HomeMy WebLinkAboutR21180-B - CO 1 - TEMCO - Country Club Village Sewer & Street ImprovementsPALM DESERT REDEVELOPMENT AGENCY
OFFICE OF THE EXECUTIVE DIRECTOR
STAFF REPORT
REQUEST: CHANGE ORDER NO. 1 FOR COUNTRY CLUB VILLAGE SEWER
AND STREET IMPROVEMENTS (CONTRACT NO. R21180B)
CONTRACTOR: TEMCO
24400 WALNUT STREET, C-100
NEWHALL, CA 91321
SUBMITTED BY: PAT CONLON, SPECIAL PROJECTS ADMINISTRATOR
DATE: JULY 8, 2004
CONTENTS: CHANGE ORDER NO. 1
Recommendation:
By Minute Motion, that the Agency Board:
1. Approve Change Order No. 1 in the amount of $79,948.00 for
additional work required by TEMCO on the installation of the street and
sewer system; and
2. Authorize the Director of Finance to transfer $79,948.00 from the
project contingency to the base contract (Account No. 853-4598-433-
4001).
Discussion:
Due to a discrepancy in the CVWD as -built plans, the existing sewer line located on
Merle Drive is approximately 4 feet deeper than what is shown on the bid specifications.
This condition causes additional work for Temco. Instead of a 6-foot deep excavation
for the 19 sewer laterals installed on this existing sewer line, the contractor must now
excavate down to 10 feet in depth. This deeper sewer line also requires constructing 2
special drop manhole assemblies to tie the new sewer system into the deeper existing
Merle Drive sewer line.
The Change Order price breaks down as follows:
(19) Deeper sewer laterals @ $3,716.00 each $70,604.00
(2) Drop manhole assemblies @ $4,672.00 each 9.344.00
Total $79,948.00
GACityMgr\Amy HughesMord Res\Conlon\Staff Reports\71004CCSewer-TemcoChangeOrderNO.l.doc
Staff Report
Change Order No. 1 for Country Club Sewer and Street Improvements
(Contract R2118013)
July 10, 2004
Page 2 of 2
Funds are available in the project contingency to cover the cost of this additional work.
Please contact me with any questions.
Submitted by:
Pat Conlon
Spe-;ial Projects Administrator
ah
Approval:
Dave Yri en
Directo f Redevelopment
,Jt6to McCarthy
ACNI Redevelops nt
alle --___�
Paul S. Gibson
Director of Finance
Carlos Ort a
Executive Director/City Manager
GAQtyMgr\Amy Hughes\Word Files\Conlon\Staff Reports\71004CCsewer-TemcoChangeOrderNO.1.doc
JUN 17 2004 3:37PM HP LRSERJET 3200
12/2112002 20:01 8316302045 FINE GRADE
p.3
PAGE 02
TEMCO
24W WWmt SLX-uw
N�wh�M, CA !! as
Phom: 41W3412.4239
FOX.0 Yli-367-760
Can mdm% WON" & A-313571
Suns 17, 211104
The Kbtb Cvmpenl w
73-733 FW W "m OM m
pah>n Desert, CA M00-MM
IM Country Club Sealer
ATM Bob Nabr, wr, CvnsWudim Maneoer
Per llow' MQOWIIi T how the falioWWM proposals.
Our price br cmwb'uctlno the drop minntodw an the =dsdn0 sewer Ones Is $ 467LOO
per each.
Our price to hook up the deeper laterals on Marie Dr. In $ 30,116.Od wO or �
70A04.00 for the 14 laterals.
Very tmly yours.
Received Jun-17-04 03:51pm From- To -PALM DESERT CITY CLE Page 03
PALL DESERT REDEVELOPMENT AGENCY
CONSTRUCTION CHANGE ORDER
Contract Purpose:
Contractor's Name:
Country Club Village Sewer & Street Improvement
Temco
Contract # / P.O. #
Change Order No.
Contingency:
s Account No.
Project No.
R21180B I 11397
1
YES x + NO
853-4598-433-4001
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES DECREASE INCREASE
(Supplemental Plans and Specifications Attached) In Contract Price In Contract Price
(19) Sewer laterals at greater depth than shown on plans and
(2) Special drop manhole assemblies $79,948.00
TOTALS: I
NET CHANGE IN CONTRACT PRICE: $79,948.00
JUSTIFICATION:
TOTAL BUDGET FOR PROJECT: + CONTINGENCY:
Less: Expend. & Encumb. To Date: - Amount Approved by Council: + 114,214.00
Less: This Change Order Amount: - Less: Prior Change Order(s): - -0-
BALANCE OF BUDGET Less: This Change Order: - 79,948.00
REMAINING FOR PROJECT: - Balance Remaining of Contingency: 34,266.00
The amount of the Contract will be (Decreased) Increased by the Sum of: Seventv-nine Thousand Nine Hundred Fortv-
eiaht and NO/100 Dollars ($ 79,498.00 ).
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have
required signatures as per the purchase resolution.
1. REQUESTED BY:
EXECUTIVE DIRECTOR
2. ACCEPTED BY:
CONTRACTOR
3. CERTIFIED
FUNDS AVAILABLE: 4. APPROVED BY:
FINANCE DIRECTOR ROBERT A. SPIEGEL, CHAIRMAN Date Approved
NOTE: No payments will be made prior to Exec. Dir. and Agency Board approval
SECRETARY Date Approved
...Chng-Ord.RDA
PALM DESERT REDEVELOPMENT AGENCY Contract # / P.O. # R21180B I 11397
CONSTRUCTION CHANGE ORDER Change Order No. 1
Contingency: YES x I NO
Contract Purpose: Country Club Village Sewer & Street Improvements Account No. I 853-4598-433-4001
Contractor's Name: Temco Project No.
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES DECREASE INCREASE
(Supplemental Plans and Specifications Attached) I In Contract Price In Contract Price
(19) Sewer laterals at greater depth than shown on plans and
(2) Special drop manhole assemblies $79,948.00
TOTALS:
NET CHANGE IN CONTRACT PRICE: I $79,948.00
JUSTIFICATION:
TOTAL BUDGET FOR PROJECT: + CONTINGENCY:
Less: Expend. & Encumb. To Date: - Amount Approved by Council: + 114,214.00
Less: This Change Order Amount: - Less: Prior Change Order(s): - -0-
BALANCE OF BUDGET Less: This Change Order: - 79,948.00
REMAINING FOR PROJECT: - Balance Remaining of Contingency: 34,266.00
The amount of the Contract will be (Oecreesed) Increased by the Sum of: Seventv-nine Thousand Nine Hundred Fortv-
eiaht and NO/100 Dollars ($ 79,498.00 ).
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have
required signatures as per the purchase resolution.
1. REQUESTED BY: 2. ACCEPTED BY:
EXECUTIVE DIRECTOR CONTRACTOR
3. CERTIFIED
FUNDS AVAILABLE: 4. APPROVED BY:
FINANCE DIRECTOR ROBERT A. SPIEGEL, CHAIRMAN Date Approved
NOTE: No payments will be made prior to Exec. Dir. and Agency Board approval
SECRETARY Date Approved
Chng-Ord.RDA
PALL DESERT REDEVELOPMENT AGENCY Contract # / P.O. # R21180B I 11397
CONSTRUCTION CHANGE ORDER Change Order No. 1
Contingency: YES x I NO
Contract Purpose: Country Club Village Sewer & Street Improvements Account No. 853-4598-433-4001
Contractor's Name: Temco Project No.
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES DECREASE INCREASE
(Supplemental Plans and Specifications Attached) In Contract Price In Contract Price
(19) Sewer laterals at greater depth than shown on plans and
(2) Special drop manhole assemblies $79,948.00
JUSTIFICATION:
TOTAL BUDGET FOR PROJECT:
Less: Expend. & Encumb. To Date:
Less: This Change Order Amount:
BALANCE OF BUDGET
REMAINING FOR PROJECT:
TOTALS:
NET CHANGE IN CONTRACT PRICE: $79,948.00
+ CONTINGENCY:
Amount Approved by Council: + 114,214.00
Less: Prior Change Order(s): - -0-
Less: This Change Order: - 79,948.00
Balance Remaining of Contingency: 34,266.00
The amount of the Contract will be (Decreased) Increased by the Sum of: Seventv-nine Thousand Nine Hundred Forty-
eiaht and NO/100 Dollars ($ 79,498.00 ).
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have
required signatures as per the purchase resolution.
1. REQUESTED BY:
EXECUTIVE DIRECTOR
2. ACCEPTED BY:
CONTRACTOR
3. CERTIFIED
FUNDS AVAILABLE: 4. APPROVED BY:
FINANCE DIRECTOR ROBERT A. SPIEGEL, CHAIRMAN Date Approved
NOTE: No payments will be made prior to Exec. Dir. and Agency Board approval
SECRETARY Date Approved
...Chng-Ord,RDA