HomeMy WebLinkAboutHA37350 Stair Top Handrail Rplcmnt - One Quail Place 821-19MEETING DATE: PREPARED BY: REQUEST: Recommendation STAFF REPORT PALM DESERT HOUSING AUTHORITY PUBLIC WORKS DEPARTMENT November 15, 2018 Cora L. Gaugush, Management Specialist II Award Contract HA37350 to S & T Contractors Service Inc. dba Service Master Restoration by S&S, of Santa Clarita, California, in the amount of $164,616.00, for the Stair Top Handrail Replacement at One Quail Place Apartments (Project 821-19) By Minute Motion: 1. Pursuant Municipal Code Section 3.30.160(i) (Best Interest of City), award Contract HA37350 to S & T Contractors Service Inc., dba Service Master Restoration by S&S of Santa Clarita, California, in the amount of $164,616.00, for the Stair Top Handrail Replacement at One Quail Place Apartments (Project 821-19); 2. Authorize the Director of Finance to set aside a 10% contingency, in the amount of $16,461.60; 3. Authorize the Executive Director or designee to review and approve written requests for the use of any portion of the contingency toward unforeseen conditions; and 4. Authorize the Executive Director and/or the Chairman to execute the negotiated contract and any documents necessary to facilitate the contract award. Funds are available in the Authority's capital replacement budget for this project. Committee/Commission Recommendation The Housing Commission reviewed this recommendation at its regular meeting of November 14, 2018. An oral report of their action will be presented. November 15, 2018 - Staff Report Stair Top Rail Replacement at One Quail Place Apartments Page 2 of 3 Strategic Plan The Stair Top Handrail Replacement at One Quail Place Apartments is an on -going maintenance activity and, as such, does not contribute directly to the objectives of the Strategic Plan. Background Analysis This project will replace all the stair top handrails at One Quail Place Apartments, with a wooden rail treated with a polyurea coating. The property is owned and maintained by the Palm Desert Housing Authority, and the top handrail has not been replaced since the apartments were constructed in 1983. The top handrail has reached its life expectancy and needs to be replaced. The protective coating will provide UV protection for the wood as well as a textured finish to the handrail. A Notice Inviting Bids was advertised in August of this year and bids were due on October 12, 2018, at which time no responsive bid was received. When no responsive bids were received, staff contacted the contractor that provided samples of the product for the pre - bid meeting, S & T Contractors Services, Inc. dba Service Master Restoration by S&S. The company specializes in this type of coating for a variety of products. They are very familiar with the product and One Quail Place. Additionally, the Housing Authority has previously used this contractor for other repairs/replacement items at this location and has been satisfied with their work. They provided a cost of $38.00 for the top handrail replacement, complete, per linear foot. The complex will need 4,332 linear feet of handrail replaced, for a total of $164,616.00. Pursuant to Municipal Code 3.30.160(i), staff is requesting that the City Council award this contract to S & T Contractors Services, Inc. dba Service Master Restoration by S&S, in the best interest of the City. Fiscal Analysis The fiscal impact of this contract is the cost of the contract itself in the amount of $164,616, plus 10% contingency in the amount of $16,461.60, (if used for unforeseen conditions) which will be paid from the Authority's capital replacement budget. LEGAL REVIEW DEPT. REVIEW W. City Attorney r(' es Tom Garcia, P.E. Director of Public Works FINANCIAL REVIEW Director of Finance CITY MANAGER Lauri Aylaian City Manager November 15, 2018 - Staff Report Stair Top Rail Replacement at One Quail Place Apartments Page 3 of 3 APPLICANT: S & T Contractors Services, Inc. dba Service Master Restoration by S&S 21163 Centre Pointe Parkway Santa Clarita, California 91350 ATTACHMENTS: Contract HA37350 Proposal Payment Bond Performance Bond 1/ L3Y hOUSO AUTN ON 6 VERIFIED BY: Original on rite with City erk's Offic MEs: 1- Irnik., [ ( , N h *i WeigP_r: ard Ti an 40ES : ALOI e,� Contract No. HA37350 CONTRACT THIS CONTRACT is made this 15th day of November, 2018, in the County of Riverside, State of California, by and between the Palm Desert Housing Authority, hereinafter called Authority, and S & T Contractors Service, Inc. dba Service Master Restoration by S&S, hereinafter called Contractor. The Authority and the Contractor for the considerations stated herein agree as follows: ARTICLE 1. SCOPE OF WORK. The Contractor shall perform all Work within the time stipulated in the Contract and shall provide all labor, materials, equipment, tools, utility services, and transportation to complete all of the Work required in strict compliance with the Contract Documents as specified in Article 5 below for the following Project: Stair Top Rail Replacement at One Quail Place Apartments Project 821-19 Contract No. HA37350 The Contractor and its surety shall be liable to the Authority for any damages arising as a result of the Contractor's failure to comply with this obligation. ARTICLE 2. TIME FOR COMPLETION. Time is of the essence in the performance of the Work. The Work shall be commenced on the date stated in the Authority's Notice to Proceed. The Contractor shall complete all Work required by the Contract Documents within 90 calendar days from the commencement date stated in the Notice to Proceed, hereinafter the Contract Time. By its signature hereunder, Contractor agrees the Contract Time for completion set forth above is adequate and reasonable to complete the Work. ARTICLE 3. CONTRACT PRICE. The Authority shall pay to the Contractor as full compensation for the performance of the Contract, subject to any additions or deductions as provided in the Contract Documents, and including all applicable taxes and costs, the sum of One Hundred Sixtv-Four Thousand Six Hundred Sixteen and 00/100 Dollars ($164,616.00), hereinafter the Contract Price. Payment shall be made as set forth in the General Conditions. ARTICLE 4. LIQUIDATED DAMAGES. The Contractor acknowledges that the Authority will sustain actual damages for each and every day completion of the Project is delayed beyond the Contract Time. Because of the nature of the Project, it would be impracticable or extremely difficult to determine the Authority's actual damages. Accordingly, as provided in Government Code section 53069.85, it is agreed that the Contractor will pay the Authority the sum of $350.00 for each and every calendar day of delay in completing the Work beyond the time prescribed in the Contract Documents for finishing the Work, as Liquidated Damages and not as a penalty or forfeiture. In the event the Liquidated Damages are not paid, the Contractor agrees the Authority may deduct that amount from any money due or that may become due the Contractor under the Contract. This Article 1 77802.00000\24431586.2 Contract No. HA37350 does not affect the Authority's rights to other damages or remedies specified in the Contract Documents or allowed by law. Should Contractor be inexcusably delayed in the performance of the Work, Authority may deduct Liquidated Damages based on its estimate of when Contractor will achieve Final Completion or other milestones. Authority need not wait until Final Completion to withhold Liquidated Damages from Contractor. Liquidated Damages are not a penalty but an agreed upon estimate of the actual damages that would be sustained by the Authority for delay, including but not limited to loss of revenue, inconvenience to the Authority and the public, and increased Project administration expenses, such as extra inspection, construction management, staff time and architectural and engineering expenses. Liquidated Damages do not include actual damages the Authority incurs on account of claims by third parties against the Authority on account of any delay. Should money due or to become due to the Contractor be insufficient to cover Liquidated Damages or other offsets due, then Contractor forthwith shall pay the remainder of the assessed liquidated damages to Authority. ARTICLE 5. COMPONENT PARTS OF THE CONTRACT. The "Contract Documents" include the following documents, each of which is incorporated into this Contract by reference: • Notice Inviting Bids • Instructions to Bidders • Bid Form • Contractor's Certificate Regarding Workers' Compensation • Bid Bond • Non -Collusion Declaration form • Contractor Information and Experience Form • List of Subcontractors Form • Iran Contracting Act Certification • Contract • Performance Bond • Payment Bond • General Conditions • Special Conditions • Technical Specifications (including Appendices) • Addenda • Permit Requirements • Approved and fully executed change orders 2 77802.00000\24431586.2 Contract No. HA37350 • Standard Specifications for Public Works Construction (Greenbook), Latest Edition, except Sections 1-9 • Any other documents contained in or incorporated into the Contract The Contactor shall complete the Work in strict accordance with all of the Contract Documents. All of the Contract Documents are intended to be complementary. Work required by one of the Contract Documents and not by others shall be done as if required by all. This Contract shall supersede any prior agreement of the parties. ARTICLE 6. PROVISIONS REQUIRED BY LAW. Each and every provision of law required to be included in these Contract Documents shall be deemed to be included in these Contract Documents. The Contractor shall comply with all requirements of applicable federal, state and local laws, rules and regulations, including but not limited to, the provisions of the California Labor Code and Public Contract Code applicable to this Project. If the Work involves federal funds, the Contractor and all its subcontractors shall comply with all requirements set forth in the attached Federal Requirements. ARTICLE 7. INDEMNIFICATION. Contractor shall provide indemnification as set forth in the General Conditions. ARTICLE 8. PREVAILING WAGES. Contractor shall be required to pay the prevailing rate of wages in accordance with the Labor Code which such rates may be obtained online at http//www.dir.ca.gov/dlsr. and which must be posted at the job site. ARTICLE 9. NOTIFICATION TO AUTHORITY. Contractor acknowledges that the Authority provides forty-eight (48) hours -notice to residents in advance of the start of any Work that is to occur at any residential unit. Contractor shall provide sufficient notice to the Authority before beginning any such Work so that the Authority may provide timely notice to residents. The Authority shall be given at least 48 hours -notice prior to the creation of any condition affecting pedestrian paths of travel. Contractor shall continuously inform Authority of the progress of the Work or of any impacts of the Work upon residential units or facilities. ARTICLE 10. LOCAL LICENSES AND PERMITS. Unless the Contract Documents state otherwise, Contractor shall be responsible for securing City of Palm Desert business license(s), building permits, and any other licenses or permits necessary to perform the Work. 3 77802.00000\24431586.2 Contract No. HA37350 IN WITNESS WHEREOF, this Contract has been duly executed by the above - named parties, on the day and year above written. [NAME OF CONTRACTOR] PALM DESERT HOUSING AUTHORITY By: By: Signature Signature Name and Title: License No. DIR Registration No. 4 Name and Title: Attest: Rachelle Klassen, Secretary Approved as to Form: Robert W Hargraves, City Attorney 77802.0 000\24431586.2 A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document. State of California SS. County of Riverside On , 20 before me, , a Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument. I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct. WITNESS my hand and official seal. Signature 5 77802.00000\24431586.2 A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document. State of California County of Riverside On , 20 before me, , a Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument. I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct. WITNESS my hand and official seal. Signature END OF CONTRACT 6 77802.00000\24431586.2 PERFORMANCE BOND KNOW ALL PERSONS BY THESE PRESENTS: THAT WHEREAS, the Palm Desert Housing Authority (hereinafter referred to as "Authority") has awarded to S & T Contractors Service, Inc. dba Service Master Restoration by S&S, (hereinafter referred to as the "Contractor") an agreement for Stair Top Rail Replacement at One Quail Place Apartments (Project 821-19) (hereinafter referred to as the "Project"). WHEREAS, the work to be performed by the Contractor is more particularly set forth in the Contract Documents for the Project dated November 15, 2018 (hereinafter referred to as "Contract Documents"), the terms and conditions of which are expressly incorporated herein by reference; and WHEREAS, the Contractor is required by said Contract Documents to perform the terms thereof and to furnish a bond for the faithful performance of said Contract Documents. NOW, THEREFORE, we, S & T Contractors Service, Inc. dba Service Master Restoration by S&S, the undersigned Contractor and as Surety, a corporation organized and duly authorized to transact business under the laws of the State of California, are held and firmly bound unto the Authority in the sum of One Hundred Sixty Four Thousand Six Hundred Sixteen and 00/100 DOLLARS, ($164,616.00), said sum being not less than one hundred percent (100%) of the total amount of the Contract, for which amount well and truly to be made, we bind ourselves, our heirs, executors and administrators, successors and assigns, jointly and severally, firmly by these presents. THE CONDITION OF THIS OBLIGATION IS SUCH, that, if the Contractor, his or its heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions and agreements in the Contract Documents and any alteration thereof made as therein provided, on its part, to be kept and performed at the time and in the manner therein specified, and in all respects according to their intent and meaning; and shall faithfully fulfill all obligations including the one-year guarantee of all materials and workmanship; and shall indemnify and save harmless the Authority and City, their officers and agents, as stipulated in said Contract Documents, then this obligation shall become null and void; otherwise it shall be and remain in full force and effect. The obligations of Surety hereunder shall continue so long as any obligation of Contractor remains. Nothing herein shall limit the Authority's rights or the Contractor or Surety's obligations under the Contract, law or equity, including, but not limited to, California Code of Civil Procedure section 337.15. 1 77802.00000\2443 1586.2 Contract No. HA37350 Whenever Contractor shall be, and is declared by the Authority to be, in default under the Contract Documents, the Surety shall remedy the default pursuant to the Contract Documents, or shall promptly, at the Authority's option: (1) Take over and complete the Project in accordance with all terms and conditions in the Contract Documents; or (2) Obtain a bid or bids for completing the Project in accordance with all terms and conditions in the Contract Documents and upon determination by Surety of the lowest responsive and responsible bidder, arrange for a Contract between such bidder, the Surety and the Authority, and make available as work progresses sufficient funds to pay the cost of completion of the Project, Tess the balance of the contract price, including other costs and damages for which Surety may be liable. The term "balance of the contract price" as used in this paragraph shall mean the total amount payable to Contractor by the Authority under the Contract and any modification thereto, less any amount previously paid by the Authority to the Contractor and any other set offs pursuant to the Contract Documents. (3) Permit the Authority to complete the Project in any manner consistent with local, California and federal law and make available as work progresses sufficient funds to pay the cost of completion of the Project, less the balance of the contract price, including other costs and damages for which Surety may be liable. The term "balance of the contract price" as used in this paragraph shall mean the total amount payable to Contractor by the Authority under the Contract and any modification thereto, less any amount previously paid by the Authority to the Contractor and any other set offs pursuant to the Contract Documents. Surety expressly agrees that the Authority may reject any contractor or subcontractor which may be proposed by Surety in fulfillment of its obligations in the event of default by the Contractor. Surety shall not utilize Contractor in completing the Project nor shall Surety accept a bid from Contractor for completion of the Project if the Authority, when declaring the Contractor in default, notifies Surety of the Authority's objection to Contractor's further participation in the completion of the Project. The Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract Documents or to the Project to be performed thereunder shall in any way affect its obligations on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Contract Documents or to the Project, including but not limited to the provisions of sections 2819 and 2845 of the California Civil Code. 2 77802.00000\24431586.2 Contract No. HA37350 IN WITNESS WHEREOF, we have hereunto set our hands and seals this day of , 20 ). (Corporate Seal) Contractor/ Principal By Title (Corporate Seal) Surety By Attorney -in -Fact Signatures of those signing for the Contractor and Surety must be notarized and evidence of corporate authority attached. (Attach Attomey-in-Fact Certificate) Title The rate of premium on this bond is of premium charges, $ (The above must be filled in by corporate attorney.) THIS IS A REQUIRED FORM Any claims under this bond may be addressed to: (Name and Address of Surety) per thousand. The total amount 3 77802.00000\24431586.2 (Name and Address of Agent or Representative for service of process in California, if different from above) (Telephone number of Surety and Agent or Representative for service of process in California) Contract No. HA37350 4 77802.00000\24431586.2 Contract No. HA37350 ACKNOWLEDGMENT A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document. State of California County of On before me, (insert name and title of the officer) Dersonally appeared who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the oerson(s), or the entity upon behalf of which the person(s) acted, executed the instrument. I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct. WITNESS my hand and official seal. Signature (Seal) NOTE: A copy of the Power -of -Attorney authorizing the person signing on behalf of the Surety to do so must be attached hereto. 5 77802.00000\2443I586.2 PAYMENT BOND KNOW ALL MEN BY THESE PRESENTS That WHEREAS, the Palm Desert Housing Authority (hereinafter designated as the "Authority"), by action taken or a resolution passed November 15, 2018 has awarded to S & T Contractors Service. Inc. dba Service Master Restoration by S&S hereinafter designated as the "Principal," a contract for the work described as follows: Stair Top Handrail Replacement Project (821-19) (the "Project"); and WHEREAS, the work to be performed by the Principal is more particularly set forth in the Contract Documents for the Project dated November 15, 2018 ("Contract Documents"), the terms and conditions of which are expressly incorporated by reference; and WHEREAS, said Principal is required to furnish a bond in connection with said contract; providing that if said Principal or any of its Subcontractors shall fail to pay for any materials, provisions, provender, equipment, or other supplies used in, upon, for or about the performance of the work contracted to be done, or for any work or labor done thereon of any kind, or for amounts due under the Unemployment Insurance Code or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department from the wages of employees of said Principal and its Subcontractors with respect to such work or labor the Surety on this bond will pay for the same to the extent hereinafter set forth. NOW THEREFORE, we, the Principal and as Surety, are held and firmly bound unto the Authority in the penal sum of One Hundred Sixtv-Four Thousand Six Hundred Sixteen and 00/100 Dollars ($164,616.00) lawful money of the United States of America, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents. THE CONDITION OF THIS OBLIGATION IS SUCH that if said Principal, his or its subcontractors, heirs, executors, administrators, successors or assigns, shall fail to pay any of the persons named in Section 9100 of the Civil Code, fail to pay for any materials, provisions or other supplies, used in, upon, for or about the performance of the work contracted to be done, or for any work or labor thereon of any kind, or amounts due under the Unemployment Insurance Code with respect to work or labor performed under the contract, or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department or Franchise Tax Board from the wages of employees of the contractor and his subcontractors pursuant to Section 18663 of the Revenue and Taxation Code, with respect to such work and Tabor the Surety or Sureties will pay for the same, in an amount not exceeding the sum herein above specified, and also, in case suit is brought upon this bond, Surety or Sureties shall pay all litigation expenses incurred by the Authority in such suit, including reasonable attomeys' fees, court costs, expert witness fees and investigation expenses. This bond shall inure to the benefit of any of the persons named in Section 9100 of the Civil Code so as to give a right of action to such persons or their assigns in any suit brought upon this bond. 1 77802.00000\24431586.2 Contract No. HA37350 It is further stipulated and agreed that the Surety on this bond shall not be exonerated or released from the obligation of this bond by any change, extension of time for performance, addition, alteration or modification in, to, or of any contract, plans, specifications, or agreement pertaining or relating to any scheme or work of improvement herein above described, or pertaining or relating to the furnishing of labor, materials, or equipment therefore, nor by any change or modification of any terms of payment or extension of the time for any payment pertaining or relating to any scheme or work of improvement herein above described, nor by any rescission or attempted rescission of the contract, agreement or bond, nor by any conditions precedent or subsequent in the bond attempting to limit the right of recovery of claimants otherwise entitled to recover under any such contract or agreement or under the bond, nor by any fraud practiced by any person other than the claimant seeking to recover on the bond and that this bond be construed most strongly against the Surety and in favor of all persons for whose benefit such bond is given, and under no circumstances shall Surety be released from liability to those for whose benefit such bond has been given, by reason of any breach of contract between the owner or Authority and original contractor or on the part of any obligee named in such bond, but the sole conditions of recovery shall be that claimant is a person described in Section 9100 of the Civil Code, and has not been paid the full amount of his claim and that Surety does hereby waive notice of any such change, extension of time, addition, alteration or modification herein mentioned and the provisions of sections 2819 and 2845 of the Califomia Civil Code. IN WITNESS WHEREOF, we have hereunto set our hands and seals this day of , 20 (Corporate Seal) (Corporate Seal) Contractor/ Principal By Title Surety By Title Attorney -in -Fact Signatures of those signing for the Contractor and Surety must be notified and evidence of corporate authority attached. A Power -of -Attorney authorizing the person signing on behalf of the Surety to do so much be attached hereto. 2 77802.00000\24431586.2 Contract No. HA37350 ACKNOWLEDGMENT A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document. State of Califomia County of ) On before me, (insert name and title of the officer) Personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same iri his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument thel Person(s), or the entity upon behalf of which the person(s) acted, executed the instrument. I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing Paragraph is true and correct. WITNESS my hand and official seal. Signature (Seal) NOTE: A copy of the Power-of-Attomey authorizing the person signing on behalf of the Surety to do so must be attached hereto. 3 77802.00000\24431586.2 S&T Contractor's Services, Inc. 21163 Centre Point Parkway Santa Clarita, Ca 91350 Phone (818) 335-3176 or (661) 388-1003 Tax ID# 26-2552975 Contractor's License #950263 November 5, 2018 Property: One Quail Place Apartments 72600 Fred Waring Drive Palm Desert, Ca 92260 ESTIMATE We propose herby to furnish material and labor, complete in accordance with estimate specifications. All work to be completed in a substantial workmanlike manner according to specifications submitted, per standard practices. Any alteration or deviation from above specifications will become an extra charge over and above the estimate. Any hidden damage to be addressed separately. PREVAILING WAGE APPLIES Remove existing handrail - Provide and install 4332 linear feet of poplar handrail, custom coated and treated with Polyurea and finished UV Coating. Color to be determined. $38.00/LF x 4332 TOTAL: $164,616.00 Thank you. S&T Contractor's Services, Inc. PARKVIEW 0 ( 7 4300 4ipo 14206 : 4209 4705 ' 4207 4204 4202 4203 - 4201 #S 6 - '142%.! �o ,, aA`osl Jg 370q „ 1� � 0 ..$i:..1 POOL •'/ ] 1Ye� — #4 ems_ jaw 11008 .!. ±l= i lag ai-;s,-Tx 1000 1006 I wee \� loos ,.7 02 1004 1 1002 1003 i4r,001 be- 900 600 $` ( POOL _w ( i-o`� l a III« I ' :osr •\ 1 \$$?.- J 06 «.v 8o0V� 700 990909 1 706 1 709 0 I 907 i 706 1 707 ;,119W 1 102 704 1 702 1 E 903 901 703 ! 701 f -ri r _• f7s ! T 1 W 1]5�1 1703 J"' 1600 SITE MAP f 300 .000 VS 1ST FL - EVEN f.S2NO FL 7E0015 70c PAGE 3 FRED WARING DR i COURTS itiL 1900 IT' 1910 1 1912 1914 1911 0 1 1909 1911 1913 1916 1 ay�19M I f906 11 19 12 ' 179T 1.1909 1903 9p/ �y/�6yp —p1fl.laur1 ilia 1nt6 i`211iT2/u ¢116I 9Al a 1 12109 In11 2113 12113 K f IKQG 12/09 12106 2104 in03 p 12107 2106I 2103 �21011 u m� I Im ' '� Y� O pJp m V e 0 1 S One Quail Place Apartments 72-600 Fred Waring Drive Palm Desert, CA 92260 ▪ Water Shut -Off Valve Locations • Electricity Shut -Off Valve Locations Gas Shut -Off Valve Locations ▪ Interior Fire Extinguisher Locations TO PARKV1EW AVE ODD VS 1ST FL - EVEN w S 2ND FL 9LDGS WITH LIFE SAFETY SPRINKLERS ON THE DONES= WATER SYSTEM n.{ � 2700 di 2400 12710 2712 1 7714 2715 4,.1, 1 2709 2711 2713 2715 5 «l5= 07 7 6 2709 ( 27042 Y702702 ;76s 2/01 I 0 ^l. ti«I:'ti 30 TO FRED WARING O R 1 0 T PAGE4 ▪ Interior Fire Extinguisher Locations: In each Clubhouse adjacent to stairwell 1 upstairs & 1 downstairs. ▪ In each Laundry Room above utility sink 1 per Laundry Room. . In each Apartment in Hall Closet 1 per apartment. 77802.00000\24431586.2 SITE MAP -1-