HomeMy WebLinkAboutSR - R24980A CA1 - Desig Svcs - Country Village Apt.PALM DESERT REDEVELOPMENT AGENCY STAFF REPORT REQUEST: APPROVE PROFESSIONAL SERVICES AMENDMENT NO. 1 IN AN AMOUNT NOT -TO -EXCEED $25,500 FOR CONTRACT NO. R24980A WITH INTERACTIVE DESIGN CORPORATION TO PREPARE DECONSTRUCTION AND RECYCLING PLANS FOR DEMOLITION OF COUNTRY VILLAGE APARTMENTS SUBMITTED BY: BRYCE L. WHITE, PROJECT ADMINISTRATOR CONTRACTOR: INTERACTIVE DESIGN CORPORATION 199 S. CIVIC DRIVE PALM SPRINGS, CA 92262 DATE: APRIL 24, 2008 CONTENTS: NOTICE OF EXEMPTION PROFESSIONAL SERVICES AMENDMENT NO. 1 TO CONTRACT NO. R24980A INTERACTIVE DESIGN CORPORATION AMENDMENT PROPOSAL Recommendation: By Minute Motion, that the Agency Board approve Professional Services Amendment No. 1 in an amount not -to -exceed $25,500 for Contract No. R24980A with Interactive Design Corporation to prepare deconstruction and recycling plans for demolition of Country Village Apartments. Funds are available in Account Nos. 870-4195-466-3092 and 854-4195-466-3092. Executive Summarv: Approval of staff's recommendation will allow preparation of environmentally friendly deconstruction and recycling plans for demolition of the Country Village Apartments. Rejection of staff's recommendation will require demolition and disposal without plans for reuse and recycling. Discussion: In August 2006, the Agency contracted with Interactive Design Corporation (IDC) to provide site utilization and configuration at the existing Country Village Apartments' site at 42-555 Washington Street on the southwest corner of Washington Street and Avenue of the States and adjacent property to the south at 42-615 Washington Street. On October 11, 2007, the Agency Board approved a contract with IDC to develop a schematic site plan for these properties to include Casey's Restaurant, a future fire station, and an affordable senior apartment project, including a conceptual architectural design. This item was on the January 24, 2008, agenda and was continued to a date uncertain to allow staff to address concerns raised by the public regarding compliance with the California Environmental Quality Act (CEQA). Staff Report Amendment No. 1 Contract R24980A (Interactive Design Corp.) — Country Village Apartments Page 2 of 2 April 24, 2008 CEQA Review For the purposes of CEQA, the Director of Community Development has determined that the proposed preparation of engineering plans by which the Country Village Apartments could be demolished is part of a study leading to a potential project that has not been approved, adopted or funded, and therefore constitutes a Class 6 Categorical Exemption. It will not result in a serious disturbance to any environmental resources and, therefore, requires no further CEQA analysis. Before the proposed improvements can be built, the existing Country Club Apartments will need to be removed. A relocation plan has been prepared for the existing tenants, and removal of the existing buildings is intended to begin shortly after all of the units are vacated. The subject professional services amendment will provide plans for environmentally friendly removal of the buildings and clearing of the site. IDC will provide plans and specifications for the following: Phase One • Remediation of hazardous materials • Deconstruction and demolition of the buildings above the concrete slabs • Reuse and recycling of removed materials • Disposal of non -recyclable materials Phase Two • Deconstruction and demolition of the balance of the site, including concrete slabs, asphalt, and below grade items, which will remain in place until site grading begins to limit fugitive dust and erosion • Reuse and recycling of removed materials • Disposal of non -recyclable materials • Crushing and reconditioning of concrete and asphalt on site (optional) IDC's scope of services also include: (1) preparation of bid documents for Phase One; (2) contract administration for Phase One; and (3) coordination and estimated cost for professional services provided by Civil Engineer. Staff recommends approval of the subject amendment to prepare deconstruction and recycling plans for demolition of the Country Village Apartments. �itted by- "e ite N�fin Alvarez ect dmirator Redevelopment Manager Departt Head' Dave Yrigoyen Director of R evelopment/Housing Approval: Carlos e�er,xecutive Director G \rda\Beth Longman\Staff ReportsUhite\Interactive Amend 1 Cty Vill 042408.doc roval: i McCarthy A edevelopment Aa6l S. Gibson, Finance Director PROJECT NAME COUNTRY VILLAGE APARTMENTS SUMMARY OF CONTRACT CHANGE ORDERS CONTRACTOR: INTERACTIVE DESIGN CORP CONTRACT NO. R24980A ORIGINAL CONTRACT ORIGINAL CONTINGENCY ORIGINAL TOTAL CO # Change Order Description 1 Additional design services 2 3 4 5 TOTALS CONTRACT Change Order Amount 25, 500.00 $ 25,500.00 % of Contract 45.13% 0.00% 45.13% Original Appropriation Allocated to THIS CONTRACT (not to entire project) f.1111P.FBII10 Additional Revised Appropriations Contract allocated to THIS Total CONTRACT 82, 000.00 For Internal Use Only - DO NOT SEND TO VENDOR g/rda/Beth Longman/Staff Reports/Interactive CO Log Contingency Balance for this contract NOTICE OF EXEMPTION TO: ❑ Clerk of the Board of Supervisors FROM: Palm Desert Redevelopment Agency or 73-510 Fred Waring Drive t] County Clerk Palm Desert, CA 92260 I . Project Title: 2. Project Location — Identify street address and cross streets or attach a map showing project site (preferably a USGS 15' or 7 1/2' topographical map identified by quadrangle name): 3. (a) Project Location — City: (b) Project Location — County: 4. Description of nature, purpose, and beneficiaries of Project: 5. Name of Public Agency approving project: 6. Name of Person or Agency carrying out project: 7. Exempt status: (check one) (a) ❑ Ministerial project. (b) ❑ Not a project. (c) ❑ Emergency Project. (d) O Categorical Exemption. State type and class number: (e) ❑ Declared Emergency. (f) ❑ Statutory Exemption. State Code section number: (g) ❑ Other. Explanation: j 8. Reason why project was exempt: JTB\21589. 1 \CITY\2006 Country Village Apartments: Relocation Plan and Preparation of Demolition Specifications SW Corner of Avenue of the States and Washington Street Palm Desert, California Palm Desert Riverside County Adoption of a relocation plan will allow the Redevelopment Agency to assist approximately twelve residents of the Country Village Apartments to move to decent, safe, and sanitary housing that is affordable to them. Preparation of demolition plans and specifications will allow further study and analysis of a new project to provide affordable housing. The scope of such new project is not yet clearly defined. City of Palm Desert and its Redevelopment Agency I Palm Desert Redevelopment Agency Class 6 categorical exemption for the preparation of plans and specifications for demolition. 15061.3.b Exemption for approval of a relocation plan It can be clearly seen that the relocation of a limited number ! of residents poses no possibility of a significant effect on the environment, so preparation of a relocation plan is exempt from further review under Section 15061 (b) (3) of the California Code of Regulations, Title 14, Division 6, Chapter 3. Additionally, the preparation of engineering plans by Which the Country Village Apartments could be demolished is part of a study leading to a potential project that has not been approved adopted, or funded. It will not result in a serious FORM "B" disturbance to any environmental resources and, therefore, constitutes a Class 6 categorical exemption and requires no further CEQA analysis. 9. Contact Person: Martin Alvarez, Redevelopment Manager Telephone: 760.346.0611 10. Attach Preliminary Exemption Assessment (Form "A") before filing. Date Received for Filing: Signature (Lead Agency Representative) (Clerk Stamp Here) 16ifd—&W �� C-�"'^""�.J�'►� e�° �'�jt Title JTB\21589. 1\CITY\2006 FORM `B" )ALM DESERT REDEVELOPMENT AGENCY 'ROFESSIONAL SERVICE AMENDMENT ;ontract Purpose Professional design services to develop a senior housing project at the Country Village site ;onsultant's Name Interactive Design Corporation ,ddress: 199 S. Civic Drive Palm Springs, CA 92262 Contract # / P.O. # R24980A 14696 Amendment/ 1 Change Order No. Contingency: YES NO X Account No. 870-4195-466-3092 (86%) 854-4195-466-3092 (14%) Project No. Vendor No. 326 'ou are hereby requested to comply with the following changes from the contract_ plans and specifications: DECREASE INCREASE DESCRIPTION OF CHANGES In Contract Price In Contract Price Additional design services 25,500.00 TOTALS: NET CHANGE IN CONTRACT PRICE: IUSTIFICATION: TOTAL BUDGET FOR PROJECT: + 56,500.00 Less: Expend. & Encumb. To Date: - 56,500.00 Less: This Change Order Amount - 25,500.00 BALANCE OF BUDGET REMAINING FOR PROJECT: (25,500.00) CONTINGENCY: Amount Approved by Board: + Less: Prior Amendment(s): - Less: This Amendment: - Balance Remaininq of Contingency. 25,500.00 25,500.00 the amount of the Contract will be (DOGFeased) Increased by the Sum of: Twentv-five Thousand Five tundred & no/100 Dollars ($25,500.00). :Vdakaeth Longman\staR Reports\WNte\Interacbve 0"gn Amend 1.doc See reverse ;ontract R24980A Amendment No. 1 Continued from front Fhis Professional Service Amendment covers changes to the subject contract as described herein. The consultant ;hall perform all work as necessary or required to complete the Professional Service Amendment items for a lump ;um price agreed upon between the Consultant and the Palm Desert Redevelopment Agency, otherwise referred to as )wner. :ontract Time Extension -0- Days. Revised Contract Total $82.000 Fhe undersigned Consultant approves the foregoing Professional Service Amendment # 1 as to the changes, if any, n the contract price specified for each item including any and all supervision costs and other miscellaneous costs elating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Professional Service Amendment # 1 . The Consultant agrees to furnish all labor and materials and )erform all other necessary work, inclusive of that directly or indirectly related to the approved time extension, required o complete the Professional Service Amendment items. This document will become a supplement of the contract and ill provisions will apply hereto. It is understood that the Contract Amendment shall be effective when approved by the )wner. xecution of this Professional Service Amendment by the Consultant constitutes a binding accord and satisfaction that ully satisfies, waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of or related to the subject of the Professional Service Amendment, whether known or unknown, ncluding but not limited to direct and indirect costs and/or damages for delay, disruption, acceleration, and loss of )roductivity, as well as any and all consequential damages. this document will become a supplement to the Contract and all provisions will apply hereto, all items included above nust have required signatures as per the purchase resolution. REQUESTED BY: CERTIFIED FUNDS AVAILABLE: EXECUTIVE DIRECTOR FINANCE DIRECTOR NOTE: No payments will be made prior to Executive Director and Agency Board approval 2. ACCEPTED BY: CONSULTANT Date Accepted 4. APPROVED BY: JEAN M. BENSON, CHAIRMAN 4/24/08 SECRETARY 4/24/08 ;Ardal leth lorgmaMStaft RepaRslWhitekinteractive Design Amend t.doc See reverse ENE CONTRACT AMENDMENT 0709.1 mom ■N❑ INTERACTIVE DESIGN CORPORATION ARCHITECTS + DATE November 30, 2007 199 S. Civic Drive, Suite 10 Palm Springs, California 92262 TO Bryce White @ City of PD RDA T: (760) 323-4990 F: (760) 322-5308 VIA Email mail@interactivedesigncorp.com FROM Maria Song PROJECT IDC No. 0709.1 Country Village Green Deconstruction SUBJECT Contract Amendment Page I of 2 We are proceeding with development of the above referenced project In accordance with our understanding of the materialrssues noted below. Unless we rece,re written clarification or DISTRIBUTION amendment by the third business day from the date of this project record, the following will be considered as confirmed Instruction and understanding m City of PD RDA Martin Alvarez ❑ CONTRACT AMENDMENT 0709.1 Amendment to Contract Services Agreement for Architectural Design Consulting Services Dated October 01, 2007 Based upon the provisions for Contract Amendment in above mentioned contract, the following amendment shall be incorporated in the Agreement: SECTION I I -SERVICES ARCHITECT'S SERVICES: E. Demolition Plan and Specifications: Prepare a demolition plan for two phases of work. Phase One includes the demolition and/or de -construction and recycling of the buildings above the concrete slab; Phase Two includes the on -site re- conditioning of concrete, concrete with re -bar, and asphalt. a. Phase One includes the remediation of hazardous material, demolition and deconstruction of the project materials (buildings) above finish grade and finish building slab. The demolition plan will include the deconstruction recycle and reuse programs for items listed in the Palm Desert Construction/Demolition Debris Recyclers and Reuse sites determined during this phase. Items such as asphalt, concrete, concrete w/ rebar will be included as part of Phase Two work. Destination of recycled material to be provided by Lisa Ream, Recycling Technician from the City of Palm Desert. Destination of reuse sites will be finalized based on research provided by Architect. P:\0709 PD RDA Hsg\CONTRACTS\0709 I Cont Amnd rev 30NOV07.doc ■ MEN ■■■ ■■❑ INTERACTIVE DESIGN CORPORATION b. Phase Two includes the deconstruction of the project materials below finish grade and finish building slab. The demolition plan will include the deconstruction recycle program for concrete, asphalt, rebar, piping, etc. The concrete and asphalt will be crushed and reconditioned on -site for use as sub -base material for new driveways and parking areas of the proposed project. Utility Data will also be provided in this plan for reuse or permanent capping. The information of Phase Two will be provided to the Agency for inclusion in the scope of work for the construction of the proposed housing project. Note: the concrete and other paving material will remain in place both to limit fugitive dust and erosion, and for recycling as part of the as part of the construction of the new housing project. F. Preparation of Bid Documents and Bid Administration G. Contract Administration of the Demolition Phase One H. Civil Engineering Consultant: a. Site Demolition Plan: Using information from the ALTA Surveys (by DUDEK and STANTEC) supplemented by field review, Civil Engineer to provide location, size, and invert elevations of on -site utility meters, underground lines and points of connection. b. Site Demolition Plan: Civil Engineer to provide direction for on -site "potholing" to locate below grade utilities and record same on demolition plan. c. Utility Plan: Civil engineer to research and provide the sizes of existing utility line feeds to the site (laterals), off -site main line sizes, and points of connections for water, sewer, storm drain, electrical, phone, cable, and gas. 2. COMPENSATION: A. Demolition Plan and Specification for Phase One $10,000 NTX B. Demolition Plan and Specification for Phase Two $ 5,000 NTX C. Bidding and Negotiation for Phase One $ 2,000 NTX D. Contract Administration for Phase One $ 2,000 NTX E. Consultants $6,500 estimated P:10709 PD RDA Hsg\CONTRACTS\0709 I Cont Amnd rev 30NOV07.doc ■ Page 2 of 3 ■o■ man ■N❑ INTERACTIVE DESIGN CORPORATION 3. SCHEDULE: after utility information is reviewed by the design team. A. Demolition Plan and Specification for Phase One 3 Weeks B. Demolition Plan and Specification for Phase Two 2 Weeks C. Bidding and Negotiation for Phase One 3 Weeks D. Contract Administration for Phase One 3 Weeks All other provision shall remain in effect. AGREED,AND C E� Reuel Young, AIA, Pr sident C 1 g#74 Interactive Des' Corporation 199 S. Civic Drive, Suite # 10 Palm Springs, CA 92262 (760) 323-4990 Redevelopment Agency City of Palm Desert 73-510 Fred Waring Drive Palm Desert, CA 92260 (760) 346-061 1 1�olzvz� r-�-- Date / Date CADocuments and Settings\Maria\Local Settings\Temporary Internet FilesIOLKIW709 I Cont Amnd 15NOV07.doc ■ Page 3 of 3 s