PALM DESERT REDEVELOPMENT AGENCY
STAFF REPORT
REQUEST: APPROVE CONTRACT AMENDMENTS NOS. 1 AND 2 TO
HARRIS & ASSOCIATES (CONTRACT NO. R22810) FOR
ADDITIONAL CONSTRUCTION MANAGEMENT SERVICES
ASSOCIATED WITH THE CONSTRUCTION OF A NEW VISITOR
INFORMATION CENTER AT ENTRADA DEL PASEO
SUBMITTED BY: LAURI AYLAIAN, REDEVELOPMENT MANAGER
CONTRACTOR: HARRIS & ASSOCIATES
74-333 HIGHWAY 111, STE. 101
PALM DESERT, CA 92260
DATE: JUNE 23, 2005
CONTENTS: CONTRACT AMENDMENTS NOS. 1 AND 2
Recommendation:
By Minute Motion, that the Agency Board:
Approve Contract Amendments Nos. 1 and 2 in a total amount not -to -
exceed $24,005 to Harris & Associates of Palm Desert, California (Contract
No. R22810) for provision of additional construction management services
and for a six -week extension of the contract duration coincident with the
extension of the construction contract; and
2. Authorize Finance Director to move $9,828 from contingency to base for
these contract amendments.
The remaining $14,177 necessary for these contract amendments is available
in Account No. 850-4358-433-4001.
Discussion:
On 27 May 2004, the Redevelopment Agency Board awarded a contract to Harris &
Associates for provision of construction management services for the construction of the
new Visitor Information Center at the Entrada del Paseo project. The construction is
approximately 75% complete and Harris & Associates has been performing the required
services in a satisfactory manner.
Staff Report
Approve Contract Amendments Nos. 1 and 2 to Harris & Associates Contract No. R22810
Page 2 of 2
June 23, 2005
During the course of construction of the new building, several changes have been
necessitated which have impacted work activities on the contractor's critical path. This
impact has entitled the construction contractor to additional time for completion of
construction. Under separate cover, the Agency Board is being asked to consider and
approve change orders that will extend the construction completion deadline to 27 July
2005.
Simultaneously, the scope of the construction contractor's work has been increased to
incorporate additional work that was originally envisioned to be performed by separate
contractors. Agency staff has directed the construction manager to perform additional
professional services in the coordination, oversight and management of this additional
construction work.
As a result of the increased scope of work and increased contract duration, the
construction management contract warrants modification to compensate for the
additional professional services required. Contract Amendment No. 1, in the amount of
$9,500, provides compensation for additional services associated with the increase in
scope. These services include construction management for the landscape and exterior
lighting; the furnishing, fixtures and equipment; and the monument signage for the
project. Contract Amendment No. 2, in an amount not -to -exceed $14,505, provides
compensation the extended contract duration. This contract amendment anticipates
that the professional services of Harris & Associates will be required through 15 August
2005.
Agency staff recommends approval of the subject contract amendments in order to
facilitate the timely completion of the new Visitor Information Center.
Submitted by:
uri Aylaiar
Redevelopment Manager
mh
Ap oval:
J tiri McCarthy, ACM Red elopment
Carlos L. Ortega,;Kecutive Director
Department Head:
Daveen
Direc Redevelopment/Housing
Paul S. Gibson, Director of Finance
GARDAWaria Hunt\WPDATA\AYLAIAMSTFRPTS\062305contractamndsharTisassocs.doc
PRIM DESERT REDEVELOPMENT AGENCY Contract # / P.O. # R22810 I 11468
CONTRACT AMENDMENT Change Order No. 1
Contingency: YES X I NO
Contract Purpose: Visitor Information Center Contract Management Account No. 850-4358-433-4001
Contractor's Name: Harris & Associates Project No.
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES DECREASE INCREASE
(Supplemental Plans and Specifications Attached) In Contract Price In Contract Price
Additional Contract Management services as outlined in letter
from Ms. Aylaian of the Palm Desert Redevelopment Agency
to Mr. Herrera of Harris & Associates dated June 1, 2005. $9,500.00
TOTALS:
NET CHANGE IN CONTRACT PRICE: $9,500.00
JUSTIFICATION:
TOTAL BUDGET FOR PROJECT: + CONTINGENCY:
i
Less: Expend. & Encumb. To Date: - Amount Approved by Council: + 9,828.00
Less: This Change Order Amount: - Less: Prior Change Order(s): - 0.00
BALANCE OF BUDGET Less: This Change Order: - 9,500.00
REMAINING FOR PROJECT: - Balance Remaining of Contingency: 328.00
The amount of the Contract will be Increased by the Sum of: Nine Thousand Five Hundred and NO/100
Dollars ($ 9,500.00 ).
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have
required signatures as per the purchase resolution.
1. REQUESTED BY: 2. ACCEPTED BY:
EXECUTIVE D CTOR (CONTRACTOR ei(,/Q L-/ a�
3. CERTIFIED
FUNDS AVAILABLE: 4. APPROVED BY: 6/23/05
FINANCE DIRECTOR BUFORD A. CRITES, CHAIRMAN Date Approved
NOTE: No payments will be made prior to Exec. Dir. and Agency Board approval 6/23/05
SECRETARY Date Approved
Amend -RDA
PAZM DESERT REDEVELOPMENT AGENCY Contract # / P.O. # I R22810 I 11468
CONTRACT AMENDMENT Change Order No. 1
Contingency: YES X I NO
Contract Purpose: Visitor Information Center Contract Management Account No. 850-4358-433-4001
Contractor's Name: Harris & Associates Project No.
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES DECREASE INCREASE
(Supplemental Plans and Specifications Attached) In Contract Price In Contract Price
Additional Contract Management services as outlined in letter
from Ms. Aylaian of the Palm Desert Redevelopment Agency
to Mr. Herrera of Harris & Associates dated June 1, 2005. $9,500.00
TOTALS:
NET CHANGE IN CONTRACT PRICE: $9,500.00
JUSTIFICATION:
TOTAL BUDGET FOR PROJECT: + CONTINGENCY:
Less: Expend. & Encumb. To Date: - Amount Approved by Council: + 9,828.00
Less: This Change Order Amount: - Less: Prior Change Order(s): - 0.00
BALANCE OF BUDGET Less: This Change Order: - 9,500.00
REMAINING FOR PROJECT: - Balance Remaining of Contingency: 328.00
The amount of the Contract will be (Beereased) Increased by the Sum of: Nine Thousand Five Hundred and NO/100
Dollars ($ 9,500.00 ).
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have
required signatures as per the purchase resolution.
1. REQUESTED BY: 2. ACCEPTED BY:
EXEC TIV (RECTOR dONTRACTOR
3. CERTIFIED
FUNDS AVAILABLE: 4. APPROVED BY: 6/23/05
FINANCE DIRECTOR BUFORD A. CRITES, CHAIRMAN Date Approved
NOTE: No payments will be made prior to Exec. Dir. and Agency Board approval 6/23/05
SECRETARY Date Approved
Amend -RDA
PAIM DESERT REDEVELOPMENT AGENCY Contract # / P.O. # I R22810 I 11468
CONTRACT AMENDMENT Change Order No. I 1
Contingency: I YES X I NO
Contract Purpose: Visitor Information Center Contract Management Account No. I 850-4358-433-4001
Contractor's Name: Harris & Associates Project No.
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES DECREASE INCREASE
(Supplemental Plans and Specifications Attached) In Contract Price In Contract Price
Additional Contract Management services as outlined in letter
from Ms. Aylaian of the Palm Desert Redevelopment Agency
to Mr. Herrera of Harris & Associates dated June 1, 2005. $9,500.00
TOTALS:
NET CHANGE IN CONTRACT PRICE: $9,500.00
JUSTIFICATION:
TOTAL BUDGET FOR PROJECT: +
CONTINGENCY:
Less: Expend. & Encumb. To Date: - Amount Approved by Council: + 9,828.00
Less: This Change Order Amount: - Less: Prior Change Order(s): - 0.00
BALANCE OF BUDGET Less: This Change Order: - 9,500.00
REMAINING FOR PROJECT: - Balance Remaining of Contingency: 328.00
The amount of the Contract will be Increased by the Sum of: Nine Thousand Five Hundred and NO/100
Dollars ($ 9,500.00 ).
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have
required signatures as per the purchase resolution.
1. REQUESTED BY: 2. ACCEPTED BY:
EXE IVE ECTOR ONTRACTOR e7L l° �e?
3. CERTIFIED
FUNDS AVAILABLE: 4. APPROVED BY: 6/23/05
FINANCE DIRECTOR BUFORD A. CRITES, CHAIRMAN Date Approved
NOTE: No payments will be made prior to Exec. Dir. and Agency Board approval 6/23/05
SECRETARY Date Approved
.Amend -RDA
Palm Desert Redevelopment Agency
Palm Desert Visitor Center Project
01 Harris & Associates
TRANSMITTAL
NO. 00182
TO:
Lauri Aylaian
DATE: 6/2/2005
Palm Desert Redevelopment Agency
73-510 Fred Waring Drive
REF: Contract Amendment #01
Palm Desert, CA 92260-2578
Additional Services
Phone:760.346.0611 Fax:760.341.6372
WE ARE SENDING:
SUBMITTED,FOR:
❑
Shoo Drawings
M ADproval
❑ ADDroved as Submitted ❑ Resubmit 0 Conies for ADoroval
❑
Letter
❑ Your Use/Information
❑ Approved as Noted ❑ Submit 0 Copies for Distribution
❑
Prints
❑ As Requested
❑ Returned After Loan ❑ Returned 0 Copies Corr. Print
❑
Change Order
❑ Review and Comment
❑ Returned for Corrections
❑
Plans
SENT VIA:
r,..-....:. 14
❑
Samples
❑ Hand Delivered
❑
Specifications
❑ U.S. Mail
❑
Other:
❑ Overnight: ❑ Faxed:
ITEM
NO. COPIES DATE „_, ITEM ,
NUMBER` DESCRIPTION , ,;`.,STATUS
01 03 6/2/2005
Contract Amenment #01
Remarks:
Lauri,
Please find attached; (3) copies of Contract Amendment #01 in accordance with the added scope of services as mutually agreed and
outlined in your letter dated 01 JUN05.
Thank you very 7�(\
Signed: v -
Ra4niro Herrera
Copies To: Transmittal and Attachments:
HA Project Files:
File: 959-04.Transmittal #00182
Issue File:
Dated: nG fil Z- f ll S-
ECEIVED
R
'JUN 07 2005
Palm Desert RDA.
Page I of 1
f a_tr_01
74-333 Highway I I I Palm Desert, CA 92260 Phone 760.346.61 1 1 FAX 760.340.6433 rherrera@harris-assoc.com
PALM DESERT REDEVELOPMENT AGENCY Contract # / P.O. # R22810 I 11468
CONTRACT AMENDMENT Change Order No. 2
Contingency: YES X I NO X
Contract Purpose: Visitor Information Center Construction Management Account No. 850-4358-433-4001
Contractor's Name: Harris & Associates Project No.
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES DECREASE INCREASE
(Supplemental Plans and Specifications Attached) In Contract Price In Contract Price
Additional Contract Management services
due to construction time extension $14,505.00
TOTALS:
NET CHANGE IN CONTRACT PRICE:
$14,505.00
JUSTIFICATION:
TOTAL BUDGET FOR PROJECT:
+ 20,108.00
CONTINGENCY:
Less: Expend. & Encumb. To Date:
- 20,108.00
Amount Approved by Council: +
9,828.00
Less: This Change Order Amount:
- 14,177.00
Less: Prior Change Order(s): -
9,500.00
BALANCE OF BUDGET
Less: This Change Order: -
328.00
REMAINING FOR PROJECT:
- 14,177.00
Balance Remaining of Contingency:
0.00
The amount of the Contract will be Increased by the Sum of: Fourteen Thousand. Five Hundred Five and
NO/100 Dollars ($ 14,505.00 ).
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have
required signatures as per the purchase resolution.
1. REQUESTED BY:
EXECUTIVE DIRECTOR
3. CERTIFIED
2. ACCEPTED BY:
CONTRACTOR
FUNDS AVAILABLE: 4. APPROVED BY: 6/23/05
FINANCE DIRECTOR BUFORD A. CRITES, CHAIRMAN Date Approved
NOTE: No payments will be made prior to Exec. Dir. and Agency Board approval 6123/05
SECRETARY Date Approved
Amend -RDA
PALM DESERT REDEVELOPMENT AGENCY Contract # / P.O. # R22810 I 11468
CONTRACT AMENDMENT Change Order No. 2
Contingency: YES X I NO X
Contract Purpose: Visitor Information Center Construction Management Account No. 850-4358-433-4001
Contractor's Name: Harris & Associates Project No.
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES DECREASE INCREASE
(Supplemental Plans and Specifications Attached) In Contract Price In Contract Price
Additional Contract Management services
due to construction time extension $14,505.00
TOTALS:
NET CHANGE IN CONTRACT PRICE:
$14,505.00
JUSTIFICATION:
TOTAL BUDGET FOR PROJECT:
+ 20,108.00
CONTINGENCY:
Less: Expend. & Encumb. To Date-
- 20,108.00
Amount Approved by Council: +
9,828.00
Less: This Change Order Amount:
- 14,177.00
Less: Prior Change Order(s): -
9,500.00
BALANCE OF BUDGET
Less: This Change Order: -
328.00
REMAINING FOR PROJECT:
- 14,177.00
Balance Remaining of Contingency:
0.00
The amount of the Contract will be (Deereased) Increased by the Sum of: Fourteen Thousand. Five Hundred Five and
NO/100 Dollars ($ 14,505.00 ).
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have
required signatures as per the purchase resolution.
1. REQUESTED BY:
EXECUTIVE DIRECTOR
3. CERTIFIED
2. ACCEPTED BY:
CONTRACTOR
FUNDS AVAILABLE: 4. APPROVED BY: 6/23/05
FINANCE DIRECTOR BUFORD A. CRITES, CHAIRMAN Date Approved
NOTE: No payments will be made prior to Exec. Dir. and Agency Board approval 6/23/05
SECRETARY Date Approved
.Amend -RDA
PALM DESERT REDEVELOPMENT AGENCY Contract # / P.O. # R22810 I 11468
CONTRACT AMENDMENT Change Order No. 2
Contingency: YES X I NO X
Contract Purpose: Visitor Information Center Construction Management Account No. 850-4358-433-4001
Contractor's Name: Harris & Associates Project No.
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES DECREASE
(Supplemental Plans and Specifications Attached) In Contract Price
Additional Contract Management services
due to construction time extension
TOTALS:
NET CHANGE IN CONTRACT PRICE:
JUSTIFICATION:
INCREASE
In Contract Price
$14, 505.00
$14,505.00 ,
TOTAL BUDGET FOR PROJECT: + 20,108.00 CONTINGENCY:
Less: Expend. & Encumb. To Date: - 20,108.00 Amount Approved by Council: + 9,828.00
Less: This Change Order Amount: - 14,177.00 Less: Prior Change Order(s): - 9,500.00
BALANCE OF BUDGET Less: This Change Order: - 328.00
REMAINING FOR PROJECT: - 14,177.00 Balance Remaining of Contingency: 0.00
The amount of the Contract will be (Decreased) Increased by the Sum of: Fourteen Thousand. Five Hundred Five and
NO1100 Dollars ($14,505.00 ).
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have
required signatures as per the purchase resolution.
1. REQUESTED BY:
EXECUTIVE DIRECTOR
3. CERTIFIED
2. ACCEPTED BY:
CONTRACTOR
FUNDS AVAILABLE: 4. APPROVED BY: 6/23/05
FINANCE DIRECTOR BUFORD A. CRITES, CHAIRMAN Date Approved
NOTE: No payments will be made prior to Exec. Dir. and Agency Board approval 6/23/05
SECRETARY Date Approved
...Amend -RDA
7
06/09/2605 17:18 17608379487
9
HARRIS R MIRAGE PAGE 02
Letter #03
June 09, 2005
Attn: Lauri Aylaian
City of Palm Desert Redevelopment Agency
Development Manager
City of Palm Desert
73-510 Fred Waring Drive
Palm Desert, CA. 92260-2578
RE: Visitors Information Ceuter Project
Subject: Construction Management Services
Amendment 402 - Contract Time Extension
Ms. Alyaian,
Harris & Associates
Program Managers
Construction Managers
Civi( Engineers
In following up with our most recent discussions, please accept this letter as a formal
request for extended Construction Management related services and costs beyond the
initial contract completion date of 07JUL05. The Visitor Center's current contract
completion date of 28JUL05 is due to City initiated additions or design related revisions
during the construction process to date.
Throughout the course of this project our Palm Desert staff has maintained the budget at
an. average monthly base rate of $9,670 per month. Given the recent series of Landscape,
Signage, and Site revisions; I respectively recommend our extended CM services be
budgeted to at least I SAUG05. This will allow some budget flexibility in event the
landscape revision durations extends beyond the current contract completion date or for
some unforeseen reasons.
Therefore, the total requested amendment #02 amount is S14,505.00
If you should have any questions or require additional information, contact me at your
earliest convenience.
Sincerely,
HARRIS & AS OCIATES
iro S. Herrera, Jr.
Regional Manager