HomeMy WebLinkAboutSR - R22600A - CO2 - Const @ Henderson Cmty BldPALM DESERT REDEVELOPMENT AGENCY STAFF REPORT REQUEST: APPROVE CONSTRUCTION CONSTRUCTION GROUP AMOUNT OF $42,403.61 BUILDING CHANGE ORDER NO. 2 TO STETON (CONTRACT NO. R22600A) IN THE FOR THE HENDERSON COMMUNITY SUBMITTED BY: MISSY WIGHTMAN, PROJECT COORDINATOR CONTRACTOR: STETON CONSTRUCTION GROUP 145 S. STATE COLLEGE BLVD., SUITE 450 BREA, CA 92821-5818 DATE: AUGUST 9, 2007 CONTENTS: CHANGE ORDER NO. 2 (C.O.R. NOS. 16, 22, 29, 30, 31, 39, 41, 43, 44, and 54) Recommendation: By Minute Motion, that the Agency Board: (1) Approve Change Order No. 2 to Contract No. R22600A for the change order requests listed above in a cumulative amount of $42,403.61 for the Henderson Community Building; and (2) Authorize the Finance Director to move $42,403.61 from contingency to base. Executive Summarv: Approval of this recommendation will allow the General Contractor to move ahead as scheduled with the attached, referenced change order request. The above -referenced change order requests total a cumulative amount of $42,403.61. Discussion: On 13 July 2006, the Agency Board authorized the award of Contract No. R22600A in the amount of $4,540,000 to Steton Construction Group for the construction of the new 5,800 square foot Henderson Community Building at the Entrada del Paseo site. Construction is currently underway and additional changes above and beyond the original contract that need to be done for a successful completion are presented here for approval. Major changes in price have occurred due to the extension of the parapets at the roofline, and the Owner -requested pricing for the installation of security cameras/equipment and low voltage systems for voice and cable data. Roof parapets needed to be extended from their original specified heights to conceal various equipment located on the building roof. The second major Staff Report Approve Construction Change Order No. 2 to Steton Construction Group (Contract No. R22600A) Henderson Community Building Page 2 of 2 August 9, 2007 change was the low voltage systems for voice and cable that are typically not included in the original contract, but rather installed through conduit by a separate specialty contractor after the building is complete. With such a unique type of construction, staff requested this work be priced now under the general contractor, so the Agency could potentially avoid any problems that would require a contractor to have to go back in behind the walls in the future, which would require wall patches. The remaining change orders are due to changes in the plans that were not a part of the original scope that the contractor bid. These items resulted from inspections that required a change in installation to meet code, specifics not shown on the drawing at bid time that needed additional clarifications, and Owner -directed requests for pricing. All of these changes result in a contract price increase of $71,156.47. At the time of bidding and the award of contract, the landscape plans had not been completed. Instead of waiting for completion, staff put the project out to bid and adjusted the bidding specifications. The specifications stated that a placeholder of $325,000 was to be added to the Contractor's cost as a substitute until landscape plans were complete and could be accurately bid. Landscape plans have since been completed and have been priced in the amount of $296,247.14. Therefore, a credit of ($28,752.86) will be deducted from the above -stated increase, resulting in a cumulative change order amount of $42,403.61. No time extensions have been granted for Change Order 2, as it has been determined that none of the above -stated changes would have an impact on the time of completion. Based on review by the Architect, Construction Manager, and staff, Change Order No. 2 is recommended for approval to allow the construction of the Henderson Community Building to move forward towards completion. Submitted by: _WJ-'1Ar2 Missy Wi6Ktman Project Coordinator Department Head: `have Yrig n Director Re(development/Housing Carlos L. Orteg executive Director Ali- - rle; Martin Alvarez Redevelopment Manager Approval: � /t Js in McCarthy AC Redevelopm<z� Paul S. Gibson, Director of Finance .qr bVlE ' BY RDA G:\rda\Melissa Wightman\Henderson Community Building\Staff Reports\Staff Report- Change Order2.doc ON F-9—nt) VERIFIED BY 12&J 1y'C m Original on file with City Clerk's Office x 0 0 v c 0 d N Y1 L O� N N C N C St d n e PALM DESERT REDEVELOPMENT AGENCY CONSTRUCTION CHANGE ORDER Contract Purpose Construction of Henderson Community Building Consultant's Name Steton Construction Group Address: 145 South State College, Suite 450 Brea, CA 92821 Contract # / P.O. # R22600A 13386 Change Order No. 2 Contingency: YES I NO X Account No. 850-4358-433-4001 Project No. Vendor No. 9494 You are hereby requested to comply with the following changes from the contract plans and specifications: DESCRIPTION OF CHANGES DECREASE INCREASE (Supplemental Plans, Specifications, and Directives dated Attached) In Contract Price In Contract Price Actual bid for landscaping was $296,247.14 against the budget placeholder amount of $325,000.00. 28,752.86 Extension of parapets at roofline, installation of security cameras/equipment, and low voltage systems for voice and cable data. TOTALS: NET CHANGE IN CONTRACT PRICE: JUSTIFICATION: 28, 752.86 TOTAL BUDGET FOR PROJECT: + 4,524,941.00 CONTINGENCY: Less: Expend. & Encumb. To Date: - 4,524,941.00 Amount Approved by Board: + Less: This Change Order Amount: - 42,403.61 Less: Prior Change Order(s): BALANCE OF BUDGET Less: This Change Order: - REMAINING FOR PROJECT: (42,403.61) Balance Remaining of Contingency: 71,156.47 71,156.47 42,403.61 454, 000.00 (15,059.00) 42,403.61 426,655.39 The amount of the Contract will be (DaorOaael) Increased by the Sum of: Fortv-two Thousand Four Hundred Three and 61/100 Dollars ($42,403.61). G Vda\Beth Longman\Staff Reports\Wightman\Steton CO 2 Form.doc See reverse Contract R22600A Change Order No. 2 Continued from front This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order items for a lump sum price agreed upon between the Contractor and the Palm Desert Redevelopment Agency, otherwise referred to as Owner. Contract Time Extension -0- Days. Revised Contract Total $4,567,344.61 The undersigned Contractor approves the foregoing Change Order # 2 as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order # 2 . The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of that directly or indirectly related to the approved time extension, required to complete the Change Order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Change Order shall be effective when approved by the Owner. Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies, waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as any and all consequential damages. This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have required signatures as per the purchase resolution. 3 REQUESTED BY: CERTIFIED FUNDS AVAILABLE: EXECUTIVE DIRECTOR FINANCE DIRECTOR NOTE: No payments will be made prior to Executive Director and Agency Board approval 2. ACCEPTED BY: CONTRACTOR Date Accepted 4. APPROVED BY: RICHARD S. KELLY, CHAIRMAN 819/07 SECRETARY 8/9/07 G-Vda\Beth Longman\Staff ReportsMightman\Steton CO 2 Form doc See reverse douglas e. barnhart, inc. July 27, 2007 Melissa Wightman Project Coordinator City of Palm Desert, Redevelopment Agency 73-510 Fred Waring Drive Palm Desert, CA 92260-2578 Subject: deb Project #6016 Henderson Community Building Entrada del Paseo 72-559 Highway 111, Palm Desert Re: Recommendation for awards of Change Order Request 29 — Steton Construction Group Ms. Wightman, We have reviewed the attached documentation received for Change Order Request 29, ACD 19/PCO #21 as listed below from Steton Construction Group for the above named project. Based on our review, we recommend award as follows: Change Order Request # 29 — ACD # 19/PCO # 21 Recommended amount of Change Order with no time extension: $14,003.49 Sincerely, Michael Lugo -Thompson Project Manager douglas a barnhart, inc. douglas e. barnhart, inc. July 27, 2007 Melissa Wightman Project Coordinator City of Palm Desert, Redevelopment Agency 73-510 Fred Waring Drive Palm Desert, CA 92260-2578 Subject: deb Project #6016 Henderson Community Building Entrada del Paseo 72-559 Highway 111, Palm Desert Re: Recommendation for awards of Change Order Request 41 — Steton Construction Group Ms. Wightman, We have reviewed the attached documentation received for Change Order Request 41, ACD 21/PCO #23 as listed below from Steton Construction Group for the above named project. Based on our review, we recommend award as follows: Change Order Request # 41 — ACD #21.1/PCO # 23 — Add (14) CXS 100 Wattstopper & Delete (14) WI-300. Lighting controls. Recommended amount of Change Order with no time extension: $1,690.00 Change Order Request # 41 — ACD #21.5/PCO # 23 — Relocate receptacle @ conference room 1 & 2. Recommended amount of Change Order with no time extension: $227.00 Change Order Request # 41 — ACD #21.8/PCO # 23 — Added Master on/off switch. Recommended amount of Change Order with no time extension: $1436.00 Change Order Request # 41 — ACD #21.9/PCO # 23 — Added solar breaker. ($592.00) This is NOT approved, it is included in COR # 44 Recommended amount of Change Order with no time extension: NONE Change Order Request # 41 — ACD #21.10/PCO # 23 — Added receptacle@ solar equipment room. Recommended amount of Change Order with no time extension: $281.00 The next three items are associated with the $10,502 line item for the inverter system and HVAC controls. Change Order Request # 41 — ACD #21.1la/PCO # 23 —Inverter Circuit. ($687.00) This is NOT approved, it is included in COR # 38 Recommended amount of Change Order with no time extension: NONE Change Order Request # 41 — ACD #21.11b/PCO # 23 — Controls for Variable air volume ($5,524.00). This is NOT approved: Specification 16010 1.7 A States controls wiring regardless of voltage is to be provided. Specification 16109 3.1 C. States to coordinate HVAC voltage requirements with drawings and equipment submittals. Recommended amount of Change Order with no time extension: NONE Change Order Request # 41 — ACD #21.11c/PCO # 23 — Battery Inverter ($4,291.00). This is NOT approved: Previously paid in COR # 12 R 1 — ACD #7R 1 /PCO # 10 R 1 Recommended amount of Change Order with no time extension: NONE Change Order Request # 41 — ACD #21.13/PCO # 23 — Access panels furnish and install. Recommended amount of Change Order with no time extension: $1923.04 Change Order Request # 41 — ACD #21.14/PCO # 23 — Revised to air craft cable for duct work. Recommended amount of Change Order with no time extension: $2036.90 Change Order Request # 41 — ACD #21.21/PCO # 23 — J box at partition door Recommended amount of Change Order with no time extension: $169.00 Change Order Request # 41 — ACD #21.22/PCO # 23 — End to end fixtures at women's bath. ($ 1,289.00). This is NOT approved: Shown on Architectural plans. Recommended amount of Change Order with no time extension: NONE Change Order Request # 41 — ACD #21.24/PCO # 23 — Add (3) Exit lights. Recommended amount of Change Order with no time extension: Change Order Request # 41 — ACD #21.25/PCO # 23 — Add additional sprinkler heads This is NOT approved: Internal coordination by contractor is required. Recommended amount of Change Order with no time extension: Summary: Change Order Request # 41 — ACD #21/PCO # 23 — Total amount from work sheet. Recommended amount of Change Order with no time extension: Sincerely, i ael Lu o-Thompson Project Manager douglas a barnhart, inc. $747.00 ($2,195.00) NONE $9,087.33 Post Office Box 270399, San Diego, Califomia 92198-2399, (858) 385-8200, FAX (858) 385-8201 www.debconstruct.com douglas e. barnhart, inc. July 26, 2007 Melissa Wightman Project Coordinator City of Palm Desert, Redevelopment Agency 73-510 Fred Waring Drive Palm Desert, CA 92260-2578 Subject: deb Project #6016 Henderson Community Building Entrada del Paseo 72-559 Highway 111, Palm Desert Re: Recommendation for awards of Change Orders — Steton Construction Group Ms. Wightman, We have reviewed the attached documentation received for Change Order Requests listed below from Steton Construction Group for the above named project. Based on our review, we recommend award as follows: Change Order Request # 30 — ACD #20, PCO # 22 — Cabinetry to match slope on wall. Recommended amount of Change Order with NO time extension: $793.7 Change Order Request # 43 — ACD #28, PCO # 30 — Security Cameras rough electrical work. Recommended amount of Change Order with NO time extension: $14,156.19 1 /_ C nge O Request # — D #28, P 30 —Sec ity Ca eq ment an sta ion. C� R co ende t of Change •with NO time extension: 25,780.0 U I Change Order Request # 31 — ACD #22, PCO # 24 — Cabinetry to match slope on wall. Recommended amount of Change Order with NO time extension : $524.98 Change Order Request # 39 — ACD # none, PCO # 39 — Install fire line from outside project line to building. Recommended amount of Change Order with NO time extension: $5694.84 Change Order Request # 54 — ACD none, PCO # 40 — Revised air grille. Recommended amount of Change Order: with NO time extensi $673.23 Change Order Request # 16 — ACD #10, PCO # 13 — Low Voltage Systems; Voice/Cable Recommended amount of Change Order with NO time extension: $19,846.03 Change Order Request # 44 — ACD #24, PCO # 26 — Solar Disconnect, revised cabinetry and electrical. Recommended amount of Change Order with NO time extension: $6,954.07 Michael Lugo -Thompson Project Manager douglas a barnhart, inc. Post Office Box 270399, San Diego, Califomia 92198-2399, (858) 385-8200, FAX (858) 385-8201 www.debconstruct.com