HomeMy WebLinkAboutHA36610 - Mailbox Canopies-Carports at One Quail Pl AptsCONTRACT NO. HA36610
MEETING DATE:
PREPARED BY:
REQUEST:
Recommendation
STAFF REPORT
PALM DESERT HOUSING AUTHORITY
HOUSING DEPARTMENT
April 26, 2018
Jessica Gonzales, Senior Management Ana
Authorize the award of Contract No. HA36610 to S&T Contractors
Services, Inc. for Construction of Mailbox Canopies and Carports
Project at One Quail Place Apartments in a total amount of $278,500.
By Minute Motion, that the Authority Board,
1) Waive any and all irregularities and authorize the award of Contract No.
HA36610 to S&T Contractors Services, Inc. for Construction of Mailbox
Canopies and Carports Project at One Quail Place Apartments. The
contract will be in a total amount of $278,500; and
2) Authorize the Director of Finance to set aside 20% contingency of $55,700
for unforeseen conditions; and
3) Authorize the Executive Director or designee to review and approve
written requests for the use of the contingency amount of $55,700 for
unforeseen conditions; and
4) Authorize the Executive Director and/or the Chairman to execute the
negotiated contract and any documents necessary to facilitate the contract
award and project.
Monies are available in the Authority's capital replacement budget.
Housing Commission Recommendation
The Housing Commission reviewed this recommendation at its regular meeting of April
11, 2018, and unanimously recommended approval of the staff recommendation.
Strategic Plan
This request does not apply to a specific strategic plan goal.
Background Analysis
A notice inviting proposals for Construction of Mailbox Canopies and Carports Project at
One Quail Place Apartments ("Project") was advertised in the local newspaper on
April 26, 2018 - STAFF REPORT
Housing Authority - Authorize award of contract to S&T Construction Services, Inc.
Page 2 of 2
March 18, 2018 and March 28, 2018. On Wednesday, April 4, 2018 at 2:00 p.m.,
proposals were opened and read aloud by the City Clerk and the following two (2) bids
were received:
S&T Contractors Services, Inc.
NR Development, Inc.
Palm Desert, CA
Downey, CA
$278,500
$299,500
The lowest responsive bidder is S&T Contractors Services, Inc. ("S&T") in the base bid
amount of $278,500. Although S&T's bid did not include the Department of Industrial
Relations (DIR) number on the outside of the envelope submitted, S&T's bid meets the
qualifications for the Project. Staff recommends that the Authority Board waive this
irregularity and any other irregularities and award the contract to S&T for the Project in
the total amount of the base bid of $278,500 with a 20% contingency reserved for any
additional unforeseen conditions necessary to be completed not to exceed $55,700.
Staff also recommends that the Executive Director be authorized to review and approve
written requests for the use of the contingency for unforeseen conditions that require
additional work.
Fiscal Analysis
The fiscal impact of this contract is the cost of the contract itself in the amount of
$278,500 plus 20% contingency in the amount of $55,700 (for unforeseen conditions)
which will be paid from the Authority's capital replacement budget.
LEGAL REVIEW DEPT. REVIEW
N/A
Robert H. Hargreaves Janet Moore
City Attorney 1'
erector of Finance
FINANCIAL
REVIEW
%l'lL
Janet Moore
I3frector of Finance
CONTRACTOR: S&T Contractors Services, Inc.
75151 Sego Lane, Suite E6
Palm Desert, CA 92211
ATTACHMENTS: Bid Form (Exhibit B)
Draft Agreement
CITY MANAGER
Lauri Aylaia�-
City Manager
4 6{BY HOUSG AUT1-1 13 -0
ON r)L-
VERIFIED BY:
' ri nai on file %nth City I rk's. Offic.
pq6c,t-lqinikiKelkhAte^' e t" L( Ct� 1C(
J1YrtMccii
NOEM.c)),
SECTION 00400
BID FORM
BID FORM ,
NAME OF BIDDER: , 1`t� T 06deacAas- c K UEc s 07?(7 •
The undersigned, hereby declare that we have carefully examined the location of the
proposed Work, and have read and examined the Contract Documents, including all
plans, specifications, and all addenda, if any, for the following Project:
CONSTRUCTION OF MAILBOX CANOPIES AND CARPORT PROJECT
AT ONE QUAIL PLACE APARTMENTS
CONTRACT NO. HA36610
We hereby propose to furnish all labor, materials, equipment, tools, transportation,
incidentals and services, and to discharge all duties and obligations necessary and
required to perform and complete the Project in strict accordance with the Contract
Documents for the SUBMITTED TOTAL BID PRICE.
In the event the bid schedule requires unit pricing, final payment shall be determined by
the Authority from measured quantities of work performed based upon the unit price.
Item
No.
1
2
3
Description
Construction of mail box
canopy No. 1
Construction of mail box
canopy No. 2
Construction of mail box
canopy No. 3
Units
LS
LS
LS
4 Construction of carport No. 1 LS
5 Construction of carport No. 2 LS
6 Construction of carport No. 3 LS
7 Construction of carport No. 4 LS
Approximate Unit Cost
Quantity
1 $/6666.
-°
1
Total Amount
$l40
$�3, 4
1 $ St‘' $ L%, Sel6' 5'
$$ 917 56'
$2,t)—$5,5,,9
8 Construction of carport No. 5 LS
GRAND TOTAL
1
SECTION 00400
BID FORM
-12-
sz-aias)
77802.00000124431586 2 Construction of Mailbox Canopies and Carports Project Contract No HA36610 (March 18, 2018)
SECTION 00400
BID FORM
Bidders must provide pricing for every bid item.
The estimated quantities for unit price items are for purposes of comparing bids only
and the Authority made no representation that the actual quantities of work performed
will not vary from the estimates.
In case of discrepancy between the unit price and the line item cost set forth for a unit
price item, the line item cost, calculated at the unit price multiplied by the estimated
quantity, shall prevail and shall be utilized as the basis for determining the lowest
responsive, responsible bidder. However, if the amount set forth as a unit price is
ambiguous, unintelligible or uncertain for any cause, or is omitted, or is the same
amount as the entry in the "Line Item Cost" column, then the amount set forth in the
"Line Item Cost" column for the item shall prevail and shall be divided by the estimated
quantity for the item and the price thus obtained shall be the unit price. If any of the
above discrepancies exist, the Authority may recalculate the bid price on the basis of
the unit price and the bidder agrees to be bound by such recalculation. Final payment
for unit price items shall be determined by the Authority from measured quantities of
work performed based upon the unit price.
TOTAL BID PRICE (BASED ON BID SCHEDULE TOTAL OF UNIT PRICES):
$ 0_1 B5000
Total Bid Price in Numbers
JUJIA
0 U:RJ1,0-fotrJ
Tota Bid Price iWritten Form
In case of discrepancy between the written price and the numerical price, the written
price shall prevail.
The undersigned agrees that the bid accompanied by this Bid Form constitutes a firm
offer to the Authority which cannot be withdrawn for the number of calendar days
indicated in the Notice Inviting Bids from and after the bid opening, or until a Contract
for the Work is fully executed by the Authority and a third party, whichever is earlier.
If the Contract Documents specify alternate bid items, the Alternate Additive or
Deductive Bid amounts shall be added to or deducted from the Total Bid Price at the
Authority's sole option. The Authority can choose to include one or more of the
Alternate Bids in the Project. If any of the Alternate Bids are selected by the Authority,
the resulting amount shall be added to or deducted from Total Bid Price for the Project.
The Authority may select one or more of the Alternate Bids at the stated Bid Price up to
SECTION 00400
BID FORM
-13-
77802 00000124431586.2 Construction of Mailbox Canapes and Carports Project Contract No HA36610 (March 18. 2018)
SECTION 00400
BID FORM
sixty (60) days following award of the Contract. The Authority can award/select
Alternate Bid items at any time(s).
The Contract duration shall commence on the date stated in the Authority's Notice to
Proceed, and shall be completed by the Contractor in the time specified in the Contract
Documents. In no case shall the Contractor commence construction prior to the date
stated in the Authority's Notice to Proceed, or before providing the required bonds and
evidence of insurance.
Bidder certifies that it is licensed in accordance with the law p o iding for the registration
of Contractors, License No. ciSa-(03 , Expiration Date � class of license
Ce. Bidder certifies that it is registered with the Departm - nt •f ndustrial Relations to
perform public work, Registration No.03673t. If the bidder is a joint venture, each
member of the joint venture must include the above information.
The undersigned acknowledges understanding and full consideration of the
electronically issued addenda to the Contract Documents.
1. Attached is the required bid security in the amount of not less than 10% of
the Total Bid Price.
2. Attached is the fully executed Non -Collusion Declaration form.
3. Attached in the completed Designation of Subcontractors form.
4. Attached is the completed Bidder Information Form.
5. Attached is the completed Iran Contracting Act Certification.
6. Attached is the completed Contractor's Certificate Regarding Workers'
Compensation form.
I hereby certify under penalty of perjury under the laws of the State of California, that all
of the information submitt d in connection with this Bid and all of the representations
made herein are true and •`,'rrect.
Name of Bidder E-fi-
�• J��s(11C-
Signature t5(-3
Name and TitleSeG.-�..e , ( �►frJ
Dated
SECTION 00400
BID FORM
- 14 -
77802.00000124431586.2 Construction of Mailbox Canopies and Carports Project Contract No. FIA36610 (March 18, 2018)
SECTION 00400
BID FORM
A notary public or other officer completing this certificate verifies only the identity of the individual who
signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of
that document.
State of California )
SS.
County of Riverside )
On 17/2- /Z— / 20ie before e, 5h -i- 6X , a
Notary Public, personally a$peared C5E/4�e1.E Lf $_I_p LI , who proved
to me on the basis of satisfactory evidence to be the persons whose namecyrsare subscribed
to the within instrument and acknowledged to me that he/they executed the same in
er/their authorized capacity(irj, and that by is her/their signature($on the instrument the
rson(s), or the entity upon behalf of which the person() acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the
foregoing paragraph is true and correct.
WITNESS my hand and official seal.
SHIRLEY A. BARDSNES
Notary Public - California
Riverside County
'��-.►�
Commission # 2162843
M�r Comm. Expires Se? 13, 2020
END OF BID FORM
SECTION 00400
BID FORM
-15-
77802 00000124431586.2 Construction of Mailbox Canopies and Carports Protect Contract No. HA36610 (March 18, 2018)
DRAFT FOR DISCUSSION
CONTRACT
THIS CONTRACT is made this 26TH day of April, 2018, in the County of Riverside,
State of California, by and between the Palm Desert Housing Authority, hereinafter called
Authority, and , hereinafter called Contractor. The
Authority and the Contractor for the considerations stated herein agree as follows:
ARTICLE 1. SCOPE OF WORK. The Contractor shall perform all Work within the time
stipulated the Contract and shall provide all labor, materials, equipment, tools, utility
services, and transportation to complete all of the Work required in strict compliance with
the Contract Documents as specified in Article 5 below for the following Project:
CONSTRUCTION OF MAILBOX CANOPIES AND CARPORT PROJECT
AT ONE QUAIL PLACE APARTMENTS
CONTRACT NO. HA36610
The Contractor and its surety shall be liable to the Authority for any damages arising as
a result of the Contractor's failure to comply with this obligation.
ARTICLE 2. TIME FOR COMPLETION. Time is of the essence in the performance of
the Work. The Work shall be commenced on the date stated in the Authority's Notice to
Proceed. The Contractor shall complete all Work required by the Contract Documents
within 90 calendar days from the commencement date stated in the Notice to Proceed,
hereinafter the Contract Time. By its signature hereunder, Contractor agrees the Contract
Time for completion set forth above is adequate and reasonable to complete the Work.
ARTICLE 3. CONTRACT PRICE. The Authority shall pay to the Contractor as full
compensation for the performance of the Contract, subject to any additions or deductions
as provided in the Contract Documents, and including all applicable taxes and costs, the
sum of Dollars ($ ), hereinafter
the Contract Price. Payment shall be made as set forth in the General Conditions.
ARTICLE 4. LIQUIDATED DAMAGES. The Contractor acknowledges that the Authority
will sustain actual damages for each and every day completion of the Project is delayed
beyond the Contract Time. Because of the nature of the Project, it would be impracticable
or extremely difficult to determine the Authority's actual damages. Accordingly, as
provided in Government Code section 53069.85, it is agreed that the Contractor will pay
the Authority the sum of $350 for each and every calendar day of delay in completing the
Work beyond the time prescribed in the Contract Documents for finishing the Work, as
Liquidated Damages and not as a penalty or forfeiture. In the event the Liquidated
Damages are not paid, the Contractor agrees the Authority may deduct that amount from
any money due or that may become due the Contractor under the Contract. This Article
does not affect the Authority's rights to other damages or remedies specified in the
Contract Documents or allowed by law.
SECTION 00500
CONTRACT
-1-
77802 00000 t 24431586 2 Construction of Mailbox Canopies and Carports Project Contract No. HA36610 (March 18, 2018)
DRAFT FOR DISCUSSION
Should Contractor be inexcusably delayed in the performance of the Work, Authority may
deduct Liquidated Damages based on its estimate of when Contractor will achieve Final
Completion or other milestones. Authority need not wait until Final Completion to withhold
Liquidated Damages from Contractor.
Liquidated Damages are not a penalty but an agreed upon estimate of the actual
damages that would be sustained by the Authority for delay, including but not limited to
loss of revenue, inconvenience to the Authority and the public, and increased Project
administration expenses, such as extra inspection, construction management, staff time
and architectural and engineering expenses. Liquidated Damages do not include actual
damages the Authority incurs on account of claims by third parties against the Authority
on account of any delay.
Should money due or to become due to the Contractor be insufficient to cover Liquidated
Damages or other offsets due, then Contractor forthwith shall pay the remainder of the
assessed liquidated damages to Authority.
ARTICLE 5. COMPONENT PARTS OF THE CONTRACT. The "Contract Documents"
include the following documents, each of which is incorporated into this Contract by
reference:
• Notice Inviting Bids
• Instructions to Bidders
• Bid Form
• Contractor's Certificate Regarding Workers' Compensation
Bid Bond
• Non -Collusion Declaration form
• Contractor Information and Experience Form
• List of Subcontractors Form
• Iran Contracting Act Certification
• Contract
• Performance Bond
• Payment Bond
• Environmental documents and approvals
• General Conditions
• Special Conditions
• Technical Specifications (including Appendices)
• Addenda
• Plans and Drawings
• Approved and fully executed change orders
• Federal Requirements
• Standard Specifications for Public Works Construction (Greenbook), Current Edition,
except Sections 1-9
• Any other documents contained in or incorporated into the Contract
SECTION 00500
CONTRACT
-2-
77802 00000124431586 2 Construction of Mailbox Canopies and Carports Protect Contract No HA36610 (March 18 2018)
DRAFT FOR DISCUSSION
The Contactor shall complete the Work in strict accordance with all of the Contract
Documents.
All of the Contract Documents are intended to be complementary. Work required by one
of the Contract Documents and not by others shall be done as if required by all. This
Contract shall supersede any prior agreement of the parties.
ARTICLE 6. PROVISIONS REQUIRED BY LAW. Each and every provision of law
required to be included in these Contract Documents shall be deemed to be included in
these Contract Documents. The Contractor shall comply with all requirements of
applicable federal, state and local laws, rules and regulations, including but not limited to,
the provisions of the California Labor Code and Public Contract Code applicable to this
Project.
If the Work involves federal funds, the Contractor and all its subcontractors shall comply
with all requirements set forth in the attached Federal Requirements.
ARTICLE 7. INDEMNIFICATION. Contractor shall provide indemnification as set forth
in the General Conditions.
ARTICLE 8. PREVAILING WAGES. Contractor shall be required to pay the prevailing
rate of wages in accordance with the Labor Code which such rates shall be made
available at the Authority's offices, 73-510 Fred Waring Drive, Palm Desert CA 92260, or
may be obtained online at http//www.dir.ca.gov/dlsr. and which must be posted at the job
site.
ARTICLE 9. NOTIFICATION TO AUTHORITY. Contractor acknowledges that the
Authority provides forty-eight (48) hours -notice to residents in advance of the start of any
Work that is to occur at any residential unit. Contractor shall provide sufficient notice to
the Authority before beginning any such Work so that the Authority may provide timely
notice to residents. The Authority shall be given at least 48 hours -notice prior to the
creation of any condition affecting pedestrian paths of travel. Contractor shall
continuously inform Authority of the progress of the Work or of any impacts of the Work
upon residential units or facilities.
ARTICLE 10. LOCAL LICENSES AND PERMITS. Unless the Contract Documents state
otherwise, Contractor shall be responsible for securing City of Palm Desert business
license(s), building permits, and any other licenses or permits necessary to perform the
Work.
IN WITNESS WHEREOF, this Contract has been duly executed by the above -named
parties, on the day and year above written.
SECTION 00500
CONTRACT
-3-
77802.00000\24431586 2 Construction of Mailbox Canopies and Carports Project Contract No HA36610 (March 18 2018)
DRAFT FOR DISCUSSION
NAME OF CONTRACTOR1 PALM DESERT HOUSING AUTHORITY
By By
Name and Title: Name and Title:
License No.
Registration No.
END OF CONTRACT
SECTION 00500
CONTRACT
-4-
77802 00000\24431586 2 Construction of Mailbox Canopies and Carports Project Contract No HA36610 (March 18, 2018)
DRAFT FOR DISCUSSION
PERFORMANCE BOND
KNOW ALL PERSONS BY THESE PRESENTS:
THAT WHEREAS, the Palm Desert Housing Authority (hereinafter referred to as
"Authority") has awarded to , (hereinafter referred to as the
"Contractor") an agreement for
(hereinafter referred to as the "Project").
WHEREAS, the work to be performed by the Contractor is more particularly set
forth in the Contract Documents for the Project dated , (hereinafter
referred to as "Contract Documents"), the terms and conditions of which are expressly
incorporated herein by reference; and
WHEREAS, the Contractor is required by said Contract Documents to perform the
terms thereof and to furnish a bond for the faithful performance of said Contract
Documents.
NOW, THEREFORE, we, , the undersigned Contractor and
as Surety, a corporation
organized and duly authorized to transact business under the laws of the State of
California, are held and firmly bound unto the Authority in the sum of
DOLLARS, ($ ), said sum being not less
than one hundred percent (100%) of the total amount of the Contract, for which amount
well and truly to be made, we bind ourselves, our heirs, executors and administrators,
successors and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH, that, if the Contractor, his or
its heirs, executors, administrators, successors or assigns, shall in all things stand to and
abide by, and well and truly keep and perform the covenants, conditions and agreements
in the Contract Documents and any alteration thereof made as therein provided, on its
part, to be kept and performed at the time and in the manner therein specified, and in all
respects according to their intent and meaning; and shall faithfully fulfill all obligations
including the one-year guarantee of all materials and workmanship; and shall indemnify
and save harmless the Authority and City, their officers and agents, as stipulated in said
Contract Documents, then this obligation shall become null and void; otherwise it shall be
and remain in full force and effect.
The obligations of Surety hereunder shall continue so long as any obligation of
Contractor remains. Nothing herein shall limit the Authority's rights or the Contractor or
Surety's obligations under the Contract, law or equity, including, but not limited to,
California Code of Civil Procedure section 337.15.
SECTION 00610
PERFORMANCE BOND
-5-
77802 00000\24431586 2 Construction of Mailbox Canopies and Carports Project Contract No HA36610 (March 18. 2018)
DRAFT FOR DISCUSSION
Whenever Contractor shall be, and is declared by the Authority to be, in default
under the Contract Documents, the Surety shall remedy the default pursuant to the
Contract Documents, or shall promptly, at the Authority's option:
(1) Take over and complete the Project in accordance with all terms and
conditions in the Contract Documents; or
(2) Obtain a bid or bids for completing the Project in accordance with all terms
and conditions in the Contract Documents and upon determination by
Surety of the lowest responsive and responsible bidder, arrange for a
Contract between such bidder, the Surety and the Authority, and make
available as work progresses sufficient funds to pay the cost of completion
of the Project, less the balance of the contract price, including other costs
and damages for which Surety may be liable. The term "balance of the
contract price" as used in this paragraph shall mean the total amount
payable to Contractor by the Authority under the Contract and any
modification thereto, less any amount previously paid by the Authority to the
Contractor and any other set offs pursuant to the Contract Documents.
(3)
Permit the Authority to complete the Project in any manner consistent with
local, California and federal law and make available as work progresses
sufficient funds to pay the cost of completion of the Project, less the balance
of the contract price, including other costs and damages for which Surety
may be liable. The term "balance of the contract price" as used in this
paragraph shall mean the total amount payable to Contractor by the
Authority under the Contract and any modification thereto, less any amount
previously paid by the Authority to the Contractor and any other set offs
pursuant to the Contract Documents.
Surety expressly agrees that the Authority may reject any contractor or
subcontractor which may be proposed by Surety in fulfillment of its obligations in the event
of default by the Contractor.
Surety shall not utilize Contractor in completing the Project nor shall Surety accept
a bid from Contractor for completion of the Project if the Authority, when declaring the
Contractor in default, notifies Surety of the Authority's objection to Contractor's further
participation in the completion of the Project.
The Surety, for value received, hereby stipulates and agrees that no change,
extension of time, alteration or addition to the terms of the Contract Documents or to the
Project to be performed thereunder shall in any way affect its obligations on this bond,
and it does hereby waive notice of any such change, extension of time, alteration or
addition to the terms of the Contract Documents or to the Project, including but not limited
to the provisions of sections 2819 and 2845 of the California Civil Code.
SECTION 00610
PERFORMANCE BOND
-6-
77802 00000t24431586 2 Construction of Mailbox Canopies and Carports Project Contract No HA36610 (March 18, 2018)
DRAFT FOR DISCUSSION
IN WITNESS WHEREOF, we have hereunto set our hands and seals this day
of , 20_).
(Corporate Seal)
(Corporate Seal)
Contractor/ Principal
By
Title
Surety
By
Attorney -in -Fact
Signatures of those signing for the Contractor and Surety must be notarized and evidence
of corporate authority attached.
(Attach Attorney -in -Fact Certificate) Title
The rate of premium on this bond is
premium charges, $
(The above must be filled in by corporate attorney.)
THIS IS A REQUIRED FORM
Any claims under this bond may be addressed to:
(Name and Address of Surety)
(Name and Address of Agent or
Representative for service of
process in California, if different
from above)
(Telephone number of Surety and
Agent or Representative for service
of process in California
per thousand. The total amount of
SECTION 00610
PERFORMANCE BOND
-7-
77802 00000t24431586 2 Construction of Mailbox Canopies and Carports Project Contract No HA36610 (March 18. 2018)
DRAFT FOR DISCUSSION
ACKNOWLEDGMENT
A notary public or other officer completing this certificate verifies only the identity of
the individual who signed the document to which this certificate is attached, and not
the truthfulness, accuracy, or validity of that document.
State of California )
County of )
On before me,
(insert name and title of the officer)
personally appeared, who proved to me on the basis
of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within
instrument and acknowledged to me that he/she/they executed the same in his/her/their
authorized capacity(ies), and that by hi/her/their signature(s) on the instrument the person(s),
or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the
foregoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature (Seal)
NOTE: A copy of the Power -of -Attorney authorizing the person signing on behalf of the
Surety to do so must be attached hereto.
SECTION 00610
PERFORMANCE BOND
-8-
77802 00000 \ 24431586 2 Construction of Mailbox Canopies and Carports Project Contract No. I1A36610 (March 18, 2018)
DRAFT FOR DISCUSSION
PAYMENT BOND
KNOW ALL MEN BY THESE PRESENTS That
WHEREAS, the Palm Desert Housing Authority (hereinafter designated as the
"Authority"), by action taken or a resolution passed , 20 has awarded
to hereinafter designated as the "Principal," a contract for the work
described as follows:
(the "Project"); and
WHEREAS, the work to be performed by the Principal is more particularly set forth
in the Contract Documents for the Project dated ("Contract
Documents"), the terms and conditions of which are expressly incorporated by reference;
and
WHEREAS, said Principal is required to furnish a bond in connection with said
contract; providing that if said Principal or any of its Subcontractors shall fail to pay for
any materials, provisions, provender, equipment, or other supplies used in, upon, for or
about the performance of the work contracted to be done, or for any work or labor done
thereon of any kind, or for amounts due under the Unemployment Insurance Code or for
any amounts required to be deducted, withheld, and paid over to the Employment
Development Department from the wages of employees of said Principal and its
Subcontractors with respect to such work or labor the Surety on this bond will pay for the
same to the extent hereinafter set forth.
NOW THEREFORE, we, the Principal and as
Surety, are held and firmly bound unto the Authority in the penal sum of
Dollars ($ ) lawful money of the
United States of America, for the payment of which sum well and truly to be made, we
bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and
severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH that if said Principal, his or its
subcontractors, heirs, executors, administrators, successors or assigns, shall fail to pay
any of the persons named in Section 9100 of the Civil Code, fail to pay for any materials,
provisions or other supplies, used in, upon, for or about the performance of the work
contracted to be done, or for any work or labor thereon of any kind, or amounts due under
the Unemployment Insurance Code with respect to work or labor performed under the
contract, or for any amounts required to be deducted, withheld, and paid over to the
Employment Development Department or Franchise Tax Board from the wages of
employees of the contractor and his subcontractors pursuant to Section 18663 of the
Revenue and Taxation Code, with respect to such work and labor the Surety or Sureties
will pay for the same, in an amount not exceeding the sum herein above specified.
This bond shall inure to the benefit of any of the persons named in Section 9100
of the Civil Code so as to give a right of action to such persons or their assigns in any suit
brought upon this bond.
SECTION 00610
PERFORMANCE BOND
-9-
77802 00000124431586 2 Construction of Mailbox Canopies and Carports Project Contract No HA36610 (March 18, 2018)
DRAFT FOR DISCUSSION
It is further stipulated and agreed that the Surety on this bond shall not be
exonerated or released from the obligation of this bond by any change, extension of time
for performance, addition, alteration or modification in, to, or of any contract, plans,
specifications, or agreement pertaining or relating to any scheme or work of improvement
herein above described, or pertaining or relating to the furnishing of labor, materials, or
equipment therefore, nor by any change or modification of any terms of payment or
extension of the time for any payment pertaining or relating to any scheme or work of
improvement herein above described, nor by any rescission or attempted rescission of
the contract, agreement or bond, nor by any conditions precedent or subsequent in the
bond attempting to limit the right of recovery of claimants otherwise entitled to recover
under any such contract or agreement or under the bond, nor by any fraud practiced by
any person other than the claimant seeking to recover on the bond and that this bond be
construed most strongly against the Surety and in favor of all persons for whose benefit
such bond is given, and under no circumstances shall Surety be released from liability to
those for whose benefit such bond has been given, by reason of any breach of contract
between the owner or Authority and original contractor or on the part of any obligee
named in such bond, but the sole conditions of recovery shall be that claimant is a person
described in Section 9100 of the Civil Code, and has not been paid the full amount of his
claim and that Surety does hereby waive notice of any such change, extension of time,
addition, alteration or modification herein mentioned and the provisions of sections 2819
and 2845 of the California Civil Code.
IN WITNESS WHEREOF, we have hereunto set our hands and seals this
day of , 20.
(Corporate Seal)
(Corporate Seal)
Contractor/ Principal
By
Title
Surety
By
Title
Attorney -in -Fact
Signatures of those signing for the Contractor and Surety must be notified and evidence
of corporate authority attached. A Power -of -Attorney authorizing the person signing on
behalf of the Surety to do so much be attached hereto.
SECTION 00610
PERFORMANCE BOND
-10-
77802 00000124431586 2 Construction of Mailbox Canopies and Carports Project Contract No. HA36610 (March 18, 2018)
DRAFT FOR DISCUSSION
ACKNOWLEDGMENT
A notary public or other officer completing this certificate verifies only the identity of the
individual who signed the document to which this certificate is attached, and not the
truthfulness, accuracy, or validity of that document.
State of California )
County of )
On before me,
(insert name and title of the officer) personally appeared,
who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s)
is/are subscribed to the within instrument and acknowledged to me that he/she/they executed
the same in his/her/their authorized capacity(ies), and that by hi/her/their signature(s) on the
instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the
instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the
foregoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature (Seal)
NOTE: A copy of the Power -of -Attorney authorizing the person signing on behalf of the
Surety to do so must be attached hereto.
SECTION 00610
PERFORMANCE BOND
-11-
77802 00000t24431586 2 Construction of Mailbox Canopies and Carports Project Contract No HA36610 (March 18, 2018)