HomeMy WebLinkAboutSR - R21090A CO1- Entrada Del Paseo Phase 2 LndscpingContract No. R21090A PALM DESERT REDEVELOPMENT AGENCY STAFF REPORT REQUEST: APPROVE CHANGE ORDER NO. 1 (NO COST) EXTENDING THE CONTRACT COMPLETION DATE TO MAY 14, 2008, FOR CONTRACT NO. R21090A WITH SIERRA LANDSCAPE COMPANY, INC., FOR CONSTRUCTION OF THE ENTRADA DEL PASEO PHASE 2 LANDSCAPING SUBMITTED BY: MARTIN ALVAREZ, REDEVELOPMENT MANAGER CONTRACTOR: SIERRA LANDSCAPE COMPANY, INC. P.O. BOX 14247 PALM DESERT, CA 92255-4247 DATE: APRIL 24, 2008 CONTENTS: CHANGE ORDER NO. 1 Recommendation: By Minute Motion, that the Agency Board: (1) Approve Change Order No. 1 (no cost), extending the completion date to May 14, 2008, for Contract No. R21090A with Sierra Landscape Company, Inc., for the construction of Entrada del Paseo Phase 2 landscaping Executive Summary: Approval of staff recommendation will approve a no -cost change order to modify the Eric Johnson Phase 2 Landscaping project completion date from February 25, 2008, to May 14, 2008. Staff recommends approval. Discussion: On September 13, 2007, the Agency Board award Contract R21090A to Sierra Landscape Company, Inc., in the amount of $2,440,600 for the Entrada del Paseo Phase 2 Landscaping. The project includes the following components: • Eric Johnson Landscaping Phase II (Indian Canyon); • Multi -Sensory Gardens (north of Henderson Building); • Landscaping surrounding La Spiga Restaurant; • Landscaping adjacent to the Palm Valley Storm Channel Staff Report Approve Change Order No. 1 to Contract R21090A to Sierra Landscape Company, Inc. for construction of the Entrada del Paseo Phase 2 Landscaping Page 2 of 2 April 24, 2008 The Notice to Proceed was issued on October 29, 2007, with a 120 day completion (February 25, 2008). The project has made significant progress and is 85 percent complete. The Indian Canyon landscaping section (north of Visitor Center) encountered a delay in securing the specialized granite slabs required to complete the Parson Walls. The delivery of the slabs was delayed 78 days due to weather conditions (snow pack) in the Sierra Nevada region where the product is mined. Being a critical path component of the Indian Canyon section, no other work could be performed in this area until the Parson Wall system was installed. Sierra Landscaping has requested a change order to modify their contract completion date from February 25, 2008, to May 14, 2008. The Agency's Construction Manager and staff have reviewed the request and believe it is justifiable. Therefore, Staff recommends approval of a no -cost change order to extend the contract completion date to May 14, 2008. Submitted by: Merin Alvarez, Redevelopment Mgr. Department Head: Dave Yrig?Y01", Dir. of Red./Housing &4�tlw Carlos L. Ort4ya, Executive Director BY RDA ON q-C�- VERIFIED BY J Original on file with City Clerk's Office Approval: nt G\rdaWartin Alvarez\Entrada\EJ PhIhStaff Report- CO No 1 Sierra.doc / C � t Z / O U Q C) o� f � o o Z V O p O CL Uj N A V. N .3 Z W = Z cn v a aUO Ouj �v LU 0. 00. O U -0o0 Z 04 cr uj O U Z U i e � T 'L L Y � o � cm c Z U � m � Z � u' o h-- U o v O a: ZO 4 Q o V cc O O 0 00 O 0 0 O O o 0 c4 O cfl .r O co Iq p 0 N O O O .� > 14 4 N 0 N 0 b O O o 0 U 0 0 O N 'J 0 UOQ V i V c O a. Z ULu � 0 Z Z F— O 00 U U N co Q Q Q C) Z Z ? aD (� 0 E O 00 LO �t N M � O U ALM DESERT REDEVELOPMENT AGENCY 'ONSTRUCTION: CHANGE: ORDER ),tract Purpose Construct Entrada del Paseo Phase 2 Landscaping ►nsultant's Name Sierra Landscape Company, Inc. (dress: 73-771 Dinah Shore Drive, Suite 200 Palm Desert, CA 92211 contract # / P.O. # R21090A 14543 Change order No. 1 contingency: YES NO X Account No. 850-4358-433-4001 Project No. Vendor No. :)u are hereby requested to comply with the following changes from the contract plans and specifications: IESCRIPTION OF CHANGES DECREASE INCREASE I upplemental Plans, Specifications, and Directives dated Attached) In Contract Price in Contract Price construction time extension only TOTALS: - NET CHANGE IN CONTRACT PRICE: - JSTIFICATION: OTAL BUDGET FOR PROJECT: + 2,440600.00 CONTINGENCY: Less: Expend. & Encumb. To Date: - 2,440:600.00 Amount Approved by Board: + Less: This Change Order Amount - Less: Prior Change Ordegs): - BALANCE OF BUDGET Less: This Change Order: - REMAINING FOR PROJECT: - Balance Remaining of Continqency. - f: 9 91ar.6 ($ ). -OYMth LonW w %" R.P"WvanzWWM 00 1A%C see reverse ... ►ntract R21090A Change Order No. 1 Continued from front pis Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish uipment and materials, and perform all work as necessary or required to complete the Change Order items for a np sum price agreed upon between the Contractor and the Palm Desert Redevelopment Agency, otherwise referred as Owner. )ntract Time Extension 78 Days (to May 14, 2008). 3vised Contract Total $2,440.600.00 ie undersigned Contractor approves the foregoing Change Order # 1 as to the changes, if any, in the contract ce specified for each item including any and all supervision costs and other miscellaneous costs relating to the ange in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said range Order # 1 The Contractor agrees to furnish all labor and materials and perform all other necessary work, ;lusive of that directly or indirectly related to the approved time extension, required to complete the Change Order ms. This document will become a supplement of the contract and all provisions will apply hereto. It is understood 3t the Change Order shall be effective when approved by the Owner. :ecution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies, gives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of related to the subject of the Change Order, whether known or unknown, including but not limited to direct and jrect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as iy and all consequential damages. its document will become a supplement to the Contract and all provisions will apply hereto, all items included above ust have required signatures as per the purchase resolution. REQUESTED BY: CERTIFIED FUNDS AVAILABLE: EXECUTIVE DIRECTOR FINANCE DIRECTOR NOTE: No payments will be made prior to Executive Director and Agency Board approval 2. ACCEPTED BY: CONTRACTOR Date Accepted 4. APPROVED BY: JEAN M. BENSON, CHAIRMAN 4/24/08 SECRETARY 4/24/08 ra.wa, LoWran~ R.p«e Wvw*tSWm CO I.dw See reverse ... Mailing Address bierra P.O. Box 14247 Palm Desert, CA 92255 DSCE�(760) 345-5959 LAN1% (760) 345-03280328 (0 To: Mike Lugo Thompson City of Palm Desert Attn: Public Works 73510 Fred Waring Dr. Palm Desert CA 92260 Proposed Change Order # 6-A Date: )3110/2008 Project: Entrada del Paseo Attn: Public Works EL PASEO/PAINTER'S PATH Palm Desert CA 92260 Description of Work Amount Additional Schedule Days Add Days to Schedule - 78 Days Project Completion Date May 14, 2008 PARSONS BOULDER WALL - CRITICAL PATH ITEM, NO OTHER WORK ABLE TO START WITHOUT BACKFILL OF WALL/GRADING AFTER WALL COMPLETE. FINAL APPROVAL OF RED MOUNTAIN STONE MATERIAL/START OF PROCUREMENT 12/21/07. RECEIPT OF RED MOUNTAIN SLABS FROM SOLE SOURCE SUPPLIER 313108 Total Change: $0.00 Aoaroval Slanature: Auth. Rep.: Date: Entered I3y:308 CrisOne Dzlelak Sierra Rep.:_Date: �'I r I d 7072 Rac# 1406 douglas e. barnhart, inc. March 31, 2008 Melissa Grisa Project Coordinator City of Palm Desert, Redevelopment Agency 73-510 Fred Waring Drive Palm Desert, CA 92260-2578 Subject: deb Project #6016 Entrada del Paseo Landscape Phase II Highway l I I & Painters Path, Palm Desert Re: Recommendation for awards of Change Order — Sierra Landscape Company, Inc. Ms. Grisa, We have reviewed the attached documentation received for Change Order Requests listed below from Sierra Landscape Company, Inc. for the above named project. Based on our review, we recommend award as follows: Multiple added scope including contract extension per COR #6 COR Descriotion Amount 006 Requested 78 calendar day schedule completion extension $0 Total: $0 Original Contract Value: $2,440,600 Previous Change Orders: $0 Current Contract Value: $2,440,600 Amount of current Change Order (C/O #1): $0 New Contract Value including this Change Order (C/O #1): $2,440,600 New Contract duration will be changed by: 78 Days Revised Substantial Completion date as of this Change Order: May 14, 2008 Sincerely, Mark C appell, Senior Project Manager douglas a barnhart, inc.