapa\Word Fdes\PDHA\Las Serenas Aspnait\PROJECT FILE Las Serenas Park,ng Lot \Invo,ces\Change Order - Construction No 2 doc
See reverse ...
Contract HA 35160 Change Order No. 2 Continued from front
This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish
equipment and materials, and perform all work as necessary or required to complete the Change Order items for a
lump sum price agreed upon between the Contractor and the City of Palm Desert, otherwise referred to as Owner.
Contract Time Extension
-0- Days.
Revised Contract Total $279,577.00
The undersigned Contractor approves the foregoing Change Order # 2 as to the changes, if any, in the contract
price specified for each item including any and all supervision costs and other miscellaneous costs relating to the
change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said
Change Order # 2 . The Contractor agrees to furnish all labor and materials and perform all other necessary work,
inclusive of that directly or indirectly related to the approved time extension, required to complete the Change Order
items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood
that the Change Order shall be effective when approved by the Owner.
Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies,
waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of
or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and
indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as
any and all consequential damages.
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above
must have required signatures as per the purchase resolution.
REQUESTED BY 2. ACCEPTED BY.
DEPARTMENT HEAD CONTRACTOR Date Accepted
3 CERTIFIED
FUNDS AVAILABLE: 4. APPROVED BY:
FINANCE DIRECTOR EXECUTIVE DIRECTOR Date Approved
NOTE: No payments will be made prior
to City Manager and Council approval
G Vda\Veronica Tapia\Word Files\PDNA\Las Serenas AsphaIttPROJECT FILE Las Serenas Parking Lotunvoices\Cnange Order - Construction No 2 doc
See reverse
Item
1
2
9/2/2016
Description
Change Order Proposal
Las Serenas Parking Lot Improvements
prepared for
City of Palm Desert
Prep and Paint Curb (approximately 1992 LF red
and 28 LF blue)
Asphalt Repairs (includes R&R of approximately
175'x4' @ roundabout inside curb and 20'x4'
near parking stall 121, patch pothole near valley
gutter at Bldg M, fill approx 75 LF of joint
between AC and gutter near Bldg M)
Special Conditions:
WE5TCO11
Quantity Unit Unit Price Total
1 LS $ $ 4,430.00
1 LS $ $ 13,920.00
TOTAL BID
$ 18,350.00
Prep for curb paint includes scraping visible peeling and flaking paint off curbs. This does not guarantee
existing paint will not continue to peel.
Schedule for work to be mutually agreed upon.
PAYMENT 1 of 1 Revised. 9/6/2016 @ 4 00 PM