HomeMy WebLinkAboutR22730 - CA5 - La Rocca VillasPALM DESERT REDEVELOPMENT AGENCY STAFF REPORT REQUEST: AUTHORIZE CONTRACT AMENDMENT NO. 5 TO MSA CONSULTING (CONTRACT NO. R22730) FOR ADDITIONAL SERVICES FOR THE REMOVAL AND REPLACEMENT OF A DETERIORATED IRRIGATION LINE, DESIGN OF A TEMPORARY ACCESS ROAD, AND CONSTRUCTION ADMINISTARTION AND STAKING FOR THE LA ROCCA VILLAS. SUBMITTED BY: CATHERINE WALKER, SENIOR MANAGEMENT ANALYST CONTRACTOR: MSA CONSULTING 34-200 BOB HOPE DR. RANCHO MIRAGE, CA 92270 DATE: AUGUST 24, 2006 CONTENTS: CONTRACT AMENDMENT NO. 5 TO CONTRACT NO. R22730 Recommendation: By Minute Motion, that the Agency Board: 1. Authorize Contract Amendment No. 5 in the amount not to exceed $25,000 to MSA Consulting of Rancho Mirage, California (Contract No. R22730) for production of engineering and construction documents for the removal and replacement of a deteriorated CVWD irrigation line, the design and engineering of a temporary access road ; and 2. Authorize the Chairman to execute the same. Funds are available in Account No. 870-4698-466-4001. Discussion: On May 13, 2004, the Redevelopment Agency Board awarded a contract to MSA Consulting for final civil engineering services for the proposed single-family and senior duplex housing project on 20 acres of land immediately west and south of Hovley Gardens. The civil engineering services are almost complete. As part of the design of the 20-acre affordable housing project, the Agency requested additional services from MSA for the design of a temporary access road, and for the production of engineering and construction documents for the removal and replacement of an existing CVWD irrigation line. The temporary access road will allow for a streamlined flow of traffic for all construction vehicles during the production of the single-family and senior units. The access road is designed to run from Merle to the northern most point of the senior villas, allowing for the simultaneous construction of the villas and the single-family units. The pre-existing irrigation line runs north/south in close proximity to the temporary access road and lies adjacent to the Portola Staff Report Authorize Contract Amendment No. 5 to MSA Consulting Contract No. R22730 Page 2 of 2 August 24, 2006 Country Club. Due to the advanced age of the irrigation line, CVWD informed the Agency that movement of construction vehicles along the access road would most likely cause the line to shatter. The Agency decided to remove and replace the existing line in order to prevent any possible damage and insure the line's longevity. Staff recommends approval of Amendment No. 5 to the MSA Consulting contract for the purpose of completing two necessary components for the construction of the Falcon Crest single-family homes and the La Rocca Villas senior housing units. Submitted by: Catherine Walker Senior Management Analyst Approval: Department Head: _ Dave Yrigoyen Director of Redevelopment/Housing 1 X14 ✓--- Paul S. Gibson, Director of Finance BY RDA ON (`-a F_ n (o VERIFIED BY �TQ r Original on file with City Clerk's Offico G:1RDA\Beth LongmanlStaH ReportsMalkeAMSA CO 5 082406.doc PALM EEC E1, ITLOPM NIT AGE, NC / Contract # / P.O. # I R22730 I 11426 CONI& ACE N I NS' Change Order No. I 5 Contingency: I YES I NO Contract Purpose: Single Family & Senior Housing Civil Engineering Account No. I 870-4698-466-4001 Contractor's Name: MSA Consulting, Inc. Project No. You are hereby requested to comply with the following changes from the contract plans and specifications: DESCRIPTION OF CHANGES DECREASE INCREASE (Supplemental Plans and Specifications Attached) In Contract Price In Contract Price Produce engineering and construction documents for removal and replacement of existing CVWD irrigation line, and design/engineering of temporary access road $25,000.00 TOTALS: NET CHANGE IN CONTRACT PRICE: $25,000.00 JUSTIFICATION: TOTAL BUDGET FOR PROJECT: + 313,875.00 CONTINGENCY: Less: Expend. & Encumb. To Date: 313,875.00 Amount Approved by Council: + Less: This Change Order Amount: 25,000.00 Less: Prior Change Order(s): BALANCE OF BUDGET Less: This Change Order: REMAINING FOR PROJECT:-25,000.00 Balance Remaining of Contingency: 0.00 The amount of the Contract will be ( ) Increased by the Sum of: Twentv-five Thousand and NO/100 Dollars ($25,000.00). This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have required signatures as per the purchase resolution. 1. REQUESTED BY: EXECUTIVE DIRECTOR 3. CERTIFIED 2. ACCEPTED BY: CONTRACTOR FUNDS AVAILABLE: 4. APPROVED BY: 8/24/06 FINANCE DIRECTOR JIM FERGUSON, CHAIRMAN Date Approved NOTE: No payments will be made prior to Exec. Dir. and Agency Board approval 8/24/06 SECRETARY Date Approved A..d-RDA