HomeMy WebLinkAboutR19540A - CO8 and NOC - WDL Const. - New VICPALM DESERT REDEVELOPMENT AGENCY
STAFF REPORT
REQUEST: APPROVE CONSTRUCTION CLOSEOUT CHANGE ORDER NO.
8 TO WDL CONSTRUCTION (CONTRACT R19540-A) FOR
INCREASING SCOPE OF WORK AND EXTENDING THE
CONTRACT TIME FOR THE NEW VISITOR INFORMATION
CENTER, AND AUTHORIZE THE CITY CLERK TO FILE A
NOTICE OF COMPLETION
SUBMITTED BY: LAURI AYLAIAN, REDEVELOPMENT MANAGER
CONTRACTOR: WDL CONSTRUCTION
74-075 EL PASEO, STE. B-3
PALM DESERT, CA 92260
DATE: OCTOBER 27, 2005
CONTENTS: 1) CONSTRUCTION CHANGE ORDER NO. 8 TO CONTRACT
NO. R 19540-A
2) NOTICE OF COMPLETION
Recommendation:
By Minute Motion, that the Agency Board:
1. Approve a final change order, Construction Change Order No. 8 in
the amount of $71,381.81, to WDL Construction for adding fire lane
signage, increasing the quantity and nature of hardscape and
landscape around the building, and increasing the contract
duration 25 days; and
2. Authorize the City Clerk to file a Notice of Completion for the
subject project upon staff confirmation that all punchlist work has
been completed.
The funding necessary for this added work is available in Account No.
850-4358-433-4001.
Executive Summarv:
Approval of the staff recommendation will close out the Visitor Center construction
contract by approving additional compensation for: extended overhead and general
Staff Report
Change Order No. 8 and Notice of Completion for Contract R19540-A
Page 2 of 3
October 13, 2005
conditions costs due to Owner changes; contract additions on a directed basis; and the
addition of 28 fire lane signs, as requested by the Fire Marshal. It will also authorize the
City Clerk to file a Notice of Completion when the fire lane sign installation is complete.
Discussion:
On September 9, 2004, the Agency Board awarded Contract No. R19540-A to WDL
Construction for construction of a new Visitor Information Center. The work is
substantially complete, and the building is occupied and open for business. In order to
expedite completion, several change orders were previously issued that increased the
scope of work done under this contract, while simultaneously reducing the scope of
work to be done under the future contract for landscape and hardscape at Entrada del
Paseo. The additional work required that the contract time be increased by 25 calendar
days, which results in an increase in the contractor's general conditions costs (job
trailer, superintendent's wages, etc.) and overhead expenses. The total of these
extended overhead and general conditions costs is $31,047.28, and is included in
Change Order No.8.
Change Order No. 8 also includes the following three items:
$13,249.75 for 28 "No Parking" signs required by the Fire Marshal to be
installed along both sides of the curved lane behind the Visitor Center;
$17,613.12 for hardscape additions and revisions around the exterior of the
building; and
$9,471.66 for landscape additions and modifications between the preliminary
set of landscape plans, from which bids were solicited, and the permitted set
of landscape plans, which carried the final approvals from CVWD and the City
of Palm Desert Landscape Department (early bidding from preliminary plans
was accomplished in order to authorize work before the summer hiatus from
Agency Board meetings).
The first item listed above has not yet been performed, but if approved by the Agency
Board, it will be completed prior to filing of the Notice of Completion for the project. The
second item listed was performed as directed work to address items such as ADA,
erosion concerns, and concrete footings for added lights, with the final amount
negotiated by Harris & Associates (the Agency's Construction Manager). The third item
was authorized by the Executive Director under the authority granted by Section
3.30.270 of the Palm Desert Municipal Code. This same section of the Code requires
this report of the Executive Director's action.
G %RDA\Mana Hunt\WPDATAWYLAIAN\STFRPTS\102705 WDL CO 8 and NOC doc
Staff Report
Change Order No. 8 and Notice of Completion for Contract R19540-A
Page 3 of 3
October 13, 2005
Since all contract work has been satisfactorily completed except minor punchlist items
and the fire lane signage described above, staff also requests that the City Clerk be
authorized to file a Notice of Completion with the County Recorder upon confirmation
from the Construction Manager that these last punchlist items are complete.
Change Order No. 8 will be the final change order on the subject contract. The non -
elective change orders on this project have totaled 4.5 percent of the original contract
value, which is within industry standards for a project of this size and nature.
Submitted by:
Lauri Aylaian
Redevelopment Manager
mh
Approval:
lopment
utive Director
Department Head:
Dave Yridoy
Director, edevelopment/Housing
aA&1;�-
Paul S. Gibson, Director of Finance
G \RDA\Mana Hunt%WPDATA',AYLAIAN\STFRPTS',102705 WDL CO Band NOC doc
PALM DESERT REDEVELOPMENT AGENCY Contract # / P.O. # R19540A I 11775
CONSTRUCTION CHANGE, ORDER Change Order No. 8
Contingency: YES I NO X
Contract Purpose: Construction of new Visitor Information Center Account No. 850-4358-433-4001
Contractor's Name: WDL Construction Project No.
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES DECREASE INCREASE
(Supplemental Plans and Specifications Attached) In Contract Price In Contract Price
Add fire lane signage; $71,381.81
increase quantity and nature of hardscape and landscape around building;
increase contract duration by 25 days
TOTALS:
NET CHANGE IN CONTRACT PRICE: $71,381.81
JUSTIFICATION:
TOTAL BUDGET FOR PROJECT: + 3,380,952.41 CONTINGENCY:
Less: Expend. & Encumb. To Date: - 3,380,952A1 Amount Approved by Council: +
Less: This Change Order Amount: - 71,381.81 Less: Prior Change Order(s): -
BALANCE OF BUDGET Less: This Change Order: -
REMAINING FOR PROJECT: - 71,381.81 Balance Remaininq of Contingency: -
The amount of the Contract will be (Decreased) Increased by the Sum of: Seventy-one Thousand. Three Hundred Eiahty-
one and 81/100 Dollars ($71,381.81).
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have
required signatures as per the purchase resolution.
1. REQUESTED BY:
EXECUTIVE DIRECTOR
3. CERTIFIED
2. ACCEPTED BY:
CONTRACTOR
FUNDS AVAILABLE: 4. APPROVED BY: 10/27/05
FINANCE DIRECTOR BUFORD A. CRITES, CHAIRMAN Date Approved
NOTE: No payments will be made prior to Exec. Dir. and Agency Board approval 10/27/05
SECRETARY Date Approved
Chng-Ord.KDA
To be recorded with the Riverside County Recorder
within 10 days after completion and acceptance by
the City Council. NO RECORDING FEE PER
SECTION 6103 OF THE GOVERNMENT CODE.
When recorded, return to:
Office of the City Clerk
City of Palm Desert
73-510 Fred Waring Drive
Palm Desert, CA 92260
NOTICE OF COMPLETION
(Cal. Civ. Code § 3093 — Public Works)
NOTICE IS HEREBY GIVEN:
1. That the interest or estate stated in paragraph 3 herein in the real property herein described is SOLELY
OWNED by the PALM DESERT REDEVELOPMENT AGENCY, A PUBLIC BODY, CORPORATE AND
POLITIC, a political subdivision of the State of California, and whose address is 73-510 FRED WARING
DRIVE, PALM DESERT, CALIFORNIA.
2. That the full name and address of the owner of said interest or estate is set forth in the preceding
paragraph.
3. That the nature of the title of the stated owner, as set forth in paragraph 1, is in fee.
4. That on the 271h day of October, 2005 a work of improvement described as Contract No. R19540-A on
the real property herein described was completed.
5. That the name of the original contractor, if any, for said work of improvement was: WDL Construction,
74-075 El Paseo, Ste. B-3, Palm Desert, CA 92260.
6. That the real property herein referred to is situated in the City of Palm Desert, County of Riverside,
State of California, and is described as Construction of Visitor Information Center, 72-567 Highway 111,
Palm Desert, CA 92260.
PALM DESERT REDEVELOPMENT AGENCY
Dated: By:
Buford A. Crites, Chairman
STATE OF CALIFORNIA }
}ss
COUNTY OF RIVERSIDE }
I hereby certify that I am the City Clerk of the governing board of the PALM DESERT REDEVELOPMENT AGENCY, CALIFORNIA, the
political subdivision which executed the foregoing Notice and on whose behalf I make this verification: That I have read said Notice,
know its contents, and that the same is true. I certify under penalty of perjury that the foregoing is true and correct.
Executed at Palm Desert, California, on this day of 20
RACHELLE D. KLASSEN, SECRETARY