PALM DESERT REDEVELOPMENT AGENCY
STAFF REPORT
REQUEST: RATIFY CONSTRUCTION CHANGE ORDER NO. 5 TO WDL
CONSTRUCTION (CONTRACT NO. R19540-A) FOR
MISCELLANEOUS CHANGES INCIDENTAL TO THE
CONSTRUCTION OF A NEW VISITOR INFORMATION CENTER
AT ENTRADA DEL PASEO
SUBMITTED BY: LAURI AYLAIAN, REDEVELOPMENT MANAGER
CONTRACTOR: WDL CONSTRUCTION
74-075 EL PASEO, STE. B3
PALM DESERT, CA 92260
DATE: SEPTEMBER 8, 2005
CONTENTS: CONSTRUCTION CHANGE ORDER NO. 5
Recommendation:
By Minute Motion, that the Agency Board ratify Construction Change Order No. 5 in the
amount of $15,723.29 to WDL Construction of Palm Desert, California, for seven
miscellaneous field -directed changes necessary for the construction of the new Visitor
Information Center at Entrada del Paseo.
The funding necessary for this added work is available in Account No. 850-4358-433-
4001.
Discussion:
On 9 September 2004, the Agency Board awarded Contract No. R19540-A to WDL
Construction for the construction of a new 8,200 square foot Visitor Information Center.
During the construction process, some unanticipated conditions have arisen which have
necessitated that the contractor perform additional work. These changes are minor in
nature and are typical for a project of this magnitude. They include: addition of one roof
drain; revising ductwork and two HVAC grilles to avoid conflicts with structural steel
members; adding sheet metal flashing for moisture protection near the sloped roof soffit;
providing a sunshade for the mechanical equipment located on the building roof;
providing visual display boards in two meeting rooms, and similar modifications.
Because the changes described above did not impact work on critical path items
identified in the current construction schedule for the Visitor Information Center, no
contract time extension is necessary.
G tRDAtMana Hunt\WPDATAWYLAIAN\STFRPTSt090805WDLCO5 Ooc
Staff Report
Ratify Change Order No. 5 to WDL Construction (Contract No. R19540A
Page 2 of 2
September 8, 2005
The work included in Change Order No. 5 was approved by the Executive Director
under the authority granted by Section 3.30.270 of the Palm Desert Municipal Code.
This same section of Code requires this report of the Executive Director's action.
To date, the non -elective change orders on this project have totaled 1.8% of the original
contract value, which is well within industry standards for a project of this size.
Submitted by:
Lauri Aylaian
Redevelopment Manager
mh
Approval:
pment
Director
Department Head:
>oe�dev�elopment/Housing
1
Dave Yr
Director
Paul S. Gibson, Director of Finance
G \RDA\Maria Hunt\WPDATAWYLAIAMSTFRPTS\090805WDLCO5 doc
PALM k ! gEVELOMW AGENCY Contract # / P.O. #
COWRUCMI CHM OR= Change Order No.
Contingency:
Contract Purpose: Construction of new Visitor Information Center Account No.
Contractor's Name: W DL Construction Project No.
R19540A I 11775
5
YES I NO X.
850-4358-433-4001
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES DECREASE
(Supplemental Plans and Specifications Attached) In Contract Price
Perform work described in the following attached documents:
Contract Change Order No. 00016 by Harris & Associates Dated 7/25/05:
Contract Change Order No. 00017 by Harris & Associates Dated 7/25/05:
Contract Change Order No. 00018 by Harris & Associates Dated 7/25/05:
Contract Change Order No. 00019 by Harris & Associates Dated 7125/05:
Contract Change Order No. 00020 by Harris & Associates Dated 7/25/05:
Contract Change Order No. 00021 by Harris & Associates Dated 7/26/05:
Contract Change Order No. 00022 by Harris & Associates Dated 7/26/05:
TOTALS:
NET CHANGE IN CONTRACT PRICE:
JUSTIFICATION:
TOTAL BUDGET FOR PROJECT: + 3,311,583.08 CONTINGENCY:
Less: Expend. & Encumb. To Date: - 3,311,583.08 Amount Approved by Council: +
Less: This Change Order Amount: - 15,723.29 Less: Prior Change Order(s): -
BALANCE OF BUDGET Less: This Change Order: -
REMAINING FOR PROJECT: - 15,723.29 Balance Remaining of Contingency: -
INCREASE
In Contract Price
$ 1,337.91��
1,925.33-�
4,934.72 v
3,530.33�
1,373.73-1
1,646.87
974.40
$15,723.29
The amount of the Contract will be (9.. J) Increased by the Sum of: Fifteen Thousand. Seven Hundred Twentv-three
and 29/100 Dollars ($ 15,723.29 ).
This document will become a supplement to the Contract and all provisions will apply hereto, all items inZTOR'
ve must have
required signatures as per the purchase resolution.
1. REQUESTED BY: 2. ACCEPTED BY: - O�
EXECUTIVE DIRECTOR CON 7A
3. CERTIFIED
FUNDS AVAILABLE: 4. APPROVED BY: 8/25/05
FINANCE DIRECTOR BUFORD A. CRITES, CHAIRMAN Date Approved
NOTE: No payments will be made prior to Exec. Dir. and Agency Board approval 8/25/05
SECRETARY Date Approved
.Chug Ord RDA
Palm Desert Redevelopment Agency
Palm Desert Visitor Center Project
EI Harris & Associates
CONTRACT CHANGE ORDER NO. 00016
To: Michael Vujica Date: July 25, 2005
WDL Construction
74-075 El Paseo Reference Spec. Section: RCO #016
Suite B-3
Palm Desert, CA 92260
Subject: Added Roof Drain
Gentlemen:
You are hereby directed to make the heroin described changes from the plans and specifications or do the following described work not
included in the plans and specifications of this contract All new work herein described shall be done in accordance with the applicable
provisions of the plans and specifications, except as modified by this contract change order. NOTE: This change order is not effective
until approved by the Owner, or until an authorized Field Directive is executed.
DESCRIPTION OF CHANGE/REASON FOR CHANGE:
This change order provides for all work associated for the addition of (1) 2" roof drain and related drain p[iping at the
mid -level roof of the high turret.
Upon review of the roof plan, it was clarified in RFI #059 that a new 2" roof drain and drainage piping system was
required at the mid -level roof of the high turret.
COST OF CHANGE: $1,337.91
CONTRACT TIME ADJUSTMENT:
0 Days I
This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, profit any and all
Indirect costs, and time adjustment to perform the above described change. All other costs are non-compensable.
Recommended Bri ate: (Accepted By: ate:
2-a7-0S
WDL Const)uction
H�ris & Associates Palm Des Redevelopment Agency
File No.: 959-04 Page I of I
Issue File: 014
74-333 Highway I I I Palm Desert, CA 92260 Phone 760.346.61 11 FAX 760.340.6433 rherrera@harris-assoc.com f a cco01
Palm Desert Redevelopment Agency
Palm Desert Visitor Center Project
0 Harris & Associates
CONTRACT CHANGE ORDER NO. 00017
To: Michael Vujica Date: July 2S, 200S
WDL Construction
74-075 El Paseo Reference Spec. Section: RCO #022
Suite 9-3
Palm Desert, CA. 92260
Subject: Duct/Vent Modifications
Gentlemen:
You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not
included in the plans and specifications of this contract All new work herein described shall be done in accordance with the applicable
provisions of the plans and specifications, except as modified by this contract change order. NOTE: This change order is not effective
until approved by the Owner, or until an authorized Field Directive is executed.
DESCRIPTION OF CHANGE/REASON FOR CHANGE:
This change order provides all work associated for the revision of HVAC duct, vent modifications for (2) grilles at the
Gallery above the Information Desk, and the replacement of (3) light fixtures previously installed.
There were (2) ducts feeding separate grilles that by design would not work due to conflicts with structural steel
members. Architectural Supplementary Instructions #36.1 revised (1) duct location across the room and changed both
HVAC grille sizes.
COST OF CHANGE: $1,92S.331
CONTRACT TIME ADJUSTMENT: 0 Days
This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, profit any and all
indirect costs, and time adjustment to perform the above described change. All other costs are non-compensable.
Recommended By:
Har�s & Associates t
ate: (Accepted By:
.-IAl -
WDL ConstrucdW
/Y c /e7`-
Palm DesertiBdevelopment Agency
ate:
File No.: 959-04
Issue File: 024
Page I of I
74-333 Hixhway I 1 I Palm Desert, CA 92260 Phone 760.346.61 1 1 FAX 760.340.6433 rhei,Yra@harris-assoc.com f a oco01
Palm Desert Redevelopment Agency
Palm Desert Visitor Center Project
0 Harris & Associates
CONTRACT CHANGE ORDER NO. 00018
To: Michael Vujica Date: July 25, 2005
WDL Construction
74-075 El Paseo Reference Spec. Section: RCO #023
Suite B-3
Palm Desert, CA. 92260
Subject: Clearstory Flashing Revision
Gentlemen:
You am hereby directed to make the herein described changes from the plans and specifications or do the following described work not
included in the plans and specifications of this contract. All new work herein described shall be done in accordance with the applicable
provisions of the plans and specifications, except as modified by this contract change order. NOTE: This change order is not effective
until approved by the Owner, or until an authorized Field Directive is executed.
DESCRIPTION OF CHANGEIREASON FOR CHANGE:
This change order provides for all work associated for the revision of the upper clearstory exterior window head at roof
soffit condition.
Architectural Supplimentary Instruction #040 provided for additional sheet metal flashing to address the absence of a
moisture protection detail at the underside of the sloped roof soffit overhang and clearstory window header.
COST OF CHANGE: $4,934.72
CONTRACT TIME ADJUSTMENT:
0 Days I
This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, profit any and all
Indirect costs, and time adjustment to perform the above described change. All other costs are non-compensable.
Recommended By.
I
HaA is dr Associates
ate: +Accepted By.1 ate:
WDL Constructio
Palm Dese edevelopment Agency
File No.: 959-04
Issue File: 023
Page I of I
74-333 Highway I I I Palm Desert. CA 92260 Phone 760.346.6111 FAX 760.340.6433 rherrera@harris-assoc.com f a cco01
Palm Desert Redevelopment Agency
Palm Desert Visitor Center Project
0 Harris & Associates
CONTRACT CHANGE ORDER NO. 00019
To: Michael Vujica Date: July 25, 2005
WDL Construction
74-075 El Paseo Reference Spec. Section: RCO #026
Suite B-3
Palm Desert, CA. 92260
Subject: Systecon Sunshade
Gentlemen:
You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not
Included in the plans and specifications of this contract All new work herein described shall be done in accordance with the applicable
provisions of the plans and specifications, except as modified by this contract change order. NOTE: This change order is not effective
until approved by the Owner, or until an authorized Field Directive is executed.
DESCRIPTION OF CHANGE/REASON FOR CHANGE:
This change order provides for all work associated for the installation of framed sunshade canopy over the Systecon
pumping package equipment located on the building roof.
When observing the location of the equipment pumping package relative to the height of the surrounding roof parapets,
the Systecon installer recommended the equipment be sunshaded for heat protection. Architectural Supplementary
Instructions #014 was generated that provided for a framed sheet metal canopy to protect the equipment from the
seasonal extreme heat conditions.
COST OF CHANGE:
CONTRACT TIME ADJUSTMENT:
$3,530.34
0 Days I
This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, profit any and all
Indirect costs, and time adjustment to perform the above described change. All other costs are non-compensable.
Recommended By.1
H�rris & Associates
ate: *ccepted By:l
2¢?..f��
WDL Construction
Palm Des tevelopment Agency
ate:
,- Z� - 1/-5-
File No.: 959-04
Issue File: 008
Page I of I
74-333 Highway I I I Palm Desert. CA 92260 Phone 760.346.611 1 FAX 760.340.6433 rherrera@hams-assoc.com f a cco01
Palm Desert Redevelopment Agency
Palm Desert Visitor Center Project
0 Harris & Associates
CONTRACT CHANGE ORDER NO. 00020
To: Michael Vujica Date: July 25, 2005
WDL Construction
74-075 El Paseo Reference Spec. Section: RCO 027 �
Suite B-3
Palm Desert, CA. 92260
Subject: Tile/Carpet Transition Strip
Gentlemen:
You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not
Included in the plans and specifications of this contract. All new work herein described shall be done in accordance with the applicable
provisions of the plans and specifications, except as modified by this contract change order. NOTE: This change order is not effective
until approved by the Owner, or until an authorized Field Directive is executed.
DESCRIPTION OF CHANGE/REASON FOR CHANGE:
This change order provides for all work associated for the purchase and installation of a Schlutter metal transition strip
between the carpet and slate tile condition at the Retail area.
Upon review of the finish floor plans, Architectural CSK #l6 was generated to address the rough edge condition had the
Schlutter metal strip not been placed between the stone tile/carpet condition.
COST OF CHANGE: $ 1,373.73
CONTRACT TIME ADJUSTMENT: 0 Days
This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, profit any and all
Indirect costs, and time adjustment to perform the above described change. All other costs are non-compensable.
Recommended By:I
c
Hats & Associates 1
ate:
2S ,---'J III .'Za5
`Accepted By:,
r
WDL CApA
Palm Desert
Agency
File No.: 959-04
Issue File: 029
Page I of 1
74-333 Highway I I I Palm Desert. CA 92260 Phone 760.346.611 1 FAX 760.340.6433 rherrera@harris-assocaxn f a cco01
Palm Desert Redevelopment Agency
Palm Desert Visitor Center Project.
01 Harris & Associates
CONTRACT CHANGE ORDER NO. 00021
To: Michael Vujica Date: July 26, 200S
WDL Construction
74-075 El Paseo Reference Spec. Section: RCO 029 ✓
Suite 8-3
Palm Desert, CA. 92260
Subject: Visual Display Boards
Gentlemen:
You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not
included in the plans and specifications of this contract All new work herein described shall be done in accordance with the applicable
provisions of the plans and specifications, except as modified by this contract change order. NOTE: This change order is not effective
until approved by the Owner, or until an authorized Field Directive is executed.
DESCRIPTION OF CHANGE/REASON FOR CHANGE:
This change order provides for all work associated for the purchase and installation of (2) 4' x T Type "F" visual display
boards located in Meeting Room #1 12 and Office #123.
The drawings did not show the quantity or locations and the visual board type and manufacturer was revised from what
was originally specified.
COST OF CHANGE:
CONTRACT TIME ADJUSTMENT:
$1,646.87
0 Days
This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, profit any and all
Indirect costs, and time adjustment to perform the above described change. All other costs are non-compensable.
Recommended By:l
H s do Associates
File No.: 959-04
ate: Accepted By:I ate:
06. -T-I -ZC0/A7�a��pS
WDL4Constr6ln
Palm Dese edevelopment Agency
Page IofI
Issue File: 034
74-333 Highway I I I Palm Desert, CA 92260 Phone 760.346.61 1 1 FAX 760.340.6433 rharrera@harrisassoc.com f a_cco01
Palm Desert Redevelopment Agency
Palm Desert Visitor Center Project
0 Harris & Associates
CONTRACT CHANGE ORDER NO. 00022
To: Michael Vujica Date: July 26, 2005
WDL Construction
74-075 El Paseo Reference Spec. Section: RCO #031 [�
Suite B-3
Palm Desert, CA 92260
Subject: Grout Repressed Slab @ Room #120
Gentlemen:
You am hereby directed to make the herein described changes from the plans and specifications or do the following described work not
Included in the plans and specifications of this contract All new work heroin described shall be done In accordance with the applicable
provisions of the plans and specifications, except as modified by this contract change order. NOTE: This change order is not effective
until approved by the Owner, or until an authorized Field Directive Is executed.
DESCRIPTION OF CHANGEIREASON FOR CHANGE:
This change order provides for all work associated for the grout in -fill of the depressed shower slab at Unisex Room
# 120.
In review of the drawings; Architectural Supplementary Instructions #05 was generated to correct the structural
drawings that indicated the shower area to be depressed which was not ultimately required for the designed ceramic tile
finish.
COST OF CHANGE:
CONTRACT TIME ADJUSTMENT:
$974.40 1
0 Days I
This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, profit any and all
Indirect costs, and time adjustment to perform the above described change. All other costs are non-compensable.
Recommended By.1
Hrris & Assodates
ate: Accepted Sr.
WDL Cons all
el _AZ4�
Palm DeserAedevelopment Agency
ate:
7-02�`l/�
File No.: 959-04
Issue File: 035
Page 1 of I
74-333 Highway I I I Palm Desert, CA 92260 Phone 760.346.6111 FAX 760.340.6433 rherrera@hwds-assoccom f a aco01