Loading...
HomeMy WebLinkAboutSR - R22600A - CO1 - Henderson Cmnty BldgC-1 PALM DESERT REDEVELOPMENT AGENCY STAFF REPORT REQUEST: APPROVE CONSTRUCTION CHANGE ORDER NO. 1 TO STETON CONSTRUCTION GROUP (CONTRACT NO. R22600A) IN THE CUMULATIVE CREDITED AMOUNT OF ($15,059) FOR THE HENDERSON COMMUNITY BUILDING SUBMITTED BY: MISSY WIGHTMAN, PROJECT COORDINATOR CONTRACTOR: STETON CONSTRUCTION GROUP 145 SOUTH STATE COLLEGE BLVD. SUITE 450 BREA, CA 92821-5818 DATE: APRIL 12, 2007 CONTENTS: CHANGE ORDER NO. 1 (C.O.R. NOS. 1R1, 2, 3, 4, 6, 8, 9, 10 and 12R1) Recommendation: By Minute Motion, that the Agency Board: (1) Approve Change Order No. 1 to Contract No. R22600A for the change order requests 1R1, 2, 3, 4, 6, 8, 9, 10 and 12R1 in a credited amount of ($15,059) for the Henderson Community Building; and (2) adjust the original contingency of $454,000 to the increased amount $469,059 to reserve for future change order requests. Executive Summarv: Approval of this recommendation will allow the General Contractor to move ahead as scheduled with the attached, referenced change order requests. The above -referenced change orders together generate a total credit of ($15,059). Discussion: On 13 July 2006, the Agency Board authorized the award of Contract No. R22600A in the amount of $4,540,000 to Steton Construction Group for the construction of the new 5,800 square foot Henderson Community Building at the Entrada del Paseo site. Since the lowest bid came in above the estimated amount for construction, staff has been Staff Report Approve Construction Change Order No. 1 to Steton Construction Group (Contract No. R22600A) in the Cumulative Credited Amount of ($15, 059) for the Henderson Community Building Page 2 of 2 April 12, 2007 working diligently with the Architect, Construction Manager, and General Contractor to reduce construction costs without altering the design or integrity of the materials. To date, the recommended price reduction changes have resulted in a credit of ($78,240). The first major change was deleting the insulating cement mix at all interior walls, and keeping it at all exterior walls only where it is needed. The standard cement mix will now be used at all interior walls. The second largest credit was utilizing foam roofing, rather than the typical built-up roofing. Neither of these changes will compromise the integrity of the design, nor the quality of construction. The remaining attached change order requests have resulted due to revisions made to the original construction documents or additional cost reduction strategies implemented by staff in consultation with the Construction Manager, Architect and Project Engineers. Based on the Architect's, Construction Manager's, and staff's review, Change Order No. 1 is recommended for approval to allow the construction of the Henderson Community Building to move forward towards completion. Submitted by: 4%4i�;� Missy fthtfnan Project Coordinator mh Department Head: Dam Yrigo;d"evelopment/Housing Director of Carlos L. OYtega, Exe ive Director Martin Alvarez Redevelopment Manager Approval: eRMeCdCeve*iop aAC n_ Paul S. Gibson, Director of Finance CA , BY RDA ON 4 — la—C>� -i VERIFIED BY �hQ i Original on file witt7 City Clerk's office Wrda\Melissa Wightman\Henderson Community Building\Staff Reports\Staff Report- Change Orders.doc Z 7 O c d V- 0N- 0 is � °�j `c �3' 0 4-1 O�`�r M 1cn 4 M. 0 J v PALM DESERT REDEVELOPMENT AGENCY CONSTRUCTION CHANGE ORDER Contract Purpose Construction of Henderson Community Building Consultant's Name Steton Construction Group 145 South State College, Suite 450 Add�ess. grea, CA 92821 Contract # / P.O. # Change Order No. R22600A � 13386 1 Contingency: � YES � NO Account No. � 850-4358-433-4001 Project No. Vendor No. � 9494 � You are hereby requested to comply with the following changes from the contract plans and specifications: DESCRIPTION OF CHANGES DECREASE INCREASE (Supplemental Plans, Specifications, and Directives dated Attached) In ContraCt PriCe In ContraCt PriCe Replace built up roof with foam roofing 30,012.00 Perform irrigation mofifications per owner's direction Import and compact additional soil Southern California Edison utility plan revision Implement SWPPP plan modifications per owner direction Revised pricing to utilize alternate lighting fixtures Provide credit to delete steel per ACD #14 Utilize standard cement mix in lieu of insulating mix at all interior walls and provide 1/4" radius at all outside corners perACD #5R1 Battery inverter and egress lighting correction JUSTIFICATION: TOTAL BUDGET FOR PROJECT: + Less: Expend. & Encumb. To Date: - Less: This Change Order Amount: - BALANCE OF BUDGET REMAINING FOR PROJECT: TOTALS: NET CHANGE IN CONTRACT PRICE: 5,439.00 39,687.00 531.00 12,526.00 1,823.00 1,702.00 44,703.00 4,998.00 78,240.00 4,524,941.00 CONTINGENCY: 4,524,941.00 Amount Approved by Board: (15,059.00) Less: Prior Change Order(s): Less: This Change Order: 15,059.00 Balance Remaining of Contingency: 63,181.00 (15,059.00) + 454,000.00 - (15, 059.00) 469, 059.00 The amount of the Contract will be (Decreased) �� by the Sum of: Fifteen Thousand Fiftv-nine and no/100 Dollars ($15,059.00). W\Agenda Items\2007-Apr 12\Chg Order 1 Contrect R22600A\CO 1 doc See reverse Contract $22600A Change Order No. 1 Continued from front This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, fumish equipment and materials, and perform all work as necessary or required to complete the Change Order items for a lump sum price agreed upon between the Contractor and the Palm Desert Redevelopment Agency, otherwise referred to as Owner. Contract Time Extension -0- Days. Revised Contract Total $4,524,941.00 The undersigned Contractor approves the foregoing Change Order # 1 as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order # 1. The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of that directly or indirectly related to the approved time extension, required to complete the Change Order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Change Order shall be effective when approved by the Owner. Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies, waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as any and all consequential damages. This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have required signatures as per the purchase resolution. REQUESTED BY: EXECUTIVE DIRECTOR CERTIFIED FUNDS AVAILABLE: 2. ACCEPTED BY: CONTRACTOR Date Accepted 4. APPROVED BY: FINANCE DIRECTOR NOTE: No payments will be made prior to Executive Director and Agency Board approval RICHARD S. KELLY, CHAIRMAN SECRETARY 4/12/07 4/12/07 W\Agenda Items\2007-Apr 12\Chg Order 1 Contrect R22600A\CO 1 doc See reverse � � � � O �� � � rn � r � �2 � _' � m m N � a �o � N N r c� � � � ;.r: 4� {n � � �; A � 0 0 ? cn � � � A A N � � cn 1 (,, O O �1 ry � « s.; � � O � O Cn � O O � � 0 O � � O O � 0 (D 00 V � U7 A W N �J O �# ° � � Cn� �� �-a � c �� O�,o� �� m a� m�n- u,' O� N�o � rn°� v G�G� � f° � cn�ro� �. � m �� m°1 O�� � ZZ � � � u� � (7 T �p � x � n D D � � � � � r« n�a� � W � rr D��� ac �. v� �� o�.� -� � C)C� nm m 3. r«m� 3� o� 3� o C m 00 0 Q: p N^� •n+, � 7 �i "O 7 � Q �_�`I �y �� O � O � A7 �� � .0 � z;U 0 ��_ � � = 3 � �� a a � `� �cni j� �. : `° m� � �'��Q � �o � z� O° � � D � � � -' �' � � n � � % � O C `y � O� .�' � ': fR � j � � - j Q1 y � � � � � � m O �� o � � �. Q o � w � � � C� 0 Z � � � � €� � i� � W � � � i � O � {h C�J� O7 w �� � � � .� � iJi � j � cfl �� c � � " O t � �' � `? `? `' o 0 o a `-' � n j � % � % � �m � c� A ? A A � � ? ? � � y �y '�'.�« � cn ir w cn cn cn cn � cs� o Q � n� � � rn � � � � � � � d � �� � � A /� � � � j VI � � V � %0 � W 6� oo � (D O O O O O O O O � O �_ /� � D n a 69 fi9 'a 0 '� p� A p � �. o� � � a �. °:,� �oa� p� �� oo� � �n oo� G ��� p n %/ � Z �r � � � tfl rfl � �s js � � o j G) J .�f � i ..J. � h / � � � � � � v V � N � � � A CP V C]S U1 Oo 00 OD D7 P n S[1 . j . O W O) 00 07 W W 0� U1 O(D �. � ? N .CND .[NO .1.�7� C�11 � W N � % O O O O O O O O d d � y C 3 a � 0 TI � � t'i Zz0 n � ��a os3 nm z G) m � CJ m N March 14, 2007 Mr. Mazk Chappell Construction Manager douglas e. bamhart, inc. 41-495 Boardwalk Suite D Palm Desert, CA 92211 Subject: Palm Desert Redevelopment Agency Henderson Community Building Change Order Request O1R1 —PCO #O1 Dear Mark, Steton Consriuction Group respectfully submits our Change Order Request O1R1 reflecting changes to the Handerson Community Building Project in the amount of ($3fl,012}. This change order is for the following scope of work: STETON CONSTRUCTION GROtJP 145 S. State College Blvd. Suite -050 Brea, CA 92821 (714) 255-7080 Fax (714) 255-7086 Ltc. No. 641454 inio@steroncg.com www.steloncg.com Replace built up roofing required in the contract documents with Foam Roofing as requested in ACD #Ol dated 08/15/06. � p? •�� •o% We are requesting a 0(zero) catendar day extension of the contract time duration as a result of the above changes. If you have any questions regarding the above, piease contact me at your earliest convenience. If not, and if the above meets with your approval, please sign below as your authorization to proceed. Please note that Steton reserves the right to recover any additionat costs resulting from the a6ove listed Owner requested change. Sincerely, ST�TON CONSTRUCTION GROUP ���� � ��--�- Justin Kazak Project Manager Cc: Phyllis St Georga ! FiSe Mark Chappell Construction Manager DaYe AccepYed S:UobsWende(son Community BuildinglChange Order Requests Hcnderson\COR Ol - APP20V6DLSCG GOR � l- 07-0I-2Q.dac HENOERSON COMMUNITY BUILOtNG PALM DESERT,CA 2006�3D5 Replace Bulit Up Rooting Wfth Foam Rooflng Steton Conatruction Group � SCG RECAP PCO 7 ACD 1 COR 7R1 _ _ �__'�—' _' . Ifl "_l2)" l3� �, �I 1, Straiqht Time WaaeslSalaries- Labor I 2. Frinqe Benefits and PaYroll Taxes - Labor � 3. Ove[time WaqeslSalaries � 4. Frinqe Benefts and PaVroll Taxes - Overtime �IReCr � 5. Meterials and Consumables ltems � COSTs � 6. Sales Taxes (On line 5) � � 7. Rental Charpes � � 8. RoValties � 9. Permits _ I f0. Actual Costs (Sum of Iines 1-91 _ � 11. Sub-Sub (15% of Line 10; col 31 f� 12• Subcontractor (5% of line 10; co1.31 FEE i 13. 5ubcontractors (15°l0 of tine 101 � 14. Conhactor (5% of line 10; col. 2& 31 � � 15. Contractor (15% of line 10; col. 11 � 16.CoaVacto�s Fee (sum of �ines 12-16) I SUBTOTAL 17 ADDITIONAL COST (Sum of lines 10 & 17} I ALLOWANCE 18.,Insurance & bonds (2.0% of line 171 I TOTAL �9. TOSAL COST ` {Sum of Iines 17 & 1 B: col 4) GC 0 0 0 0 0 0 a 0 0 0 (1,4011 0 (1,4011 2nd 8 Lower 1st Tier Subs Tfer Subs 0 0 0 0 0 0 0 0 0 0 0 0 0 D 0' a 0 0 0 • ., . 0 (<) - 9I TOTAL I 01 0� OI OI 0� DI 0� o' 0 OI 0� 0 0' (1,401)� 0, (1,4�1)' (1,401� (28,0221 OI (29,423}i (281 (5601 0 � (588}� . n�..- -,-J,� -- � '�'t5':',Ss!�'��,—�:;4;r°;�{i'�,:f�1;Ull"'i.'k�'i}i,���ilp,ill,i�e'..�"' � � ��!iPqyl���y����Cl�t;'d;,;.��;'I�6.,�ii�ii.{�.,i{�ii�li;;c��� 'I,; .i�f�Iiiv`�:^k�i�: _ �30012). An additional 0_ working days (0 calendar days) are requested to be added for schedule delay purposes. Steto� resecves the right to recover any additioaal costs �esultiag from the abova listed Owner requested change. 9(2Q2�O12:1tPM B.UabsLLlantlenanCommunLLy0u0tling�CM�yOMderRequmbHantlersantCORP1-APPROVEDISCGCOROI-W-0B-YO.xBRecep I � O H � U � � � m ( � y � � � d, i M O O O 6 o O O N o N O O O O O O O N O O O N N N O O O O O O O O O O O;%:I. � �f �'' � O �i'1��; ,C� ;d�, �Ii jl �I�li:� .I(� Ilil� 'til:'� i�',:r' :i�i�. `'+"�!'�;'i:`i �i;�Y �;;I,. ',,;� ����L'� .�i � i - - =;i^.� �i �;T — -^' ,.^G,,ii;i�,'4+'^ o 0 0 0 0 0 0 0 0 0 0 0 6i2�., ;,;.�. o�:4' ;,, ' II� O O O O O O O O O O O o p O O O O O O O O O C � � r u`�° �"iTdl ��N N Q � a4U �� i' r, � z a � H � 0 W S li! 0 � � � C O � s LL � � 8 a a � � a °� 0 m t° ea m Na a 3 C � u � e 0 �.i c � � O c7 O O O O q soso f�D W .r... � 0000000wocoo � � v v g�g .' � i�i�� r��l,� ' Fi;;�`.;��:';o���� '�:i iF;:{d s��i� O ,;�t'i �I�j�� �ik�ii�� o ' d� ?�i'�'r�. : G:; i:� �iP F 'i,y:�„� i�F��; j��i�l: ;,�,� ���,,; � �; �.��i I�� ���i� ..;i�l im�,�pk' o :ri��ii'f+49; �,pr o I l�.i.i � �,� �;.i ',���iil� �4�1� ��iil4�':� '�'''�r��!� o-_,: s ;;.'; . � � liy'.'l�!I��i��jtl � iltli � 1III ��pl,ry. .�'.�� ��. � ��I r '�� h t i � ��i�f e'..is :��p,7r.: — :;b :.��Tv'� � !'si�li �,�L ��i,�� W �,ii�i i��!' 1; I p:f � k1 � i I�� ia: , i,iI, i i I!I; �S *I�� ,klti�� �..ti..y�����:�:4yV\ � � � � a � � � � � �_ � �I � I a y o J O a � y � W N � � � ~ ~ rn o I . y (0 p yy Q n^ � C � N 'C N N � G Na�o.�� � � "I ��a�o� ;a " o� �s m P m U p v � o �' V� I £ �c m �c a � n i- m 3 m`c° � t �°y m z`� w m v� v a y �� E� � N�� N U�� y � y 0�{. �� c N c � v c i ^E > > > > � � � � p ,� cn ii O u�. � in �� a¢= Z z° r i z z z¢ E .= c�i �+i V vi � r ca ai p �.N- .M- .�- ^�^�� � �� -----_...—..._�_ W _�_..__ F U � � Q J �N O p LL O p U j F- a 2 d K a in � R 0 N �h 0 0 a n � N m Steloo CouatrucHon Group. Brd, Cailfornln SUB DETAII. COST PROPOSAL BREAKDOWN 11'EM 7 2 3 4 5 6 � a � a1 � 10 � � 11 � � 72 � � 13 � _ � Riverside Regional Park Headquarters Annex Replace Built Up Roofing With Foam Roofing Ari-Thane Foam Prodcuts, Inc. , CIS SUBTOTAL I - � - � 1 ' I � - � I - � � - � + ' i 70TALSTLABOR/QTY� - CLS SUBTOTAL 1TEM DE$CR[pTION t 2 3 ITEM 1 2 3 4 5 6 7 � 8 � � I� � 1 Lump Sum For Foam Roofing � 2 I 3 �M � 1 � 2 � 3 ProJect Name: TiUe Of Change: 3ubcontractor Name: DESCRIp'CiON TOTALOTLABORIQTY ATL DESCRIP140N p REIVTAI. QTY PCO 1 ACD 1 COR 1R7 � wece �.f> sErrs[frrs � U Q'CY RATE � AhTf- RATE � AhTl' HR - . HR - _ HR - . HR - _ � ' ' � ' HR - - I ' ' � - HR - ' � ' ' � ' HRi - I - I - I - IHRI - - I - � - I - � HR � ' ' � ' I � - I _ I HR • - � • r - � ' � HR - - I - • � - � HR - - I - � - � HR ' ' � ' ' ( ' � � ' _ � ' � ' Q7'Y WAGE(oQ BENEI�IIB � U HR RATE AMT RqTE � AMT � HR - - _ . � HR - - - _ _ � HR - - - - � - I _ , ( � M7T MTL RENTAL CHARGES MA7'ENAIS ' � U QTY RATE � AMT- RATE � AM1'- �' - I - - ( _ - ( - � - � ' � ' ' ' � ' ' � _ I I - I � - SUBTOTAL� � + � TAX� � I � TOTAL� � � ( DESCR�'I10N TOTAL� DESCRiPTION - I - I • I � - +� 7.75 � � - 1 � ROYALTIES OAT1' QTY- I RATZ LS t,001 49,578 I � � I � � , � TOTAL� � e&ntKtxs QTY RAT& - I ' � . � . � ARTf ( 49,578 � _ � 49,578 m SCG COR 01 - 07-03•20.x1s 1 of 1 3/20J2007 Mar 14 �7 12:tip ���j� 9Q96664736 p. l � tp // V\ G6R-�kGI /`/��..�". ,�,2<'l�— i.sr�,�/ 14965 La Palma pr. Chirtp, CA 917t0 � 9p8-606-4717 Phone 909$48-q736 fa�c Qarryl $coit 96'1-453-3708 CeSI E-maii — dartyi@arithane.00m www.aritbano.com f __���� 'ro: John r-a�� 714255-7086 rho�eac n� Rev�sed Roof Prt�p5a1 F� Darryt rsgae: 1 + Cover oate: 3/74l2007 CC: ❑ u�t o�or �w ❑ wca9e co�c � rreaso Rar,ry o rw�. rtocxue • Gommen�s: John, The attachetl Rroposai retlects prlang changes requined tar our prevailing wage rate, as fequested_ � o�, .�y a-7 piease contact me with arry questions or concem5. Thank-You Darryl Mar �24 q7 12x 11p 9096064736 p.2 � . . :�'+5+'�' -' 14965 La Pwimp Or Ghi�u, CA 97710 Pho1re: 909-808-47771 FaY: 909-806d736 _� �l Reaidantial Licence 277593 ! CommorGlal License 887790 �� � ww_kv_,artthRirie,com y ,,,,,,,��..�.� .,,�,,,,,, , ,,,,,,,,, ,,,,, ,,,, , ��,,,,,,,,,,, ,�,�������,�, � ,,,,,,,�,�, „�,,,,�,,,, � , „ ,,, ,,,,,,,,,,,,,,,,,,_� _ I PROPOSAL A1HX? ACCF,PTANC'E ( - � DATE:3H4t2007 - = CUSTONER PROJEGT = = I S1�mn Co�Wction i Hendaraoo Gommunitv BuiWinq � _ - ! 145 3. l3hLr COIICQe. SEE I/50 i 72-659 Hwv'1'1'I 1 = = 1 Brea, CA 92821 -- 1 Palm Docart CA 99260 I ' I 774255-7080 ph 1 -. ' I 7�42S5-7Q86fnss i "'ALTERNA'it WD•" _ _{ = 1 A1ln_ Juatln i pREVAILIN[i WAOE PROPOSAL � - _ „ , , , , , ,.�, �,,,,,,�� � .,, ��.�.��,,,� , �„�,,,,,�, , „ ,.,, „ , , ,.„�..� � ,,,,,,�,�,,,�,,.� - = APPLICABLE SPECIFICATIpN3 CHECKED iN ORDEiL TO APPLY A GLASS "A" 3PRAY POLYURETHANE FOAM ROOF SVSTEM = - TO THE 9lJILO1NG, BASE6l7N APPROXIMATELY§ $QQ 8Q_ FT_ ' = SPECIFICATIONS: �T"rtto 24 �'Coot Roof^ cnmpflant) - _ i. Prepare It1e new oonc�ete roof surface as neoessary%r tlie proper applicallon ot SPF. Reet nurtaca must br depn ond tlry_ � = 2. Maek as naceasary to protecl property and equiprttant from ovarspray. - J. Prime roof detic wi{h SWA 2W0 saa�er at a rate of h gn1, per t00 sq. ft, avarage , ae nooeasery. _ _ 4. Apply a � irwh (Ra) Mickncss of SWD 125b 3.0 dmaily poryyrothane foam tn We roaf wrfoce. � = 5. Buildup foam tn provida a•h ineh per toot (faparatl) slopa to drain .00F syatem. = 8. Build-up foam to twm all aickc4. at Y. inch per foot as raquired. - _ � 7. Foam osnl th¢ 6nck4ido of Uro parapet walb to approx, 12` ebove Iha dndc. ' a- Foamseaia/celbowductpeneua�ion». 9_ Cont efl new foam vririr SWO'192BF (GREY or TqN) elestnmeric basocoat at � rate of 1 gaL per 100 aq. �. _ '- '10_ Appiy 3Wp'IQ28F "Kml-KOMTM lVJHIT�Fj" elaStOmMSe t0{xoat at a tt�tte M 7_6 gals. pgr tpt7 oq. ft. - (SWD t929F ICOOFKpio*" coaling tn an Enetpy Starl CFaRC �np4nM, whito, high'ofloeMrlto COOtlifp o! B39G wlfh 8536 thartnai emiyv'rv�{y) ' - 97. 6�oadcas2 tq qranuWr wafae into wef topcoee (roof suRece onN). - = 12. Clean and Ugtaii pemisen. - . � ar�s s to-YF6R `•RFHFwARLe� �S�NciLE SO�IIRCe� No �FJ�K w!![tf2A1VYY (Msintenirtw COnNacla NDT RnWil.vdj - (" wam�xy Eamneton requiros mainronaneo pteeadu� at end o� er:ginoE wnrmrrty, et aadafona� eost a�ltlition�l Tercn6 ano Co�MWo�e may appry7 - - BIO BOND / PERFORNANGE BONO! 61JILOIN6 PERMI7- NOT INCIUDED - -� NO�S; Structutai co�rbt@ r00( �tetk m Wt bc OtIOwCtl to airo frx 30 deyn p�ip[ lo foam rool eppllcelion. _ _ YAWE ENGINEER SENEPITB� Tna fellanng xe NpT teqaimE with tha SPF rtwf Fyatam apedM1eO s6ove� fSy i9AWLL, SIIpCLJy1M2� CpUIlIO(fI06NM19F. _ ' IenC flnahinge. catlt s��. plcch podcetn and ar�u amuanu. - We agree to rumish all labor, mafe�iaats, eq�tipmunt, atC, to completo the woiic tlesedbsd otwve as per Me specifica(rons, Er�bjeCf to Gw terms antl candifions conteined herorn and on Me �everse shfe ofthis page. Thic proposelindudes el! applicabfe taxes a�+U helght c�arges. TOTdL PRIG�- sR9 T+A On /i�RTY NfNL THOUSANO q H ND�O AND SEVEN7Y E/GNT DOLR,.ARSI (Yhls Pcp�va� may be wilhdrnwn 6y u1 H not aeeePted w"rihin 90 daya) PAYMENT TERMS: PFi�GRESS PAYMEPffS WITH 100% Ol.IF. t �PON C.OMPA FftON ffF WnRK PHw EsceMtion Nottea: Wnpmtlirtab�s increaaea in taw matcrial cOsts Itave iotCeo oUr pnta P��b� to Oe ItrnileA W 30 qaYa. SpecRwny. pru p�nteGien is limded ta malefi4la pu�Ch050f1 dMl app1lM Wi(hiR �hio 30-Ony p9riad. AfLT11a� FO�(Il PfOdUCfC, If1C. ehall bp wibwctl �a peia LI�Wph _ lepitimate mafeAUl i�C�eaes5lneunad aft�r tliiv 36qaY PM1OB Prolecfim perioQ. = Upon payment in fvll, ARI-THANE FOAM PRODUCTS. 1NG vriluasue a 10.Yter fwewabie warcart[y as snecilfeq abovn_ Art-Tharte Foam Protlucts, Irtc. '4--�w�a7-V� � � �oartyi sirottj ' _ ACCEPTANCE OF PRqPOSAL— The aGovp pfipeg, sneciRcauens antl contliNona aa wel� us the condlHona on tlre revarae aids of thin - = cqntrad have bean featl, are salisfactory anO are hereby accepte6. Final payrpent will be mada pr4mp�ly upon oompietion. Ari-Thane is = = autnorized m peAo.m tFw woAc as specFfiotl. Unbaa apecified, Tetel P�oe' doexs fwt inclWe: weekends, overtima or holitlays. - = SIGMATURE: pq7c- _ ; x�. : i: �� £�.' .. ?... s__£�_ .yj� �i .• �. : �� ,. • . March 2, 2007 Melissa Wightman Project Coordina[or City of Palm Desert, Redevelopment Agency 73-510 Fred Waring Drive Palm Desert, CA 92260-2578 Subjec[: deb Project #6016 Henderson Community Building Entrada del Paseo 72-559 Highway 111, Palm Desert Re: Recommendation for awards of Cl�ange Order — Steton Construction Group — COR #2 Ms. Wightman, We have reviewed the attached documentation received for Change Order Request #2 from Steton Construction Group for the above named project. Based on our review, we recommend award as follows: Change Order #2 — Perform inigation modifications per owner direction. � O� � 12' �� Recommended amotmt of Change Ozder: Sincerely, �� � Mark Cha�pell, Senior Project Manager douglas e barnhart, inc. $5439.00 March O1, 2007 STETON CONSTRUCTION GROUP 145 S. State Collega Blvd. Suile 450 Brea, CA 92821 (7'14) 255-7080 Fax(714)255-7086 Lic. No. 641454 Mr. Mark Chappeli Construction Manager douglas e. barnhart, inc. 41-495 Boardwalk Suite D Palm Desert, CA 9221 i Subject: Palm Desert Redevelopment Agency Henderson Community Building Change Order Request 02 — PCO #02 Dear Mazk, Steton Construction Group respectfutly submits our Change Order Request 02 reflecting changes to the Fienderson Community Building Project in the amount of $5,439. This change order is for the following scopa ofwork: ���y�,�Z.p-7 Perform irrigation modifications per Owner direction. Please note that this does not include the remobilization charge for McKenna work stoppage due to this and existing grade change issues. We are requesting a 0(zero) calendar day extension of the contract time duration as a result of the above changes. If you have any questions regarding the above, please contact me at your earliest info@stetoncg.com convenience. If not, and if the above meets with our a roval lease si below as our wvnv.stetoncg.com Y PP � P � Y authori2ation to proceed. Sincerely, ST�TON CONSTRUCTION GROUP ���\� � �� Justin Kazak Project Manager Cc: Phyllis St George / Ruth Fernandez / File Mark Chappell Conshvction Manager Date Accepted S:VobsV-lenderson Communiy Duilding\Change Order Requests Henderson\COR 021SCG COR 02 - 07-03-01.doc HENpERSON COMMUNtTY BUILDING PALM DESERT,CA 2006-305 Irrtgation Modtftcations Per pwner Dlrectlon Steton Consfructlon Gcnup fl SCG RECAP PCO 2 ACD PJ/A COR 2 — �» -- - �zl - -- �3� ���. 2nd & Lower GC 1stTierSubs TierSubs � 1. Straiqht Time Wages/Salaries- Labor 0 0 0 I � 2. Frinpe Benefits and Pavroll 7axes - Labor 0 0 0 � 3. Overtime WaqeslSalaries 0 0 0 ' 4. Fringe Benefits and Payroll Taxes - Overtime 0� 0 0 � DIRECT I 5. Materials and Consumabies Items 0 0 0 CosTS I 6. Sales 7axes (On line 5) _ _ _ 0 0 0 �� � 7. Rental Charpes 425 0 0 II � 8. Royalties 0 0 0 � 9. Permits 0 0 0 f 10. Actual Costs (Sum of lines 'I-91 425 � 5 017 � 0 � I 11. Sub-Sub (15°!a af Line 10; col 31 �t.>;I�.i�j4��,�1�p���l��l�'�ti���.ilil;:_.I�IFpl�tl<<ry���i��.��'1�� 0 ;;r;rvn e���u��l l� s"N�'1 i!I�q1�N ':?i�',�y:(�: ii��:; , i.'i '' 1 �� i �'ie`„ S I' �!':' i� I12.Subcontractorf5%ofline'IO;col.3) �;'d,n;i!.lii�,ii' ��at��.1�iM1';fi�7�ni����,E��11��Wi.:F��?Ini��Wl��!PdI:uV�p:.r�IF:�"j.j. I he;�n: AIP:,-t'' rq� r, ��e� tJ ��': �i:.'fi¢�4'S4,'�I�( �tµ"+8�i•si'il@�: F�k . FEE I13.Subcontractars(15%Of110810) �):s(,'(:5p;�f.l;pi�!ffil'la��lt:���t�,%r^.6�'.;iilfAl�^„����'M�i;�.k�k�ol,C:r�::+��1.� � 14. Contrector (5% of line 10; coi, 2& 3) � 251 'r�w.��i,���i�;h"�y��j4,,.�j�(�� �NI���l14,ri���,j�E�'ip�;�;„ I 15. Contractor (�5% of Ilne 10; C01. 41 � 64 �'.n,",�IFCIiII,j�U��j�iis��+;r�i�?�S'���'��tYi�I�l���l�'�1�^,:�.� ��:�, 5;�,.i���,ir�� r �� t 16.Contractors Fse (sum of lines 12-16) 315 • ui:C,:a�1�;�;;r,I�1oi�};�7H� 0 I SUBTOTAL 17. ADDITIONAL COST (Sum of Vines 10 & i7) I 315 5.017 0 � AlLownNCE 18. Insurance & bonds (2.0% of line 171 6 100 � ___ _. 0 19.TOTALCOST ;..t�,hnii!ik��'�,�Nb'��P�,��i�.:,.�,..}q:�r:l"ii"!LY.II�'„I}�A,i:�., ,:��.�:cr ( TOTAL I i��ii�,lI'��'4�, �F;I�w�s"�;liry'�TV4�lql�i�h�t�i��',.+;'r�- t'�,i;�`I44j; (Sum of lines 17 & 18: col 4) �;�Iu��.,Villilln��liu:F:i';'��.+,'a i �+rr,r,.g,l�;��y�:�i��tiFu. ,E'.{'ti::i:;, ;��?. An addiGonal 0 working days L calendar days) are requested to be added for schedule delay purposes. Steton reserves the right [o recover any additional costs resulting from the above listed Owner requested change. — �4� TOTAL OI 0I Oi 0, 0 0� 425 p' 0� 425 0� 0, 0' 251 � 64 315 � 5,332 I 107 ; 5 439 � 3I]/200]8.35AM B.UOCaWendeisonCommuniryBmlEin9�C�anpeONerRequefbHonEoponlCOR02\SCGCOROi-0]-0]dt.�6Pewp Steton Constn�cHou Group - Brea, Csltfornla GC DETAII., COST PROPOSAL BREAI�OWN Project Name: Henderson Commu�ity Building Title Of Change: Irzigation Modificatlons Per Owner Diredion ContraCtor Name: Steton Construction Group �I'I'EM � 1 � 2 ! 3 , a � 5 � 6 � 7 j B � 9 � 10 � 11 � 12 DFSCRIPTION CL9 SUB70TAL U QTY - HR - - HR - - HR - - HR - - HR - - HR - - HR - - HR - - HR - - HR - - HR - - HR - - HA - WAGE (at) RATE AMT - � - � - I _ � - ! PCO 2 CCD N/A COR 2 BENEF3T9 RA1'E � AM7' � TOTAL 37 LABOR f �TY - - I • - Q7Y WAGE (at) BENEIQ'CS �TTEM DE3CRIP770N CLS SUBTOTAL U ffit RATE AMT RA1'E AM7' � 1 ( - HR _ . . - � - � 2 HR - � 3 HR - � TOSAL OS LA80R 14N I RTL RENTAL MTI. MT4. 7tENTAL CHARGS9 MATERldl.4` TI'EM DESCRiYiTON U QTY U Q1'Y RATE AMT RATE AMT t- ' ' ' ' " 2 ' " ' " ' ' 3 ' ' ' ' ' ' 4 ' ' ' ' ' ' li 5 ' ' ' _ ' � ' � � 6 Trash Bin LS 1.0 - 425.00 425 - � - � ` 7 ' ' _ ' : � ` � I 8 ' ' ' ' + - � �� SUBTOTAL� A26 I - � TAX - 825I • ( TOTAL� 42b - � ROYALI'fE5 ITTgM DESCAIPTION � UN1T Q7'Y RA'1'E AMT I 1 � ' ' ' ' 2 ' ' ' � 3 ' ' _ � 70TAL � - � PERhIIT9 `TTEM DESCRIPTTON L3NTT � QT1' RATE AhfP I 1 � ' ' ' I 2 � ' ' ' I 3 ' ' ' � TOTALI I - SCG COR OZ - 07-03-Ot.xls i ot 7 3/2/2007 a v W � m � � 2 � Q �"' �- o O O N W O O O M O O O V' O O O I� �+Nj m O � W M (D O � (V �t � O O O O O O O O O O O �i..�:'�•�t} � OI�I � ;};,;y �':`.:; ;��; �,;�iii; k71i':,'l,;:�; ';:;�; r; �' :'" �!,r, �t_,r }:;,i .i�i��'.i:;: ;c: :, : , .;u ;� <; 0 0 0 0 0 0 0 0 0 o a, p;��'{� o I�j;,: t.u� liitii �;J i � :,� ,rr��t il;l�'S� ;; �'�i ����','{ .i i: in 1�1��� d t i,`� r'��., �t�x. .�, k a, �t.'i�� � �� � �j �Ir�'f�t i': � i � Pi��� ?,! .4 : �;{.j '�!r�? �'�=° 1,,;,��� �;�. �;i�+.;`�;`, , 0 0 0 0 0 0 0 0 0 0 0 0: ri �`�M �rr{� dk:?, °;9i�'n,"a�l;lli �i�rJe i+t'�`:; `�' � � '�*?�'! "SM,t.,.n�IT� � Ni�1:i.✓,:' k�w,l,'Jyi^;��tl. ri.i � ::: "q ' �7�1 � `ie ���y i i,;;. . �-; ��1�i'� �!,�i< .:: o�,`; yl!'I?' .1V r.!'.: 0 0 0 0 0 0 0 0 0 0 o j;�,is,�;; o r� ci 2 O J � m z � �2 �` � U 2 O Q.' W 0 Z W N�N aUU C ',�A � � C � N C � � d a C 0 a � � 0 0 0 �E N .� 0 0 0 0 0 0 0 0 0 0 0 N , O O O N 6f O O O c') O I E� PN'J m O�� M = 3 '- �r r v C N � N D � C a �o J a � 0 � � e U I C i U ' � I � � 0 � � C o,: I, n O �i � W E `o C S] j o J O II ' ' y � m a�'i E � � °% m 0 0 F' � y .- N m O 'O � N C y a� a E u' - o a m � w `o e F- +- >���� o= E 9 � � atS ? N � N U Q � N O �1 O r E N m N c N �' � 06 TS Z O � 3 � m v� y �� E m 10 I- �� N C7 C N N C N N N O N o' Q C �O. N N c i� � �>> p 7�� ��- �� ����� a a t'i ^ o o� o o S � o Q Z Z N Z Z Z Q c� �(V M V' �(> tD Ih � W O r�� C� t0 i+ �� .- r �- fn ---_�--_— U _,_— W y a W I-¢- � p � � O p U � Q ryn & K � N % O M ri 0 � m 0 N M Steton ComtrucHon Group-Brcs, Cslitomin I7'EM 1 2 3 4 5 6 7 8 3 +o �i �z ( 13 � CL4 SUBTOTAL U JM 2&4 HR JM 284 HR FM 113 HR JM 267 HR JM 267 HR FM 106 HR - HR - HR - I HR QZ'1' B.00 8.00 8.00 7.50 7.50 7.50 WAGE (at) AA1'E AM'1' 35.54 284 35.54 284 74.17 113 35.54 267 35.54 � 287 74.17 � 706 - � - _ � _ � - � - � - I - 1 - � - i _ � - � • � I ' IHRI ' I I - IHRI - I I - IHRI - I, I - �HR� ' I TOTAL ST LABOR f qN L321 � � 46.50 BENEFf['S � �� i �._ , I . � - � - � - � - � ' � _ ' Q1'Y WAGE (ot) ( BENEI� R'S � iTEM DESCRIP'I7ON CLS 3UBTOTAL U HR RATS AMT Rp7'$ AM�I' � 1 Labor To Install And Motl{fy Irtigation (09/03/O6) JM 13 HR 0.25 50.47 73 - - � 2 Labor To Install And Modi(y �rdgation (O9/03/O6) JM 13 HR 025 50.47 53 � - - ���. 3 La6or7o Inslall And Modify Irrigation (09/03/06j FM 5 HR 0.25 20.12 5 - - �� TOTALOTLABORtOTY 30 075 30 " ��, RTL I2ENTAL MTi MTL � RENTAT.CHAHGES M.ITERTATS � TTEM DESCE[STlON U Q'CY U QTY � RATE � AMT RpTE pMT � 1 4" PVC Pipe Schedule 40 • 300.0 - 2.91 . 873 � 2 2" PVC Pipe Schedule 40 - 150.0 - 0.88 147 � 3 1-i@" PVC Pipe Schedule 40 - 150.0 - 0.72 108 4 Yellow UF Wire - 1,000.0 - � . 0.17 170 5 Red UF Wire - 500.0 - � - 0.17 85 6 Black UF Wire - 2,500.0 _ � - 0.17 425 7 3/4" PVC Pipe CL200 - 200.D - 0.42 � 84 � 8 � Wira Connectors - 40.0 - � - 2.66 � 106 � 9 � Valve Box - 1 2.0 - I • 25.SD � 51 � 10 � 3!4"ElectricSweep - � 3.0 - � - ( 0.86 � 3 � N � Backhoe � i6A � � - 50.00 � 800 � - � - � � SUBTOTAL� � � � � 800 � � 2,062 � � TAX� ( . � � � • � 7.75 � 169 � I TOTALI I � I I 800) I $271 I ROYAL'17FS � Ii7'EM DESCRIPCION TJ[y1T Q�[y gp7yr pMT � 1 I ' ' ' � 2 � 3 iTEM t 2 3 � Projsct Name: Title Of Change: Subcontrector Name: SUB DETAIL COST PROPOSAL BREAKDOWN Henderson Community Building Irngation Modifications Per Owner Direction PCO 2 ACD N/A COR 2 Platinum Landscapa, Inc. � DESCRIP"fION la6or To Install And Modiy Irtigation (09/03lOB) La6or To Install And Motli(y Irzigation (09/03I06) Labor To Insfall And ModiTy Irrigalion (09/03l06) Labor To Instail And Modiry Irtlgation (09lO4/OB) Labor To Install And Modlry Irrfgation (09/04/O6) La6or To InsWll Md Modify Irtfgation (09/04/O6) TOTAL I I PERMTIS -- - DESCRTP170N U1VIY' QTY RATE ( A1NT - - �+ - - • I - � TOTAL � � SCG COR 02 - 07-03-Oi.xls i of 1 3/Z/2007 l 12: 19 FAX Platinuxn tandscape Inc. 77588 El Duna Ct., Ste. �' Palm Desert, CA 92211 760-200-3673/Fax:760-200-3623 �.ic# C27-820893 6111 To STSTON CONSTRUC.TION GROUP 145 S. STATB COLLBGB BLVp., STE450 BREA, GA 92821-59t8 HeNDfiRSON BLDG. JOBH6016 pesCdptlon LABOR 9-9-2DOG � I.ABORSR LABOR 9-3-2006 � LAHORER LABOR 9d-200G � LANbSCAPL' TBNOER L.4EOR 9-3-200G - [.a60R LABOR 9•3-:00( � 4ABOR LABOR 9-3-2006 � LANDSCAPB TEND6R 8QUtPMEN? 9•3-200G I AROR 9-4-2UOG � [.A130AER LABOR 9-4•20D6 � LABOR6R LABOR 9A-2006 - LnNDSCAPB TENDER EQUWM6NT 9-4-3006 PVC PIPE SCH 40 4" PVC PTPE 5CH 40 2" pvCPFPS SCH a0 I l/2" UP W(RB YflLLOW UP WIRBREp UP WIRE BLACK PVC PIPECL20U 3/4" WTRk CONN�GTOR'S vpV L& SOX ELBCTR IC S W BEP 3/4" SUgCONTxaCTOR MAxKUP S3105 T2% Quentity 8 8 H 0.25 0.25 0,25 B 7.5 7.5 7.S 8 3U0 I50 I50 i,AUO 500 z,5o� 360 40 2 5 t price Each �5.5a 35.34 14.t? $0.47 50.47 20.12 SD,00 35.54 35.54 14.17 50.00 2.91 o.9a 0.72 0.17 0.17 n.�a u.ax 2.658 25.50 0.98 G54.00 i.%$% f� 002/002 �tlY01C(.' Dale Invaice # 10/16/200G 7543 IP.O. Number � I � CUR % 1 10f2� % Tatal Oue Data 10/18/zUOG Amount 284.32 284.32 I 13.7G 12.Gz 12.62 5.03 qQ0,00 266,55 266.55 106.28 a0a.0o 8'73.00T 147.00T 106.00T 170.00T 85.00T 425.00T sa.�oT 10f,.32T $ I.pOT 2.44T G54,00 159.�5 55,016.96 .! `!; . . .: - . _ March 2, 2007 Melissa Wightman Project Coordinator City of Palm Desert, Redevelopment Agency 73-510 Fred Waring Drive Palm Desert, CA 92260-2578 Subject: deb Project #6016 Henderson Community Building Entrada del Paseo 72-559 Highway 1 I], Palm Desert Re: Recommendation for awards of Change Order — Steton Construction Group — COR #3 Ms. Wightman, We have reviewed the attached documentation received for Change Order Request #3 from Steton Construction Group for the above named project. Based on our review, we recommend award as follows: Change Order #3 — Import and compact additional soil due to existing grade difference from what was indicated in the contract documen[. j-x>�'� o�� �Z•07 Recommended amount of Change Order: $39,687.00 Sincerely, Ci' .� Mark Cha pell, Senior Project Manager douglas e bamhart, inc. Mazch O1, 2007 STETON CONSTRUCTION GROUP 145 S. State College Blvd. Suite 450 Brea, CA 92821 (714) 255-7080 Fax (714) 255-7086 I.ic. No. 641454 infoQstetoncg.com www.stetoncg.com Mr. Mazk Chappell Construction Manager douglas e, barnhart, inc. 41-495 Boardwalk Suite D Palm Desert, CA 92211 Subject: Palm Desert Redevelopment Agency Henderson Community Building Change Order Request 03 — PCO #03 Bear Mark, Steton Construction Group respectfully submits our Change Order Request 03 reflecting changes to the Henderson Community Building Project in the amount of $39,687. This change order is for the following scope of work: Import and compact additional soil due to existing grade difference from what was indicated in the contract documents. �.(� � 2, �2 • q7 We are requesting a 0(zero) calendar day extension of the contract time duration as a result of the above changes. If you have any questions regarding the above, please contact me at your eartiest convenience. Tf not, and if the above meets with your approval, please sign below as your authorization to proceed. Please note that Steton reserves the right to recover any additiona! costs resulting from the above listed Owner requested change. Sincerely, ST�TON CONSTRTTCTION GROUP Justin azak ��� Project Manager Cc: Phyllis St George / Ruth Fernandez / File Mark Chappetl Construction Manager Date Acceptec! S:VobsVHenderson Community Building\Change Order Requesls HendersonlCOR 03\SCG COR 03 - 07-03-Ol.doc HENDER56N COMMUNITY BUILOING PALM DESEF27. CA 2606-305 Add'I Import Due To Dift. In Grades Wlth Actuai CondlUons Steton Construction Group K -- -- DIRECT COS7S ��� iSUBTOTAL ; ALLOWANCE TOTAL 1 Straipht Time WaqeslSalaries- Labor 2 Frinpe Benefits and Payroll Taxes - Labor I 3. Overtime Waqes/Salaries � 4. Frinpe Benefits and Payroil Taxes - � 5. Materials and Consumabies Items � 6. Sales Taxes (On line 5) � 7. Rental Charqes � 8. Rovalties � 9. Permits � 10. Actual Costs (Sum of lines t-9) � 11. Sub-Sub (15% of Line 10; col 3) � 12. Subcontractor (5°/a of line 10; coi.3) � 13. Subcontractors (15% of line 10) Overtime � � � SCG RECAP PCO 3 ACD N!A COR 3 � (,) — (z3 (a) (a) ��, 2nd & Lower TOTAL I GC 1stTierSubs TierSubs I 01 OI OI 0' OI 0 OI 0; I OI O) OI 0 I OI OI 0 0: I OI OI O) 0: OI OI OI 0 OI OI OI OI OI OI OI OI OI OI OI 0' 0 � 37,056 � 0 0�, '���-! !�f i!fi �uqi���P� �„�n,i*� "i:i;�A ��i�I I I }Ir��.ilflN,��a�ft4.�d ��� �I'If� ���n��u�uA���ili;�i iu� 0 � � �i�>:dS;+iiht�l�tE��4aj��oY�ti�"W`i��i:�A�;l�'��.,Ufjil�j L��R:,v4v��,itri�f;yH%�' �tir; I ; .. �� �. a, � ., �,G <» ��� : u�l;:� � �=,,. � ;• v:tl,. �;,I o �,��K�r��•^��t� .rr:11�,,��i el;q',..h.{;i�y�: ���µ'�i i�i �5;i:.n� �I�I�iSip;.o � .:::iii.t.y!,:I}aFii!:fi!vlr��h�i.�S�;!fiin;im;N:4✓.,1�'��.f;Ii:1i���t;>�Ilail'I�d�1Y'.F,lu+ilii=� 0 : � 14. Contractor (5% of line 10; col. 2& 3) I 1,853 (j� �' �i; h;! �idi'iwW��l`nA���a�j�ifi�if�`a�Ei���l�u�i� I 15. Contrector(15%ofline 10; col. 1) � 0_1�i��;,. lii{��;�nl':����ii��5����;h�il�4.��'�IH���Sll��ii`.��'�%i�iy � 16.Contractors Fee isum of lines 12-16) � i,853 (;1y;�lj�;��"pl;�+��?r��i��l� 0 � I, 7(Su�m'of I�'� es 10 &S 7) I 1,853 I 37,056 I 0 I � 18. lnsurance & bonds (2.0% of line 17) � 37 � 741 � 0 � I19.TOTALCOST � ��i'�:'il�Y�i';i;{:jjljl; ;?11 q;iil'i`:'IP'��c;;ll.� �'ri:3�'i�. ^�,�•^;�� „: ,���iii ���`���;:I��;., ��;;;��.�:i{'.:j�,l (Sum of lines 17 & 18: col A) Il��iin�r,�i�;i§�c,$:9;4�fi;li���!I.�;,tde%i'I��i(:L•' : E' i:r'! 1• ,:�,. ,i:,�'. � An additional 0 working days (0 calendar days) ara requested to be added for schedule delay purposes. Steton reserves the right to recover any additionai costs res�iting from the above Iisted Owner requested change. 1,853 1,853 38, 909 778 , 39,687 II JY1Y100]83]AM 6:UOESWenQawnCammumryBwlENplCM1anBeDNe�RaQuef�sHenOenon\COR001SCGCOR03-O)-0101.ab0.nrsp a U W � m � � Z 9 � m a 7 g � � U z O � W G 2 W 2 Nf�M 00� a¢c.�i c 0 � 'v e 0 U m � a � m � � c � � H a 0 r N a 0 r� - m9 N Q a 7 Q � � V � � e U c w N F O �� N O O O O O N O O O N O O O� O O O �I � M N N O: N N M � t+�j I 0 0 0 0 0 0 0 0 0 0 0";��"'i:�� �,j�jji�jT;,�� �J9i��;l,�i�' Il,I`i���,�it �.:>� `(:i;;ii, �';,s+t,;;: '�'� .. :!.': � ;, 0 0 0 0 0 0 0 0 0 0 0 O O O O O O O O O O O V O O O O O O O O Q O O � � • r � O' I I � _ _ � _...�.. �-� �-_ i.ili� i`�fii� n�:�I`�:��j �NTi � � o 0 0 o tD CD O O O c) o(�{�il�;�j i(h �..c n'7' �,�r7.i% f0 m c O � tV Iyl4 i� M';:`j!j';3': i�i. � c W 01 th IV �(vi' '���i� °D la'��i ��'.ji: u�:,• o y Lp .- N N M 1 •�I �li'.+ � '°�II �fl�ll ?II���I �•~j�. V � ���� r J��J '�� i�'a �I � m �f� �t,� l� �. i��,�'I� � �- - - - - - -- -- --���-I ilGi�;�- - �r�1: �;��E� "�� d E 'r a � 0`9 O a � � N x xN H N i- �" � � � C _ � N e- @ p y p�^ N� � a a�° d E� c o � �, - � �_`� _ _= e y ' N�s; �o � � o � � � o 3� ��b°" `�� � ��i �N> N C N Q t�l � O J r.� G> C t0 N @ �G Q O ,C m E m <0 I"� C.% N O � C �� ZO N! � `? r� U � � �O � y a> �m c N c:% a_yi c i� �� j�� c> ��� p w. y LL O LL� N�� a Ti _ o o� o 0 0 � o Q z z m z z z¢ E � tV M?�Il f0 1�- W m p ���� M�.n- � ln ---------- W ------ U U F Q � � 0 3 LL o p U � k- Q 6 8 K m' n 0 M 0 0 d� m � � n Shton ConatrucHon Group - Brn, Callfamia Project Nama: Title Of Change: Su6contractor Name: ImeM � 1 � 2 � 3 � 4 � 5 � 8 7 8 9 t0 71 12 13 DESCRIFI'tON TI'EM 1 2 3 DESCR]Y'P10N TI'EM DESCRIPT(ON . 1 Atlditionat ImpoA � Z � 3 � 4 � 5 � s � 7 I 8 9 � 10 � 11 SUB DETAII. COST PROPOSAL BREAKDOWN Henderson Community Buitding Add'I Import Due To DIH. in Grades With Actual Conditions McKenna General Engineering, Inc. — — wacE �6�� 1 cLs sysrar,u, u 4Tr n+'i'e � nnrr- HR HR HR - HR - - - - HR - - - - HR - - - - HR - - - - HR - - - - HR - - - - HR • - - - HR - - - - HR - - - - HR • - - T07ALSTLABOR/QiY - - ' QT'Y WAGE (ot) CL4 SUS'P�PAL U� HR RATE � AM'P - HR - - - HR - - ` • - HR - + - TOTAL DTLABORfQTY - - ' RTL RENTAL MTl hiTL RF.NTAL CIIARC�PS II QTY 17 QTY AATE � AhTC - 1.846.0 - ' � SUBTOTAL + TAX � SOTAL IprE7H DESCRTPTTON � 1 � 2 { 3 � TTEM � 7 � 2 � 3 �_ SCG C�R 03 - 07-03-Ot.xls D&SCRIPTION - � ' 24,905 7.75 2,318 32,223 ROYAL77PS UNIT Q'1'Y' � 12A7'E � AMT. t 70TAL � � PERhIISS UNFI' I Q7Y I RATE I TOTAL I tati PCO 3 ACD kfA COR 3 eErexxns �� � BENEPfIB � RA11 � 1�hS4 � _ � 1 -� 21fA7'ERTdT.0 RA1'E AM7' 18.20 29.965 A1MC 3!2(2007 rar "' x.,-,=K,:. � x }n � 0 GENERAtFN61NCtRlN6CONTFACTOA February 16, 2Q07 Mr. Justin Kazak SGeton Construction Group 145 S. Sta�e Cotfege Btvd. Su'� 450 Brea, CA 92821 Subject Hende�son Community Bui6ding AddiUonal Impat Due DifFering Site Conditlons DearJustin, McKenna Genera! EnginaerfncJ �sp�u1N reQuests that a Change Order be issueci for ihe Henderson Commun'ity Buikling projed in Paim Desert, CA foradditiona{ import The total value of ttiis Changer Order Request is 537,098.28 as shown belw✓, Please Issue a GoMrect Change Order in this amount so that vre may biil for the addibonal woric. Import Ta1c �Co�ractor Mark Up 1 7. Subtotai Tota( If you have any questions please csq me at (351} 258-7575. sincerery, ���,,���'qy� nacKenrra Ga,erai Ergir,eer;rg, �n�. �$ �$ �$ 29,905.20 2,317.65 32,222.85 4,833.43 37,056.25 � 1335 Corona Poinle Court, Corona CA 92879 Phone: 95�-736-7707 • Fau 951 736-7706 • kepps(dlmdcennagc.tbrp � � .. . - ._ March 2, 2007 Me]issa Wightman Project Coordinator City of Palm Desert, Redevelopment Agency 73-510 Fred Waring Drive Palm Desert, CA 92260-2578 Subject: deb Project #6016 Henderson Community Building Entrada del Paseo 72-559 Highway 11 I, Palm Desert Re: Recommendation for awards of Change Order — Steton Constniction Group — COR #4 Ms. Wightman, We have reviewed the attached documentation received for Change Order Request #4 from Steton Cons[ruction Group for the above named project. Based on our review, we recommend award as follows: ��=1-N-� Change Order #4 — ACD #0�2�Revised Southern (SCE) Utility Plan i�� 8°%' �2''p� Recommended amount of Change Order: Sincerel��, $531.00 � Mark Chappell, Senior Project Manager douglas e barnhart, inc. M��n o l, zoa� Mr. Mazk Chappell Construction Manager douglas e. barnhart, inc. 41-495 Boardwalk Suite D Palm Desert, CA 92211 Subject: Palm Desert Redevelopment Agency Henderson Community Building Change Order Request 04 — PCO #04 Dear Mark, Steton Construction Group respectfully submits our Change Order Request 04 reflecting changes to the Henderson Community Building Project in the amount of $531. This change STETON order is for the fotlowing scope of work: ca�rsTRucrioH , �ti?.i - ��f.� �����f ��:,�,`�' �„`sn. GROUP ACD #�02 — Revised Southern Califomia Edison (SCE) Utility Plan. � f-�✓�'� ��•�2�'j ias s. sta�e coueqe eioa. We are requesting a 0(zero) calendar day extension of the contract time duration as a result suite a5o of the above changes. Brea, CA 92821 (714) 255-7080 If you have any questions regarding the above, please contact me at your earliest Fax (714) 255-7086 convenience. If not and if the above meets with our a roval, lease si below as oar Lic. No. 64'1454 > y pp p gn y authorization to proceed. Please note that Steton reserves the right to recover any additional inro@sietoncy.com costs resultin from the above listed Owner re uested chan e vrxwstetoncg.00m g q $ • Sincerely, ST�TON CON5TRUCTION GROUP �k\,� � ^�� Justin Kazak Project Manager Cc: Phyllis St George 1 Ruth Fernandez! File Mark Chappell Construction Manager Date Accepted S:UobsVienderson Community Building\Change Ordet Reques�s Henderson\COR 04VSCG COR 04 -07-03-Ol,doc HENDERSON COMMUNI7Y BUILD�NG PALM DESER7,CA 2006�305 Ravised Southem Calltomia Edlson {SCE) Utility Plan Steton Constructlan Group SCG RECAP PCO 4 ACD 2 COR 4 --- --- --- ---- - - -- �" _ `Z) _—_ (3) 2nd & Lower GC 1st Tler Subs Tier Subs � 1. Straiqht Time Waqes/Salaries- Labor � 0 � 0 � 0 � 2. Frinpe Benefits and PaYroll Taxes - Labor � 0 � 0 � 0 � I i 3. Overtime Waqes/Salaries � 0 � 0 � 0 �_ i � 4. Frinqe Benefits and Pavroll Taxes - Overtime � 0 � 0 � 0 (DIRECT � 5. Materials and Consumables Items � 0 � 0 � 0 coSTs � 6. Sales Taxes (On line 5) ( 0 � 0 � Q � � 7. Rantal Charqes 0 � 0( 0 i � 6. Rovalties � 0 � 0 � D � 9. Permits � 0 � 0 � 0 � � 10. Actual Costs fSum of lines 1-9) � 0 � 496 � 0 � � � 11. Sub-Sub (15%of Llne 10; Co13) �!��f����ee'�,�aii�r'i��S'�'�I�,'�'F��%l�fii�ii:':ii�tia'it� 0 � I �'12.Subcontractorf5%oflinel0:col.3) I;jln;�'+��Ir,r�ji�" �i+�r,?;r.j<;;�If�h;�L�;ia�M�i�i�i!�i;'�l:'�"�����i��5�`;;��'�I� I o �I � i e �� r 1 �r r�4ryJ�: pan.i+��,I,�7.yyl:idM1thAi?i I PEE �13.Subcontractors(15/oofline10) �;r,iei:u�rl!M::�,. ��I,y,,ir��;��:���?�it�!•r;,f�;,:>iet`;t,:;,. ;;::� :��ux:, �, r. o ��N'�u�i'i'�P"L;';';k:��:.i;r. (,�' �fi''�C`�'�(�f�'!c" l� I, I 14. Contractor (5 /o of line 10; col. 2& 3) � 25 �4� G, �.�,I,� L.�s,,,4,��Via,���:..•:iGil<,�I�Irf.4�Rl�iii.� ytlt:i°lel';.4 fv b�l: �II ' r.���l ViA � - - i I15.Contractor(15%ofline70;w1.1) � O�.�Y„���<<r,;;;P(I?iiti�il7�ii!1�i�6:'I•:';'<ilir:��i,:d����iI�I;�i�� i � 16.Contractors Fee (sum of lines 12-16) � 25 �itu'ii��4ti:�cM!uu�ti�`f��4�1 0 � SUBTOTAL I 1�, ADDITIONAL COST (Sum of lines 10 & 17) I 25 I 496 I 0 I � n��OwqNCe ( 18. Insurance & bonds (2.0°/a of line 17) 0 � 10 � 0 � 19.TOTALCOST �';,i:i i�;y!i'''i9i;"'�'!•'�p�j'r':'If����,,,�,�;?��;��r�,��:.,i,::,;,.�.::- r� I TOTAL I ..;,,i,p�i:yN;j,,4fii.i�i��J�:al::...�*� , .,.�..���;r; _ (SUm Of IineS 17 & 18: COI 4) __ _ _ _. _ _ fT;b;tl�i�:Pf,,�t� ;./.i :;,t�G,? 5�r:f �s�.:,d:i �:''_ "� .l;i;''�:) An additional 0 working days (0 calendar days) are requested to be added for schedule delay purposes. Steton reserves the right to recover any additional costs resulting from the above listed Owner requested change. (4) TOTAL 0 OI QI 01 0 0' 0' 0 0� 0� �, � 0 25 0� 25 ' 520 10 531 �I1/200]8:09AM S:Vob3WentlorsonCOmmvrctyBWiCInB�Cho�peONerqequeelsHandanonlCORO<1SCGCORO�-0]-0�-01.zbRaup 0. U W Q: m � N � Z Q � m} F Z _ � � U 2 W W 0 Z w S W O O O I� i� O O O�-�- O O O N O O O (O � � � N V' � V�' Q F- � '"' O O O O O O O O O O O°•.r.: uR{��. 0' 1!:i'��.y �Y�'°i� i�iii'!�;n: :Li��:,,i., . o � � � v M •7 N V c� m 0 0 0 0 0 0 0 0 0 o a;Fs':: ii9:b o t�i�!i 1;1q91'�.!J;iC o 0 0 0 0 0 0 0 0 0 0 0 0 o O O O O O O O O O O O O O O O O O O O O — o j i�l I�}d; ;: I'y�i' ' �ii b�{I :�;�f! 1 �lr:a — �: p q,. � 0 �7.� �n"Ji . �:.: q II 0.VV e A a �+' � W U N. C O N W .9 0 .� V E d y 0 0 � o � e '> d NK a p7 G � G '.�a U � c V O N c0 O O O 1� !� O O O o�F.'f 'i*: �[J t+:i';.lil �tl.j�l cO' E a � M N M jn4���;)ci;; (O �.v�! k,�i;i r{�<< m' > � � ; � , ,�;I�i d�iK�' i;'i �i '�I, � '' .;o! ��.+ i�(.�nJ� � r� i,.: :I , d �I ' �'1<'lt irl:l��;t i �. a � � kl�i: �'R ����. �t��E'�r,�'�, j' r ��k� u,a� u�ir ,.r;�� � E Y 0 d > o J O '�° a"i a� E � � tn � p^� o - N � O y O � � C t� a m a E �n � o V � V W C � o F`- � m uZ m o C v � N '� m Q w U p� v'� p � �� Ew �a w v o: a o � � c�i c`m a�'i `m y ori Ti ¢ o � m m m w� V y o� a ay`� v �py '� O w t N E UI 'C ~ �p U � N N Cp N N N � t0 C N C'^�' d C T C � j 7= U= 7= O �- N ll O IL �(n R' p.' p�, �_ O O � O O O � O 4 z z tq z z z¢ E .- N M'Q ��D f� oJ Oi O � � e�- .p- .�-� �.r- � fn ___,_ , U W y Q J � 3 w t¢- O p LL O � U � � . ' a _ 6 � K a � N � O Nl O r � m 0 � � Stetan ComtrucNon Group -Brea, Califomu TTEM 1 2 3 4 5 6 � 7 � 8 I9 i + o I �� it � � �2 � � 73 � � � 1TEM 1 � 3 � � ITEM � � � Z � 3 � 4 � 5 � 6 � 7 I s � 9 � �o I I » ! � � � � � � � 71'EM � � � 2 � 3 � I 11'EM � � 2 � 3 � DESCAIPY'10N DESCItIP710N SCG COR 04 - 07-0&Ot.xis i oT i Project Name: Tltle Of Change: Subcontractor Name: SUB DETATi. COST PROPOSAL BREAKDOWN Henderson Community Building Revised Southem Califomia Edison (SCE) Utility Plan Circle City Electric, Inc. � � SVAGE (et) DESCRIl'CION CL4 SUBT(YI'AL U QTY RATE '', AMT Install4"PVCConduit JM (519) HR (8.93) 58.17 (31g) Inslall4"PVCPiug JM (93) HR (1.60) 58.17 (93) Inslall4" PVC Coupling JM (26) HR (0.44J 58.17 (26) Install 4" PVC Elbow (48" RadNs) JM (175) HR {3,00) 58.77 (1751 Install 5" PVC Conduit JM 569 HR 978 58.17 569 Install 5" PVC Plug � JM 41 HR 070 58.77 � 41 Install 5" PVC Coupiing � JM 28 HR 0.48 58.17 I 28 Install 5° PVC EI6ow (48" Radius) � JM 233 HR 4.00 58.17 � 233 I - HR - - I - ( �+ - HR ' I • I ' I 1 - HR ' I ' I - �, I - HR - - I - � � I, - HR - • I, - I TOTAL 3T LABOR / Q'1Y� 58 0.99 68 QTY WAGE (ot) DF.SCRIPIYON CLS SU'BTOTAL U HR RATS � AM'I' - HR - - - - HR - - - - HR - - - TOTAL OTLABOR/QTY - � . R�n. nErrrni, nrrr arrt. I aErrra,, cannGrs DESCRIPYTON U QTY U Q1'Y RATS � AhTf 4" PVC Condult - ry70.o) - 4" PVC PIuB ' (Z.0) - I - 4" PVC Coupling _ (y.p� _ � _ 4" PVC Elbow (48" Radius) - (2.0) - � - 5" PVC Conduit - �7p,p _ � _ 5" PVC PIuP - 2.0 I - I - 5" PVC Coupl(ng - 2,0 ( - ( - 5" PVC Elbow (48" Redlus) - � p,p � _ � . -- i • t I - � - I - � - I I - I - I - SUBTOTAL � � � � � _� TAX � � �+ � � + TOTAL � ' ( 1 I I • 1 PCO 4 ACD 2 COR 4 BBNEF31'S RA1'E I Arff - � - - I - - � - - � - - � ' - I - � - BENEF1'IS HA7'E AM'C_ ��x�nx v RA7B All1T 1.89 (327 3.85 (8 225 � (5 32.00 � (84 3.75 � 838 3.30 � 7 A.98 � 10 45.01 � 90 ' � ' _ t _ � 347 7.75 � 27 � 37� RDYALTIES i1PIlT � QTY � RA1'E � A11iT � - � - � TOTAL � + . � PERMI7S U1VIT' � QTY' � RA.TE ( AMT - � - � ' � • � _ � TOTAL I I i - � 3I2I2007 K�tD£R�o� � Gcit-- d� +�{ PROPOSAL CIRCLE CITY ELECTRIC.►Nc 18726 Van Buren Blvd, Riverside, CA 92508 951-789-6872 Ext: l I 1(phone} 95 I-789-OS 85 (fax) Lic No. CIO-S82166 Change Order I�io. C1-886 (Price Onty) .Iob Name: Henderson Community Center Attn: Steton Construction Date: October 3I, 2006 ELECTRICAL WORK r•:++rtr»rrwrr���rrsrterrirrr�t+t+�t+�+�ar+rtrw���riiistti�rrtai�rr�rartrr�ot»vy+r�+ri• Description: Insta115" PVC conduit in-lieu of 4^ PVC conduit from the metering equipment to a tocation short of the future transformer pad by others, per Proposal No. Rk'P-003. Add: �1,933.00 Credit: $ 1,433.00 $ 500.00 NOTES: I. NORMAL WOHKWG HOURS (UAY SfIIFT). NO ACCELIiRATION COS'I'$ ARF. INCLUDF:U IN'ItUS PItOPO.SAI,. 2. HY SIGNWG'fF11S bOCUM�N'I' YOtf �GRF.F. VOU AKE AUTHURI'LtU TU DO SOAND UNUERSTANI) YOUR CpMI'ANY IS PINACIAI.LY RGSPONSII31.li FOR 1'l1E ADOVC: WRIT'1'EN PRICE. TIiF:RH ARF NO EXCEPTIONS� 3. 'I'Hiti PKUPOSALCQN'I'AINS PRbPRIFI'ORY INFURMATION AND 13 CbNSI�EREU CONFIUrN'I'IAL'fb'I'I Ili Rii('I?f'IGMI', Il' IS tiURMITTHU UPUN THF ERPRESS CONDITIUN THAI"1'HG INFORMA'PION CON'I'AM[D HE:RL'IN WII.1. NUf Hi: KIiLIiASIdI) TO COMPICI'I'POR$ OR OTHER W I5E �E UStU DI RF.CTI.Y, OR INUfRBCI'LY. I N A WAY Dli I'HIMI iN'I'AI. TO I'I IIi INTGRGS'f OI° CIRCLG CITY GLf.CTRIC, �NC. 4. VANDAI.ISM,71tL1"PANDDAMAGE'fOMATERIALOR/ANUEQUIPMF.N'I'INS'fAI.I.F:UOR/qNUS'fOR1iUON81'i1�1.S RIiSM)N.S'1131I.1'1'Y UF(iENF:R/U.CONTRACTOR OH /ANU UWNLN. S. 'I'l il5 PRICf: IS (i00D POR 30 DAYS ONI.Y G. WORKWII.LCOMMGNCCONLYAFiERRECIGPTOF7'HI,S51(iNHUD(X:UMIiNf C.C.E. AUTHORIG�U SIGNATURE: DATE: PRINT NAME: NO"fF.: 7't11S PRUNOSAI. W I I.I. ACTI' AS A PURCHASE ONUA:R TO COMPLP:TE THE W ORK A60V F; �4Ht:N SIC.NFn 61' ISO'i'H 1'AR79Eti - — - Acceptance of proposal: the above prices, specifications and conditions are satisfactory and are hereby accepted. Circle City Electric Inc is authorized to perform the work as specified. SIGNATURE: DATE: I'RINT NAME: COMPANY NAME: 10I31/2006 8:07:22 AM Page 1 Henderson Communiry Center Ci-806 Adtl Sotals (Summary) - Bid Summary: Default Material Non-Duoled Quoies Sales Tax (7.75%) Total Material labor Dlrect (14.96 hoUrs @ S58.17) Total labor Job Subtotal (Prime Cost) Overhead (70.00°/ ) Profil (5.00%) .loh Total Actual8id Price Material to Oirecl Labor ratio: 0.48 Prime Cost per squa�e foot Jo6 Tatal per sqvare fool Actual Bid Price per square fool Labor wst per square foot $745.60 o.00 57.78 5803.38 $870.22 0.00 $870.22 50.00 0.00 D.00 $7,673.60 167.36 92.05 $7,933.01 $7,933.07 SQ.00 50.00 50.00 $O.OD 10131/2006 8:00:39 AM Item # 1197 2105 2124 2753 Description 5" PVC Contluit 5" PVC Plug 5" PVC Coupling 5" PVC EIDow (48" Radius) -- 06 Underground/Sife Total --- Job Tolal Henderson Communiry Center Ct-BBB Adtl Extansion By Phase quantlty Prlce V . _.__.. .__...._. .._... --• O6 UndergroundlSile — 17U 375.04 C 2 330.18 C 2 488.02 C 2 45.01 E ExtPdce LaborHr U Page i Ext Lab Hr 637.57 5.75 C 9J8 6.60 D.35 E 0.7D 9.96 0.24 E 0.48 90.02 2.00 E 4.00 7AA.'15 14.96 744.15 14.96 t013112006 7:27:t2 AM Page 1 Henderson Community Center C7-686 Credit Totals (Summary) - Bltl Summary: Default Material Mon-�uoted Quotes Sates Tax (7.75°/ J Total Material Labor Direct (73.97 hours � ESB.771 7ota1 �abor Job Su6total (Prime Cosq Overhead (10.00%j ProFit (5.00°h) Job Total Actual Bid Price Materiai to Direct labor ratlo: 0,35 Prime Cost per square Foot Job 7olal per square foot Actual Bid Price per square foot Labor cost per square foot 5397.56 0.00 30.85 $428.57 �812.63 o.00 $872.63 sa.ao o.00 o.00 $1.241.00 124.10 68.26 S7,433.36 $7,433.36 50.00 $0.00 $0.00 $0.00 �0131I2006 7:OB:D2 AM Item # Descdpdon 1796 2069 2123 2152 4" PVC Condwt 4" PVC pWgs 4' PVC Coupling 4" PVC Elbow (48" Redius) ••• O6 Underground/Site Total --- Job Total Hendenon Community Center Ct•886 Credit Extension 9y Phase QuanNty Price tl ..._.. . .... _.. ___ _. . �._... ._... ••- O6 UndergroundfSite --- 170 189.03 C 2 385.47 C 2 2.25 E 2 32.00 E ExtPrice LaborHr U 321.35 525 C 7.71 0.80 E 4.50 0.22 E 6A.00 1.50 E 397.56 397.56 Page t Ext Lab Hr 8.93 1.60 0.44 3.�0 13.97 13.97 �{ : � � ��.a�.;:=5.#"h- • •� � : :�. .� .�. ,f March 2, 2007 Melissa Wightman Project Coordinator City of Palm Desert, Redevelopment Agency 73-510 Fred Waring Drive Palm Desert, CA 92260-2578 Subject: deb Project #6016 Henderson Community Building Entrada del Paseo 72-559 Highway 111, Palm Desert Re: Recommendation for awards of Change Order — Steton Construction Group — COR #6 Ms. Wightman, We have reviewed the attached documentation received for Change Order Request #6 from Steton Construction Group for the above named project. Based on our review, we recommend award as follows: Change Order #6 — Implement SWPP plan modiFications per Owner direction. y-t-,:.,� � z,3. ��y . p7 Recommended amount of Change Order: $12,526.00 Sincerely, Mark Ch ppell, Senior Project Manager douglas e barnhart, inc. Much O1, 2007 Mr. Mazk Chappell Constnaction Manager douglas e. barnhart, inc. 41-495 Boardwalk Suite D Palm Desert, CA 92211 Subject: Palm Aesert Redevelopment Agency Henderson Community Building Change Order Request 06 — PCO #OS Deu Mark, Steton Construction Group respectfu(ly submits our Change Order Request 06 reflecting changes to the Henderson CommuniTy Building Project in the amount of $12,526. This STETON cfiange order is for the following scope of work: CONSTRUCTION �,�.� �.. a-� GROUP Impiement SWPP Plan modifications per Owner direction. `1�' 145 S. State College Blvd. Sufte 450 Brea, CA 92821 (774) 255-7080 Fax (714) 255-7086 Lic. No. 64'1454 info@stetoncg.com vrvva.sfefoncg.com W e are requesting a 0(zero) caVendar day extension of the contract time duration as a result of the above changes. If you have any questions regarding the above, please contact me at your eartiest convenience. If not, and ifthe above meets with your approval, please sign below as your authorization to proceed. Please note that Steton reserves the right to recover any additional costs resulting from the above listed Owner requested change. Sincerely, ST�TON CONSTRUC'i'ION GROUP �,r�� ��' � Justin Kazak Project Manager Cc: Phyllis St George / Ruth Fernandez / File Mark Chappell Construction Manager Date Accepted S.Vobs\Hcnderson Communiry Building\Chnnge Order Requests Henderson\COR O6\SCC COR O6 - 07-03�Ol.doc HENDERSON COMMUNITY BUILDING PALM DESERT, CA 2006-305 Implement SWPPP Requlrements Per Owner Steton Constructlon Group h-__-.. __ SCG RECAP PCO 5 ACD N/A COR 6 _ . - - � ---- -------�- —� -- (1) (2) (3) (41 ' I 2nd & Lower L GC ts[TierSubs 7ier5ubs I � 1. Straiqht Time Wa9es/Salaries- Labor 0 0 0 � 2. FrinGe Benefits and PaYroll Taxes - Labor 0 0 0 { 3. Overtime WaqeslSalaries 0 0} 0 I �I� 4. Frinpe Benefits and Payroll Taxes - Overtime ( 0 0 � 0 DIREC7 � 5. Materials and Consumables Items � 0 0I 0 � COSTs � 6. Sa{es T�es (On line 5) � 0 0 f 0 . � 7. Rental Charqes 0 Q I o i � 8. Royalties 0 0 � 0 � � 9. Permits 0 a � � � 10. Actual Costs (Sum of Iines 1-91 0 I 11,696 I 0 i� �., �41 i�'�� � ' i� tE'r'�kt�w4�!':d��, �, � 11. Sub-Sub (15% of Llne 9D; coi 3) �!'�r„li�!�i:'r.�El3�'.E���jill't,N�i��iil5i:sd�i6�d14�'kb,i;9p;r 0 I�:�pii +ii� F�� �1:L�� i�IM�Pli1���ijy�o i..��.� I'f�MP' 12. Subcontractor (5% of �ine 10; col.3) �°:IkinCliE�CII�,�;'V�ur�R�I�;t,ii(;:�,".t,!f��:bt�;�pir??il�,�li7;l��81i`mr�;OC�l��ki��! .dj{1)np'�iU',I;:M1L�lifi °�!.�ii;::l �;aiCv/.qi�^'i_tli i'I' �1iPtiil4::m?�i�;{r�!' '� .tp•P ..�.;t i�, i' : �, FEE I13.Subcontractors(15%oflinel0) ...._.:�'��✓;.,,.r'.,Ii;,:;.i.":'.;;�.•.+�.I��:�.c..;';e,'.i::��i:i�. . 'I1: .. ;n, ,.j� i. � i�i:. "(1:. �tJ.; �,• t�l � 1A. Contractor (5%of line 10: col 2& 3) � 585 ?i �i�'t`t1,;,;�ti,;„;?l�'e.;�.;i:;ij�,,;J: r;; ,, ' �15.Contractor(15%ofline10;co1.1) � 0 �;��;�i;�f•7t?jilS;�ij�,y�,�ji�'�t�;i:li�i�ai�i�'�if���alil�'��!; I 16.Contractors Fee sum of lines 12-16) 585 i!+�.�i1tii!;���!�r�;"r�}�ii��s�4!� 0 SUBTOTAL 17. AQDITIONAL COST (Sum of lines 10 & 17) I 585 I 11,696 0 ALIOWANCE 18. Insurance & bonds (2.0% of {ina 171 � 12 + 234 � 0 . ---- 19.TOTALCOST--------� ------�— ,�p�i,tllii��i�ilir7t�i�ii;' �"�;It°H�i�:"!i;fnP4"i�i'itii+�:n�f,'!u TOTAL - - - — (SUm of lines 17 & 18: Col 4) '; �`', }°w e` `•e'i� �#i �t ";` � �C.','i"��4��t�"'idhY':�i %`.�I'�'s;:�. itJ� ii1�IP�LU�{illiil' ----- -- �iq°�1,,:? i � i ta ,i ^ a.^l� I�' i � An additional 0 working days L calendar days) are requested to be added for schedule delay purposes. Steton reserves the right to recover any additional costs resulting from the above listed Owner requested change. TOTA 0� 0, 0I 0; Oi ol D�, p' 0 OII 0 I Q I 585 I 0' 585 � 12,281 I __246 � _ 12,526 JIZI200>B:�1AM S:VOEaWonO¢nonCommunilyDulltlNp�CM1on9oONorRaqmslaHentlenanlCOROBISCGCOR06�0]-03-0t�IZRacup Q r 0 r- a U w � m � � O O O O��� o o O O O O N O O O � 07 � N � t(1 (O I� N O �' �' �- T- IO O O O O O O O O O O;;,;' .�iL' � s;,�;, ,��u �-�� !�, � o 0 0 0 0 0 0 0 0 0 0�' �'�� ���' ?Aut� — — —•I�� 00000000000,,,,•ai ,;i;c �,u,a � ::;,;; , i�'��{I: 0 0 0 0 0 0 0 0 0 0 0 � Iq } Ip N L a¢t�i 0 0 0 0 0 0 0 0 0 0 0 O O O O O O O O O O O � rn M � N � (J � r h- [V O O U% W � 0 ".' 4•:1''i =i:: i ' i'j� .lti��:is'�J ii i' ;� � �� r�� i���i� �a�61r'�� ,,. o,��� ��; o t!� i�� �"�ry;° �+ (� '��i`; `- � �;;11�i � �p II� ��' �t;1sl Jii � $i'F! h'�d, � �j1, o Li�;ri'�����"".r�, o o j�r �ij�,��:;� I � i1 c II� ;�F I � N ��il�p i Slt ��i � �t'y7 ��k!i f � ��41i�!`�` �r���� �Ilrt��i��IGlI O IKIII.H �a���������ti!' C � �I+��•inNv:i�����' � � 1 ��� Iii ''� 1� ���7 � �;: � � i- ' i�`. � :'��i4r �'i�+� iJl ;.:ae �i��. • i d � c� � z a 0. }m � F- � a i 3 j � g I, � � C : � a' u � � Z O � m I y � Q i w o °' V � z� m .�°- '� W o a 2 N £ u/ I � I O � A j o J O .� a� `� E a? o C F' ~ N � � i @Q�e�^ � = i m- m � '@ m E �n � o aNi ,o ro o u�i c `o o F- �� �. c N c c= � p r � d3 � ` lQ N (O O C J C .� O. S � o, N U p v �p p �+ U T_ � c � c m N m � ot3 Y�j �•- 3 J( y pz�� i_ N N Q1 N ry'C N O �'O 'O � b 9 �N � I L� E � C� U =� � U G N N C N N ✓1 j- � o' o: �C ¢ °? v c i. € � � � 7 � > > > p r. ,� m c> c �6 � d o a¢_ Z 2 iA 2 Z Z Q � I in � O LL� rn �� a � r(V M V tn �O I� tU O> O� N.r�- � N�O .I�-, N N U � � _ vI U � Q W Q �I � p � tWi O i� p U � ---- --_ -- 4— — n � � � h x q � 0 � 0 � � 0 a n Steton Cowtruction Gronp - IIren, Ca3ifornta DETAII. COST PROPOSAL BREAKDOWN Projact Pdame: Henderson Community Building PCO 5 Tltle Ot Change: Implement SWPPP Requirements Per Owner ACD N!A Subcontractor Name; So Cal Sand6ags COR 6 � WAGE (at) BENEFI'l5 TTEM DESCIiIPT10N CIS SUBTOTAL U� qTY R17'E � NNT 1tATE AMT t ' HR ' ' ' ' Z - H� - - ' ' ' 3 - HR - ' ' - ' I 4 ' Hft ' - ' - ' I 5 ' H{2 ' ' ' ' ' I 6 - HR - _ I ' - ' I � - HR - • - - • 8 — -- - _ H� _ - ' ' B - HR - ' ' ' ' 70 - HR - - I - - ' 11 1 - HR ' - � - ' - 12 � • FIf2 - • ' ' ' I 13 - HR - - I ' - - TOFAL ST tABOR /4TY - - • - � Q7'Y WAGE(ot) BENEF71'S � i IT�M DESCRIP'CION CL5 SUBTOTAL U HR RATE I AM'1' 1iATE AM!' � Ei 1 ' HR - � ' ' ' � 2 . ' HR - ' { ' ' - I 3 - HR - - � • _ ' � 70TA� O7 LAHPR f OTY - I ' ' TtTL RENTAL MTL ll77'f. RENTAL CHARGES MATBRiALS I� DESCRIPTTON IT� QTY U QY'Y RATE � AM1' RATE AMT ' 1 2" Ag8re9ate Base - l0 2.Q - 8�0.�0 t,fiUO � � 2 3 ShaRer Plates (12 Month Rsntel) - EA 36.0 - 160.00 5,760 � 3 ' ' ' ' ' ' � � 4 Skiploader HR 8.0 - 80.00 640 - - � � 5 OMoad / Removaf OF Skiploader EA 1.0 - AD0.00 ADO - - � 6 Fuel / Delivery Surcharge EA 2.0 - 300.00 600 f - - �� 7 Offload / Removal Of Shaker Plates EA 2.0 • 300.00 600 � • - I 8 ' ' ' ' � ' _ � SU9TOTAL 2,240 7,360 ( TpX . 7.75 67U � TOTAL � _ 2,240 _ _ 7,830 � RDYALTiES f TI'EM DESCRIP'LTON QNPf QTY � RATE AMT ' � � ' ' ' f z - � - - � 3 - � - - � TQTAL�" _ __ �' PERMI'IS ,7�M DESCA7Yf'ION � UNi7' QTY AATE I �Nrr � � ' I i z � ' _ I 3 TOTAL� I • � � SCG COR O6 - 07-03-Ot.xls 7 of 1 3/2/20D7 Dct 20 2068 8:44RM SO CpL SRNDBRGS 95127723q3 � p.l ��,.�,v �:x,,,r , �- x � ,�� `,r �� .��r.w*%" >.. '� ts.� : s€` e5 ^ / s i / e . i :. . � K�l`1 pk/Zg D /� c� � �#- G � ". .f ` � �/ , h!, { "' ,• : _` �t.�- f'= _ ,�` t800) B34-868Z � (9SI) 277-3404 • Fax (981) 277-23Q3 �` � y � '�` r� P�` � M't''*+; � G i�' '4x�.5 �. � *� 1 ? �Y� S �a Date: Attn To: From: Project 10/20/2006 JU3TN STETON CONSTRUC'CtOFI GR�UP STEVE VILLA Pl1LM QE8ERT Fax# 714 265-7088 Tel# 714-255-7084 Cett# 714383-1732 So. Caf, Sandbags, 1nc. propoaes to provfde afl4abor, matarfa{s, hools and equiprnent necessary to perform the work descrihed below; I Description UnR oi ` Quantlty Unit 5ubtotal Salas Sales Tax Measure � Prica Tax °h Amt. �+2" ROGK IOAD I 2 BO6.00 1800.QD 7.75°/a 124,�0 1i3KtPLOADER HR � B 80.DD 640.Q0 0.00% O.�D IIN/ OUT EA l 400.00 400,OQ 0.00°/n 0.00 Total ltem �,72a.00 640.00 400.00 �FUEL) DEL.IVERY 8URCHARGE EA 2 300.OD 600.OQ 0.00°% 0.00 600.00 3-3HAKER PLA7E3 MONTHLY RENTAL 12-MONTHB EA 3B 160.��� 5760.00 7.7b% 446.A0 6.206•40 �lN / OUT FA 2 30Q,OQ BOO.OQ 0.00°% D,00 600,00 iu.i7v.R� � � � � � I - f 1 � _ � I � 1 l I � I I IESTIMATE VALD FOR 30 DAYS � � � �roTaL I I ( I Priaes subject to chanpe dvIing lndement weathef. LaOolcha,ge torinslaNstfon k Desed on Qood beqk access doAnp norma! working hw�rs. Payment terms are �ret 30, �m reMndon- Wo appreciate h5e oppoRuqky to pr'ov/de en astimat9 on thls pio%ct Pieaae ca!! Hyou hevo eny q�esfions or need furthat rrtfan)ayon. �� � ; . . .: - . _ March 2, 2007 Melissa Wightman Project Coordinator City of Palm Desert, Redevelopment Agency 73-510 Fred Waring Drive Palm Desert, CA 92260-2578 Subject: deb Project #6016 Henderson Community Building Entrada del Paseo 72-559 Highway 111, Palm Desert Re: Recommendation for awards of Change Order — Steton Construction Group — COR #8 Ms. Wightman, We have reviewed the attached documentation received for Change Order Request #8 from Steton Construction Group For the above named project. Based on our review, we recommend award as follows: %?� � aY� . Change Order #8 — ACD � Provide revised pricing to utilize the listed lighting alternatives. Recommended amount of Deductive Change Order. ($1,823.00) Sincerely, ( ( .. Mark happell, Senior Project Manager douglase barnhart,inc. Mazch Ol, 2007 Mr. Mark Chappell Construction Manager douglas e. barnhart, inc. 41-495 Boardwalk Suite D Palm Desert, CA 92211 Subject: Palm Desert Redevelopment Agency Henderson Community Building Change Order Request 08 — PCO #06 Dear Mazk, Steton Construction Group respectfully submits our Change Order Request OS reflecting changes to the Henderson Community Building Project in the amount of ($1,823). This STETON change order is for the following scope of work: CONSTRUCTION GROUP 145 S. State College Blvd. Suite 45D Brea, CA 92821 ACD #3 - Provide revised ricing to utilize the listed fighting fixture alternates. � F"f'd���? t-�j�r'i ��'�w.t �lc�:-,���rn� f� v� T�� S��v, � z�l' . We are requesting a 0(zero) calendar day extension ofthe contract time duration as a result of the above changes. (714) 255-7080 Tf you have any questions regarding the above, please contact me at your earliest Fax (714) 255-7086 convenience. If �ot and if the above meets with our a roval lease si below as our Lic. No. 641454 > Y PP , p � y authorization to proceed. Please note that Steton reserves the right to recover any additional tnto@stetoncs.com costs resultin from the above listed Owner re uested chan e w�wrstetoncg.com B 9 b • Sincerely, ST�TON CONSTRUCTION GROUP Justin azak �r� Project Manager Cc: Phyltis St George ! Ruth Fernandez / File Mark Chappell Construction Manager Date Accepted S:UabsU-Ienderson Community Building\Change Order Rcquests Henderson\COR 08 - APPROV ED\SCG COR OS - 07-03-0 i.doc HENDERSON COMMUNI7Y BUILDING PALM DESERT, CA 2006-30b ACD #3 -Altemata Llghting Package Steton Constructlon Group SCG RECAP PCO 6 ACD 3 COR B "'_ (�) (2) (31 (4) . GC 1stTierSubs ' 1. Straiqht Time WageslSalaries- �abor ( 2. Frinqe Benefits and PaVroll Taxes - Labor � 3. Overtime Wapes/Salaries � 4. Fringe Benefits and Payroll Taxes - Overtime � DIRECT � 5. Materials and Consumab�es Items ( Cos rs � 6. Sales Taxes tOn line 5) i, � 7. Rental Charqes � � 8. ROValtles � � 9. Permits � � 10. Actuai Costs (Sum of lines 7-9) � ; � 11. Sub-Sub (15% of Line 10; col 3) I i��:i;:`';:�: I � 12. Subcontraclor (5%of line 10; col.3) �:�'i-?.'ii , FEE � 13. Subwntractors (15%of line 101 �:�f; �2.'c';_<;: OI0 OI of OI OI OI 0� OI OI 2nd 8 I�ower TOTAL I� Tfer Subs 0� 0, 01 0 OI 0' al o. ol o olI oi 01 0 OI 01 ol ol ol ol OI 0 I14.ConVactor(5%ofline10;Co1.283) ( (85)�1+��;,�7��i;`ii�-::`;*�rcl.�.�.11'��$;a��i��IGi;n�?��`��'."r;'.;:� ;, , �.,,, �15.Contractor(15%oflinel0;col.1) � 0�`i��;ir.;itii„i�"'��'�r':,�;;:.,'.`t`,,,,..,..,'� li�.,,3ii�:.,�! �;c• '` � 76.Contractors Fee (sum of lines 12-i6) � (85)�',�ryi���y��4y:�i�a���iiU��i��lu ��' �0 � SUBTOTAL I 17. ADDITIONAL COST I (Sum of Itnes 10 8 17) (85) I 11,702) I 0 I nLLownNCe I 18. Insurance & bonds (2.0%of line 17) � (21� (34)� 0 � 19. TOTAL COST - � - ;'j ;;i= ���7:',`,N^•Ci ��i �,tl " - i�l: � � p, i � � TOTAL I ��{'I'�l'}�i;�{�i(' �r'''r�yi. ��!::.,.y .�'�;,�tir;.l,:�-...�; :,"�. (Sum of lines 17 & 18: col4) �s��l;•;�ry !�,ir q�H�FiF;iI `,�%�^"}iiF;r.^i�:?j;���I!` ��'' �'j Pi:k�'��'i�:l I�� „i �F, .P�.1. � �. Oiki�vi�cr I..o � uiti;T'.'�aE�i .ai An additlonal 0 working days L calendar days) are requested to be added for schedule delay purposes. Steton reserves the right to recover any additional costs resulting from the above listed Owner requested change. OI OI (85) �I 0 I' (85), (1.787) ' � (1.823)' 12/300]9.03AM S:Vo>.tWeiMenonCommunMBu�ItlinplChmnpoONerRaquoslaHaMenonICOFl08-APPROVEDI6CGCOROB•OT-0}O1.akRecep a Q U W 0.' m _ � � Z � ym F Z � � a� :.% z � � W 6 Z W x t0 M 00 a4U d m � a � C t � J N E a � � � � �? �O N Q � � O t�f � C U c .�. y F O O O O O O O O o O O O O O O O O O O n n � � � � O O 9 O O O O O O O O �.� O O O O O O O O O O O � C O O O O O O O O O O O I �II M � O O O O O O O O O O o i N �� � � � ^�� O O O O O O O N O N O U � ^ �`- d v� � c� _ ` �w U »? a�i i- � _ rn � •C �. � N �- � O N O � ^ � C fn N� N�� � D � N ^ V N C � � � — � y � N � 3��� � o v �, o � ° � E c?i c m ayi m y Ns i�S � O z °rG' � m � � U � U � � v ��p �i uDi �i � y � 6' 'C O' .N y .m. •N � N � � � U � � � ~ C � C N C .�Y C>� 3 J ,p 0 w i4 li O li .G N 2 d' d Q= Z Z(n Z Z Z Q � '- N t+) V � fU Ih N W O r N M 7 H t0 I� N� � � �-�_�-� � � E r n � o J O 9 � � � d v E ---------- W------.-� � U V t�- Q w Q � � 0 O LL � O U � �- a I n � n �'n x 0 m 0 a 6 N O O N � Stetan Coua4ruct�ao Group - Brca, California SUB DETAII, COST PROPOSAL $REAI�OWN PCoJeCt NaRla: He�derson Community Building TIUe Of Change: ACD #3 -Alternate Lighting Package Subcontractor Name: Circle City Electric, inc. T WAGE (d) I77�M DESCRIPT[ON CL4 SUBTOTAL U QTY RATE I� �T � - HR - - - p - HR - - - 3 - HR - . . 4 - HR ' _ . 5 ' HR ' " " 6 ' HR ' ' " 7 - HR - - - g - HR - • • g - HR - - - �p - HR - • - 1 >> HR - � 12 HR • - - � 13 - HR - - � . � TOTALSTLABOR/QTY - - ' Q1T WAGE(ot) (TTEM DESCRiP'1'{ON CL4 SU9T0'S'AL U'. HR RAT£ +�D17 � � - HR - - • } 2 ' HR ' ' ' 4 3 ' HR ' ' TOTALOTLABORIQTY RTL RENl'AL M7Y M'lY. i RENfAT.CHARGES �Ci'EM DESCR3PTION Y1 Q'1'Y II QT1 1UTg 'UTi� �� - - _i - ! 2 - - � . i 3 ' ' ' . ' ( 4 ' ' ' ( . I 5 ' ' _ � ' ( 8 ' ' - � " 1 7 _ " " f 9 ' ' . � 10 ' ' ' ' � 11 ' ' ' � SUBTOTAI � TAX � TO7AL �j�ry7 DESCRIPTiON � i Gredit For Specilled Liphting FlMure Package � 2 Cost For Alternate Ughting FlMure Package � 3 � �7g7y� D&SCRIP770N � 1 � 2 � 3 � SCG COR OB - 07-03-Ot.x4s PCO 6 ACD 3 COR S BENEFTfS RA1'& AR3T SENEPfIS RATE { AM'P 0 i - 1NA'I":HIAIS xnzs n�'- . 7.75 - � ROXALTTES � L11VCf Q1'Y AA7R AM�I� I� LS 1.00 I (108.082) (108,082)I LS 1.00 106,380 iQ6,300 _ 1� 70TAL (1,70Y11 PERMITS 7� � UIYIT Q7'Y � RA17: - AIDTP I _ � _ _ � TOTAL I - �. 1of1 3l2t2007 ',�,��� �- ��SY rA, �n . .9'y .,51 �`¢ ;-. I� s , � � . CIRCLE CITY ELECTRIC, mc 18726 Van Buren Blvd, Riverside, CA 92508 951-T89-6872 Ext:lil(phone)951-789-OS85(fax} I.ic No. CIO-582166 Change �rder No. CZ-886 (Price only) Job Name: 1-lenderson Community Center Attn: Steton Construction Date: danuary 4, 2607 ELECTRICAL WORK •�k�VvtT+rr�trttrMAWtt�tWY�Y�vY+I*t*irMttvMtV�VaTsr���t�wWriylMli�iyt�Yi�tirwtttrY��tt• Dcrcription: ADC #3 Aiternate Lighting Package Refcrence: ACD #3 Credit: specificd lighting package: $108,082.00 Add: Atternate {ighting package: $106380.OD Totai credit: S t,702.00 NOTE5: I. NU1tMA1. WORKIN(i f10URtifDAY tiUIFI). NO ACCIiI.1:RA'170N COS'I� Altli INC'LUUI:1) IN'I'lllti I'Npl'lAtiAl.. 2. IS1'til(;NWU'Pf Ilti I�(XUMIiNf YnU A(II[L'L' YOU ARIi AU'fHURI%F'U'1'O 1� ti0 ANU �INUtiRti'I'ANU YUIIR COMI'ANY Iti FINACIALLY HI :tiP�1NXItSLtC PqR 7'I It� Al1QVF: W RIPf IiN I°RICfe. T! IfiRti ARR NO IiXC1iIr1'IqN V 3. 'I'lll$PRUPf>SALCQNI'AINtiPROPflIfiPOIiYINFORMA'17DNANDISCONSfDF:RtUCONPlDIiN'I'IAI.'f0'1711iItG('lil'IIiN'I'. I'I' IS SUHMI'I'I'lil) UIY)N'I'I Ili IiXPRIiSS C<)NUPPION'1'l IA'I"I'tlli INPORMA'I'ION CUN'I'AINI>i) IllililitN Wtl.l. NO"1' lil i Itlil.liAtilip'1'O f:bMl'li7'I'fOliti OR O'flltiRWISG Of II.tiGD !)IRRC'TLY. OR INDIRECI'I.Y. IN A WAY UlCI'IiIMIfN"PAi.'fU '17l1i INI7iRkS'f !»'CIRCLL CfIY Ii1.liC7'RIC.INC. 4. VANUAI.ItiM.'IYllil�l'ANUDAMAfi6'fOMAT1iR)AI.UR/ANDIiQUII'MIiNYINti1'AI.I.GDOR/ANI)ti'fpRi:UUNtirI'liiti ItliSl'UNXI I31LfIY OF (71(NIiRA I. CtNJ'I'RACf<Ni ON / AND UW NF:R. 5. "1711ti PRICIi IS (i(XID POR JO DAYti ONI,Y 6. WOItY.W11.LCOMMP:NCIiON1.YAF1'IiRltl!CIIiI''I'OF'1711.SSI(iNliDIHX'i1MIiN'I" C.C.G. AU"fHORIZED SIGNATUILE: DATF.: PRTNT NAME: NO,1'Y;: )'1115 PNOIM)SAI. WII.L AC{'Ati A Pl�RC11ASt:ONOF.R"1'OCAMPLti'fE'CNti WORK 1BOVg WpF,N til(:NF:i) 6Y BO'ft( PAN77F:ti . ' Acceptance of proposal: the above prices, specifications and conditions are satisfactory and are hereby accepted. Circle City Electric Inc is authorized to perform the work as specified. S(GNATURE: DATE: PRINT NAME: COMPANY NAME: !; � ..��:�., - ��_ March 2, 2007 Melissa Wightman Project Coordinator City of Palm Desert, Redevelopment Agency 73-5 l0 Fred Waring Drive Palm Desert, CA 92260-2578 Subject: deb Project #6016 Henderson Community Building Entrada del Paseo 72-559 Highway 111, Palm Dese�t Re: Recommendation for awards of Change Order — Steton Construction Group — COR #9 Ms. Wightman, We have reviewed the attached documentation received for Change Order Reques[ #9 from Steton Construction Group for the nbove named project. Based on our review, we recommend award as follows: i-�Y: f� Change Order #9 — ACD #4 Provide credit to delete steel per ACD#4 dated 10/26/06. 0�• � 7�. u1 Recommended amount of Deductive Change Order: ($1,702.00) Sincerely, ��"� - —' Mark �happell, Senior Project Manager douglas e barnhlrt, inc. Mazch O1, 2007 Mr. Mazk Chappell Construction Manager douglas e. harnhart, inc. 41-495 Boazdwaik Suite D Palm Desert, CA 92211 Subject: Palm Desert Redevelopment Agency Henderson Community Building Change Order Request 09 — PCO #07 Dear Mazk, Steton Construction Group respectfutly submits our Change Order Request 09 reflecting changes to the Henderson Community Buitding Project in the amount of ($1,702). This STETON change order is for the following scope of work: CONSTRUCTION ��3 o3•�a•o� GROUP ACD #4 - Provide credit to delete steel per ACD #4 dated 10/26/06. �as s. state Cone9e awd. We are requesting a 0(zero) calendar day extension of the contract time duration as a result sui�e aso of the above changes. Brea, CA 92821 (�ta) z55aoao If you have any questions regarding the above, p(ease contact me at your eartiest Fax (714) 255-7086 convenience. If not and if the above meets with our a roval tease si below as our Llc. No. 641454 + Y PP > p � Y authorization to proceed. Please note that Steton reserves the right to recover any additional info�stetoncg.com costs resultin from the above listed Owner re uested chan e wvnv.sle�oncg.com g 9 6 • Sincerely, ST�TON CONSTRUCTION GROUP �;r�� �� Justin Kazak Project Manager Cc: Phyllis St George / File Mark Chappell Construction Manager Date Accepted S:UobsVienderson Community Building\Change Order Requests Henderson\COR 09 - APPROVED\SCG COR 09 - 07-03-Ol.doc HENDERSQN COMMUNtTY BUILDING PALM DESERT,CA 2D06�305 ACD �t4 - Credlf For peleting Contract Required Steal Steton Constructlon Group SCG RECAP PCO 7 ACD 4 COR 8 ��j --- �- czJ GC istTferSubs LStraiqhtTimeWaqes/Salaries-Labor I 2_Fringe Benefits and Payroll Taxes - Labor � 3. Overtime Wages/Salaries 4. Frinqe Benefits and Payrolf Taxes - Overtime � oiRecT � 5. Materials and Consumables Items COSTs ( 6. Sales Taxes (On line 5 i � 7. Rental Charpes � 6. RoYalties � 9. Permits � 10. Actual Costs (Sum of lines 1-9) � 11. Sub-SUb (15% of Line 10; C013) � 12. SubconVactor (5°/a of Ilne 10; col.3) FEe � 13. Subcontractors (15% of line 10) � 14. Contractor (5% of line 10; col. 2& 3) � 15. Contractor (15% of line 10; col. 1) � 16.Contractors Fee (sum of lines 12-16) SUBTOTAL I 17. ADDITIONAL COS7 (Sum of lines 10 & 17) nuownNCE I 18. Insurance & bonds (2.0% of line 17) � � � TOTAL I19•TOTALCOST � (Sum of lines 17 & 18: col 4) OI OI ol al 01 OI OI OI __ _.(3) (4)-_ _� 2nd & Lower TOTAL � Tier Subs I, OI OI OI OI 0� OI 0 0l OI OI Di Q� ol ol o� o) ol ol I(791I (1,589)I OI I (2 � (32) I 0 � C�}i''�'�Hl���I' � ��1i'ipi'•iif;'ii'`''LL't�'-{�y'�r'�a`Y����4��4pi!�IiF�?i��l, . �:;f��;�;�l��.hi%i�f'i4� .���I.,la�II'�j�:ISiI��Ffi�t+';I��I,L�f.44�4iiFI�IN�1'RIFI�IR� An additional 0 working days (0 calendar days) are requested to 6e added for schedule delay purposes. Steton reserves the right to recover any additional costs resulting from the above listed Owner requestetl change. 0' 0' a' o'' 0 ol, o' ol 0 0 0� OI 01 (79)I 0� (79)� (1,669) 4331 � (1.702�I 3IPI000)B:faAM S.VOESWentlersonCommunlryOUllUinglC�on9eONotRaquaslsHantlorson{COROB-APPROVEDtSCGCOROD-0]-0}Ot.xl�Recop a wN I.f. Hi � y O O O O O O O N O N O O p f� O O O a M � y O ` ` I o 0 0 0 0 0 0 0 0 0 0���I� �� �;i�l�� j�i' ?i I@(, i{il ��;: ik�li,�f;y�f;i`t;; `° �F� 11fi; ; i.,! ,r :' '�,f� ,,:, ��;; . ,'u,_ cq' lu;i' i�c�, `'k .i!!`:' �i � ;rAK,; ;i; i ��s'i �lil�� r:i" rLj..•'r��l' ,iin,:'�: � e.;'e.t -- — � tiT�4 :�e;�, ' nT. T ^' O O C7 O O O O O O O O,;i:i r,o I, p.�, . iil;; '; . 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O o O O O O O O O O p � Z � J 7 m Z � � � V z 0 � W 0 2 W _ n.am Ut�.10 a a c.> � w 'O � Q � � c 0 V C m a tL 9 � V u� � fO D N Q a �p G t9 C O V � G V c 8 N O O O O O O O N O N O M M � o� � a r a � $ `S O � � � � � � � ?: m o C � � N .- W O y O�^ � C % a � a � ,n � `o � w v � m?Ni m o c � v � � a! � v� o, N U p� v� � �n V � � c� c m� m y aY 'FS ¢ o 1= ar v m m� t v� o��op� a�,L° a a v �•- P N E N C y f0 '� � U C Jl N C N N 4�1 f.. � '� c m c °w' � c > � � j > > � > > > —p � (A ti o lL i(n K� a Q_ z z N z z 2 Q o �(V M V t!> f0 t� c0 � O � � � � �� sn- � fn _____�_�___�__��_ W U W N Q w Q � O p tWi O O U J I' = �_.. < m � 0 ei Stcton Conelruction Group - Baa, Californla Project Name: Title Of Change: $u6conVactor Name: (11'EM � 4 � 2 � 3 � 4 5 6 7 8 9 10 17 12 i 13 � ITTEM i � z 3 DESCRIPI'ION DESCRIPCIOI3 1'I'EM 1 2 3 4 � 5 Is I� 18 9 ( 10 � it { � � ,ITEM � � � z { 3 � I7fEM � � � 2 ( 3 � DESCRIPTiON CredR For Oeleted Structural Steel SY7B DETAIL COST PROPOSAL BREAKDOWN F{enderson Community Building ACD #4 - Credit For Deleting Contract Required Steel White's Steel CI3 SUBTOTAI. � - I - U HR HR HR HR HR HR HR NR HR HR HR HR � HRI � QTY WAGE (et) RAT1 I NHT- TOTALSiLA60RlQTY - TOTAL SUBSOTAL TAX TOTAL DESCRIP170N IYFSCRiP'P10N QTr CL4 SUBSOTAL U SR - HR - - HR - - HR - PCO 7 ACD 4 COR 9 sEtvexris I RAT'E A1�fP � ' ' � - � - - - � ' _ � ' B � F17'S RA7'E I AMT- ' I " � _ 1 - � WACE (ot) RATE � AMT- - � - � - RTL R&NfAL MT'1 MTT. RENTAL CHARGE9 MATERLll3 I U Q'CY U QTY RA7'E i AM7' RA1'E AMT � „ - _ ' ' " � - - ' . _ . 1 " ' ' ' ' " I - - - � - - � - - - - - - � - - - - - _�� . - jl - 7.75 - � . - � ROYAL'fQ+S I UNPC QTY RA11: A1NT LS � (100)� 1,38200I (1,382j - � 1 707AL _ _� _ �___ 11,382) __ Y�nn•rs I ""'T , aT" � �n� � �- 1 70TAL � , I � - � SCG COR 09 - 07-03-05.x15 1 of 1 3122007 Sent By: WHITE'S DRAFTING; 0 , 78034286i3� Dec-12•OB 2:51PM� CHA�GE Ct�d�D'lE�"i. WNI'fE'S STEEL � . CA Lic. #47738d . � A5�524%wnestre�t ... . Indlo, Ca. 82201 �760j 3�173407 Fax. (760j 3A2=88�T3 . . Page 1/1 h{F.�Dh+�sa,o l.m�Q—� 0`1 TO �'j"�T6t.t ,�u�s'r. CHAN��'iaRti�k NO. Q I ADDRESS ►'�"�'�_-�S'�• '`�7AYE ret.t�.Gt-BWA d+T�4.SDbATE' ��.? —�.Ca i�'�11. GA.. PNDiIE . I.7 ( 4 i 2.S$' 7q S� � JOB NAMEAND LOCATIUt� f}au�a�K ��6, .. •.JdH NUMBER O(o'. ( � � � _ 7 z— 5S`l N�� �a�,�+f� N(� a��•o� Facrs�rna�aor�r�ar } � '�byr l'�at�2 �4`{'��1 . P� ¢ �M 1'�''�t� �Sr�� r�ca�' At��sa.�. �. � Y-� rut � .� . � .� �3 e NOTE: 7h1s ravtsion bxomas oart aG nnd irt raMortnanoe vrtth.th� vxF�rtlnq co�at '. 3'VE AGREE heroby W make chonaes as epeolfied abovo, atlhia �rtca . DATE �PIi�Y1pUS CONiRACT AMUUNT . ' 'IREV}SEp CbNTRACT70tAL ACCEFTED: Thaabovo prics arx! epeeHlextlon af this ehangs ordrrr�ra,satlefaotnry ai+rinro twnby acaaptad.All woAc to.be perfnrmed under sam� bmv and contlitioru ss apeolfled Ut oHDi�vl unteas Othwwivestipuialqd. PAT�: �ar D�,'ti`�� �� ��'�5�F1 �r • �a l5 . � .� a�+. � � 72� $�?. p"tl` � a• 71 r 26 i: OD S10NA'C'UltE:...... .. • .. . March 20, 2007 Mr, Mazk Chappell Construction Manager dougias e. barnhart, inc. 41-445 Boardwalk Suite D Palm Desert, CA 92211 Subject: Palm Desert Redevelopment Agency Henderson Communify Building Change OrderRequest 12R1 —PCO #IORI Dear Mark, Steton Constcuction Group respectfic]ly submits our Change Order Request 12R1 refIecting changes to the Henderson Community Building Project in the amount of $4,998. This STETON change order is for the following scope of work: CONSTRUCTION O�-�a-'b% GROUP ACD #7R1 - Battery Inverter And Egrass Lighting System. �as s. sta�e conese si�d. We are requesting a 0(zero) calendar day extension of the contract time duration as a result su��e aso of the above changes. Brea. CA 92821 (714) 255•7080 If you have any questions regarding the above, please contact me at your earliest FaX (714) 255-7086 convenience. If not, and if the above meets with our a roval lease si below as our Lic. No. 641454 3' pp � P g" Y authorization to proceed. Please note that Steton reserves the right to recover any additional infoQstetoncg.com eosts resulting from the above (isted Owner requested change. w�w+sletoncg.com Sincerely, ST�TON CONS'1'RUCTION GROUP t\r� �,�/ ��S 3ustin Kazak Project Manager Ce: Phyllis St Geocge 1 Ruth Femandez / File Mark Chappell Construction Manager Date Accepted S:UobslFlende�an Communiry BuildinglChange Order Requests Hendersun�CQR l2 - APPROVEDISCG COR 12-07A3-20.doc HENDERSON COMMUNITY BUIL�ING PALM pESERT,CA 2006-305 ACD #7R1 - Battery Inverter And Egreas Lighting System Steton Constructlan Group SCG RECAP PCO 70R1 ACD 7R7 COR 12R7 �u; GC � (z) (3) � (4) 2nd & Lower TOTAL 'Ist Tier Subs Tier Subs � 1. Straiqht Time WageslSalaries- Labor I 0 � 0 0 � � 2. Frinqe Benefits and Pavroll Taxes - Labor � 0 � 0 0 � �_ 3. Overtime WageslSalaries 0 � 0 � D � � 4. Frinqe Benefits and Payroll Taxes - Overtime 0 � 0 � 0 � DIRECT � 5. Materials and Consumables Items � 0 0 � 0 I cosTs � 6. Sales 7axes (On line 5) � 0 0 � 0 � 7. Rental Charges � 0 � 0�, 0 � 8. Rovalties � 0 � 0 � 0 � � 9. Permits � D � 0 � 0 � � 90. Actual Costs (Sum of lines 1-91 �, 0 � 4,667 � 0 � � 11. Sub-SUb (15% of Line 10: Col 31 ��'�f�'I'��'�I��'�� �r�,:��"����;i}Ij�� � i�i� T c'�{p'I' ��Y.;1 � i�iyi �x��i:"H.i .; �,.�i�.rd�t ��:� 0 ('12.Subconhactor(5%ofline10;co1.3) ;(;���f��;�� 1�If1!';iY' '':t�' ^e�!j}I�;.;���,};;;: �?:II.,�1-�' '� .��il� � e},,,,; ��:"; i,��,:h�,,h:l�,.i'r�:'rl;��ir d:� �• FEE �13.SubcontractorsH5%ofline10) �'`.';ii��ii��'�;�!:;i;��.;:;�.;'���•��� `i;l�;'�ii�ii(;��'+Ij°���i'"�e'd^'��a��.�� � 14. Co�tractor(5%of line 10: col. 2& 3) �1Y 233 (:?I`.�' •�'�:;,�;" '�i1;;l�r�'�' ��"� „Y;i ,`� � 15. Contractor (15% of line 10; col. 1) � 0 `��;'•I �"i,�, .'}� �'"° � ;�,.. . . ;;.,:. � . ��;�., ..:. i, �„�, : i.� . . . ,�:1� �� �16.ContractorsFee(sumoflinesl2-16) � 233��;I�ii�i'�!:��r�:�+,,,��„-.�,� 0� SUBTOTAL � 17. ADDITIONAL COST I 233 I 4,667 ( 0� ALLOWANCE I 58. Insurance & bonds (2.0% of line 17) 5 I 93 ( 0 I TOTAL �9.TOTAICOST . _.` -- ,.�i;�Gii:,iiip1i�;J:i�l'—"i�.i'i�4�� ;�t ,��i.it;��'��.,i Sum of Iines 17 & 8� ` ,�° � �' ;l '� � '; � '''! ' ��Ijrh��'�I��'� � � . COI�{ ��•�' � .ei��n�if�l SiII �1;;;I�I'�i ;��I�i i:j.. ':I..�, F:?.r� � __ __ _ '""""_—___ � _ _ ___�q:j�.�.,:lcdl�i���dili"!ihll:�':14i�; :1i:ll�� .6..iSi+ICi'I An additional 0 working days L calendar days) are requested to be added for schedule delay purposes. Steton reserves the right to rewver any additional costs resWting from the a6ove listed Owner requested change. 0) OI OI 0� 0� Or 0�1 OI OI 0� 0 0 0 233 0 233 4,900 ! 98 I 4,998 I OIZof100�f:58PM 6:VatsWentlenonCommuniyBudElnptChanpeONe�RaquaslaHenOersen\COR12-APPpOVEO1SCGCORI2-OZOy20.xInR¢wp a W � m � � � � � m � � � � V fl a W G 2 T Q 0 � ��� � � �� � � � O 0 Q � 1� N O fD f� � J F¢- Q z� u� O O O O O O O O O O O 6'' �p��'; � ' i !�YG ..,+. .i.: .;i- 0 0 0 0 0 0 0 0 0 0 0 0 �' �' O O O O O O O O O O O a � � O O O O O O O O O O O I M O�N � e`�r UUO ac�v E � � c t � W � W Q L i C � m o� �i� fD O o V N Q Q� G � O Y � C O V G w N � � � � � 0 � � 0 � Q � � d' O,I I i �I . blinY IV:A il'.':;•%:..•� O O O O(O N O O O CO Q tII"17 ilw i! Q> 'j �4! ;';T � ^ r (O rn u) {;lfl �'�j� o��; q, 1! i. r m U c � N O �,.Il;��il�i <p'��i;.;�,: :`� (p �� ^ �vj d: .i.� ,y;p.l' �ljrii jl''i, 7 W '' :.�,' ��°; ;;";; i;i�; i5 d;:i,:�' .�Ei;�;i:�`'i,i��= �� _ _'_ —'—'--,...,�i�Nii!i�'.� __'�—��''_�'''_ I E 8 � I � o J O Ia � I J N N y u� X £ I . N f-- � � p`� O N 'C _ N � '� m o� o�^ � q�c I �� �a m a E� G .O Q a N � N C 0 0 ��- y 10 (� N O C j 'O � Q °a , �' w rn u' U C) nmi `1 0 �i U�- E c'y � N�aX�ip m ;�' Nf 'p i�i ¢ o I L���@�-- V � N U � N N � v N N � m� �� �,v �=v � T'€>>>> 8a>>o�l (n IL � LL g fn � LC Q. Q= 2 Z(n Z Z Z Q � I __— �_ � ^-- � � � � � � � "�fnll W ^ U W fp ¢ I � O 3 LL O I O U � I- �.... , -- -- � - - 4 . 6 W C a � y R 0 N � 0 0 � � 0 � � 0 > rc ¢ N K O � C m m x n d � z v Q Nq C U rn c m b c � E U 0 d a 3 a � � a N 0 � e��i Steton Can�fmc[[an Group-Hrer, Calitoml� ITCEM I+ � 2 � 3 � 4 � 5 IB � 7 � 8 ( � 9 � � 10 � I � + I � 12 ( � 73 � � � IYfEM � � � z 3 TTEM 1 2 3 4 5 6 7 8 � 9 � �o i I++I I I I I, �� ITTEM t � 2 � 3 � ITEM � ' 2 � 3 � DETAIL COST P1tOPOSAL BREAKDOWN ProJect Name: TiUe Of Change: Subcontractor Name: assc�r�ox �I�xYN���1 �u I � � i ( � I TOTALSTLABORfQTYi G7.9 TOTALOTLABORlQTY RTL DESC1tIIT[ON �� Cretlit For Material For Contrectual Work 750va Cost Fw Material ForAdditional Work 1 SOOva SUBTOTAL � U - HR - HR - HR - HR - HR - HR - � HR - � HR - � HR - I HR - I HR - I HR - �HR� - � � SUH1YYfAL II HR HR HR PCO 10R1 ACD 7R4 COR 12R1 1 WAGE (rt} B&iYEF11S � my x�Te � ,Urr- nn� � anrr I - � - � - � � I ' I ' ' � ' - � - - � - - I - I - � - I - - I - I ' � ' � ' � ' ( ' I - � - � - � . - � - � ' � - I - I - � • I - � - �, - � - � - � - � • � - ( - � - � - �� " I - � ' f _ ( ' � � ' � ( Q7'Y WAGS(ot) B&NEFPl'3 � DR RATE � A�lT_ RA1T: AnTf � - � ' � _ � � ' ' ' - I RENTAL M7'L M'IZ RENTAL CHARGFS MATERIAIS � QTY Tf QTY RATE AMT RAT6 � AMT I - LS (1.0) ' ' 3.448.00 (3.448)� - LS 7.0 - � - 7214.00 72�4� Henderson Commu�ily Building ACD #7Ri - Battery InverterAnd Egress Ligh6ng System Circle City ElecVic, Inc. c�s � � SUBTOTALI TAX� _ TOTAL� DESCRIPC[ON DESCATM'ION � - ! - � I - I I I � � ' - � - - - � ' ' I - • - ( _- ' " � _ _ " �. - - � - - � - � " � ' � - - � - � ' � - � - � - � _ � ' ( ' ' - � - I - I - � - I - I - � so.00 I - I - I � I - � 3,788 � ( I • 775I 292) I I - ! a,ass I ROYALTIES UNIT ' Q7'Y- I RATE A11i7' ' � ' ' � TOTAL I I _� � PERMCig - _ _ � I7N1T � QTY ( RA77S AMT � - � � - � - - � TOTAL I I I - I � � I I ( SCG COR 12 - 07-03-20.x1s 1 0l 1 3/20/2007 �`�tv�.e�cryc . r� �. v ^ � ����� ��VERSI P��: �P�.��: � � � � , CIRCLE CITY ELECTRIC. nvc 18726 Van Bvren Blvd, Riverside, CA 92508 951-789-6872 (phone) 951-189-8349 (fa�c) Lic No. CIO-S82166 Change Order No. C4-886 (Price only) Job Name: Henderson Community Center Attn: Stetop Construction Date: February 8, 2007 ELECI'R1CAL WORK *s�r�**awt►tafat+r►rssstartt*+t*�wrrrtt�i+a+++*+r�*�s,rtwf*.t�rt+rs4sWrwartwr�rtrt+�w**wrr Description: Add ISOOva inverter and delete 750va inverter. Reference: ACD #7R1 Add 1500va inverter plua te=: 57,214.00 Credit 750va inverter plus taz: 448.00 Total cost: $3,766.00 NOTES: t. NORMAL WOR[UNO HOURS (DAY 9[DP!} NO ACCELERA7iON C�TS ARE INCLUDED IN THIS PROPOSN,. 2. BY SIOMNa THIS DOCUMEN'1' YOU AaREE YOU ARE AVfHORIZED TO DO SO ANQUNDERSTANQ yOURCOMPANY IS FINACIALLY RESPONSIBLE FOR'CHE ABOVE WRITTEN PR[CE. TN6RE ARE NO FJCCEPT[ONS! 3. TMS PROPO5AL CONTAQJS PROPRfETORY INFORMATION AND 15 CONSIDEREDCONFmENliAL TO THE RECEPIENT. IT IS SUBMI'tTCD UPON THE E7�RES3 CONDI7TON TfiAT THE INFOItMATfON CONfAINED HEREIN WILL hYYf HE 3tELEASED TO COMPEIITORS OR OTHERWi9E BE USED DIRECTLY, OR LNDIRLCIT.Y, IN q WAY DE'CRIMEN7'qy TO 77� INTEREST OF CIRC[,E CTTY ELECfR[C, INC. 4. VANDAI.ISM, THEFT AND IIAMAGE TO MATERIAL OR / AND EQ[J�MeNT INSTALLED OR / AND STORED ON STfE 15 RESPQNSIBii.lTY OF dENERAL CONTRACTOR OR / AND OWNER 5. TH[S PR[CE IS GOOD FOR 30 DAYS ONLY 6. WORKWILLCAMbf6NCEONLYAFI'ERRkCIEPTOFTHtSS16NEDDIX.UMENT C.C.E. ALJTHORIZED SIGNATtJRE: r1p�; PR1NT NAME: lYOTE: THIS PROPOSAL WILL ACT AS A PiTRCHASE ORDER TO COMPLETE THE WORK ABO''VE WHEN SIGNED HY BOTH PART�S Acceptance of proposal: the above prices, specifications and conditions are satisfaaory and are hereby accepted. Circle City EIectric Inc is authorized to perforrn the work as specified. SIGNATURE: DATE: Page 1 of 1 Justin Kazak From: CcebobboswellQaol.com Sent: Friday, February 09, 2007 1:54 PM To: Justin@stetoncg.com Cc: CCERICKC@aol.com SubJect: Re: Add 1500va inverter and delete 75Dva inverter There is nothing to put on a break down. We are giving a credit on an inverter and an adder on an inverter. There is no added la6or. The only cost is the inverter itself. I guess I couid have added labar for fhe larger unit but I didn't. I do not know what you meart by not furnishing a break down. C1 has a break down, C2 is a lighting package so there is only a price difference between the old quote and the new one. There is no labor in a quofe. C3 is void because now they want the inverter back but in a larger size. There were added fixtures in C3 and conduit and labor but now with the larger inverter we are back to the original install. CA is the larger inverter. The low voltage quote is from a low voltage contractor. They are the oniy low volt contractor that would give me a quote. All the resk of the contractors either would not give me a price or had questions. I sent you this RFI but did not receive a response. I have received three different quotes from this contractor so it looks like they are not sure what is needed either. Bob Boswell Circie City Electric, Inc. 951-789-6672 x 111 951-789-0585 ( fax ) email: ccebobboswefl@aol.com Bob Boswell Cirde City Electric, Inc. 951-789-f872 x 111 951-789-0585 ( fax ) emeii: ccebobboswell@aol.com 3/20(2007