HomeMy WebLinkAboutR25590 CO4 - Phase II Civil Imprvmnts @ EntradaPALM DESERT REDEVELOPMENT AGENCY STAFF REPORT REQUEST: APPROVE CONSTRUCTION CHANGE ORDER NO. 4 TO JACOBSSON ENGINEERING CONSTRUCTION, INC. (CONTRACT NO. R25590) IN THE AMOUNT OF $40,400 FOR THE PHASE 2 CIVIL IMPROVEMENTS AT ENTRADA DEL PASEO SUBMITTED BY: MISSY GRISA, PROJECT COORDINATOR CONTRACTOR: JACOBSSON ENGINEERING CONSTRUCTION, INC. P.O. BOX 14430 PALM DESERT, CA 92255-4430 DATE: MAY 8, 2008 CONTENTS: CHANGE ORDER NO. 4 (C.O.R. P019, P021, AND C004) Recommendation: By Minute Motion, that the Agency Board: (1) Approve Change Order No. 4 to Contract No. R25590 in the amount of $40,400 for the Phase 2 Civil Improvements at Entrada del Paseo. Executive Summary: Approval of this recommendation will allow the General Contractor to complete the Entrada del Paseo Phase II Civil Improvements. The proposed Change Order addresses minor site modifications, a series of deducts and additions regarding the actual quantities of sidewalk, pavers, and curbing installed, and a revised completion date of May 16, 2008. Attached please find a summary table with itemized costs and credits: Site Modifications: Cost Revised storm drain to accommodate handicap access $8,400 in front of the Henderson Building Actual Material Bid Quantities: Cumulative change $32,000 (see table on Page 2) New Completion Date May 16, 2008 Cumulative Total: $40,400.00 Staff Report Approve Change Order No. 4 to Jacobsson Engineering Construction, Inc. (Contract No. R25590) Page 2 of 3 May 8, 2008 The proposed Change Order will improve the project's over-all safety, accessibility and will close out the project. Change Order No. 4 in the cumulative amount of $40,400 is recommended for approval. Discussion: The original scope of work for the Entrada del Paseo Phase II Civil Improvements is complete with the exception of minor punch list items. The additional scope of work added as part of Change Order 3, which includes the paving of the originally designed turf block access road and the addition of 24 parking spaces is 90% complete. Site Modifications: C.O.R. P021 addresses the conflict between the Phase 2 Civil Improvement plans and the Henderson Community Building Plans. A ribbon gutter location required removal to maintain the handicap parking stalls required 2% grade in front of the Henderson Community Building. This modification resulted in a cost of $8,400. Material Bid Quantities: During the original bid period, contractors were given bid forms with estimates for all civil materials, including but not limited to sidewalk, curb, gutter, pavers and asphalt. C.O.R. P019 address a series of deducts and additions for differences between the estimated quantities provided on the plans and the actual materials utilized by the contractor. All quantities installed have been field verified by the Construction Manager and are justifiable. The series of deducts and additions is summarized below and results in a cumulative increase of $32,000. Material Asphalt Wedge Curb Curb w/Gutter Valley Gutter 4" Sidewalk Pavers Concrete Bands Mow Strip Completion Date Extension: Add/Deduct Quantity Actual Cost 1,060 Square Feet $3,498.00 47 Linear Feet $1,034.00 -147 Linear Feet ($3,550.00) 185 Linear Feet $5,550.00 -2,725 Square Feet ($24,661.25) 2,653 Square Feet $47,754.00 114 Square Feet $1,482.00 129 Linear Feet $1,482.00 Cumulative Total $32,000.00 As part of the addition of scope to address new asphalt paving over an emergency access road and the addition of parking spaces, the Contractor was delayed during the G \rdaWelissa Wightman\Entrada del Paseo Civil Improvements\Staff Report- Change Order4 doc Staff Report Approve Change Order No. 4 to Jacobsson Engineering Construction, Inc. (Contract No. R25590) Page 3 of 3 May 8, 2008 design and plan check process. The Contractor is requesting a no cost change to modify the completion date to May 16, 2008. Staff and the Construction Manager believe this change is justifiable and recommends approval. Based on the Construction Manager's and staff's review, Change Order No. 4 in the amount of $40,400 and a final completion date of May 16, 2008 is recommended for approval to complete construction of all civil improvements. Funds are available in Account No. 850-4358-433-4001. Submitted y: Missy Grisa Project Coordinator Department Head: Dave Yrigoy eDirector devel ment/Housing .4,Cos Executive Director Martin Alvarez Redevelopment Manager Approval: Paul S. Gibson, Director of Finance "� I BY RDA VERIFIED IBY (W iL— ( r� Original on file with City Clerk's Office G:\rda\Melissa Wightman\Entrada del Paseo Civil Improvements\Staff Report- Change Order4.doc ag PALM DESERT REDEVELOPMENT AGENCY CONSTRUCTION CHANGE ORDER Contract Purpose Construction of La Spiga Phase 2 Civil Imprvmts Consultant's Name Jacobsson Engineering Address: P.O. Box 14430 Palm Desert, CA 92260 Contract # / P.O. # I R25590 13697 Change Order No. I 4 Contingency: YES I NO X Account No. 850-4358-433-4001 Project No. Vendor No. 1 2883 You are hereby requested to comply with the following changes from the contract plans and specifications: DESCRIPTION OF CHANGES DECREASE INCREASE (Supplemental Plans, Specifications, and Directivesdated Attached) In Contract Price In Contract Price Minor site modifications, and adjustments in quantities of sidewalk, pavers, and curbing installed. TOTALS: NET CHANGE IN CONTRACT PRICE: JUSTIFICATION: TOTAL BUDGET FOR PROJECT: + 869,717.80 CONTINGENCY: Less: Expend. & Encumb. To Date: - 869,717.80 Amount Approved by Board: + Less: This Change Order Amount - 40,400.00 Less: Prior Change Order(s): - BALANCE OF BUDGET Less: This Change Order: - REMAINING FOR PROJECT: (40,400.00) Balance Remaining of Contingency. 40,400.00 40,400.00 40,400.00 69,560.00 36,553.00 33,007.00 The amount of the Contract will be (1Oereas) Increased by the Sum of: Fortv Thousand Four Hundred Eiahtv and 00/100 Dollars ($40,400.00). G.kda\Beth Longman\Staff Reports\GnsaUacobsson CO 4 Form.doc See reverse ... Contract R25590 Change Order No. 4 Continued from front This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order items for a lump sum price agreed upon between the Contractor and the Palm Desert Redevelopment Agency, otherwise referred to as Owner. Contract Time Extension 345 Days to May 16, 2008. Revised Contract Total $910,117.80 The undersigned Contractor approves the foregoing Change Order # 4 as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order # 4 . The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of that directly or indirectly related to the approved time extension, required to complete the Change Order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Change Order shall be effective when approved by the Owner. Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies, waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as any and all consequential damages. This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have required signatures as per the purchase resolution. 1. REQUESTED BY: 2. ACCEPTED BY: EXECUTIVE DIRECTOR CONTRACTOR Date Accepted 3. CERTIFIED FUNDS AVAILABLE: 4. APPROVED BY: FINANCE DIRECTOR JEAN M. BENSON, CHAIRMAN 5/8/08 NOTE: No payments will be made prior to Executive Director and Agency Board approval SECRETARY 5/8/08 G \rda\Beth Longman\Staff Reports\Gnsa\Jacobsson CO 4 Form.doc See reverse douglas e. barnhart, inc. April 14, 2008 Melissa Grisa Project Coordinator City of Palm Desert, Redevelopment Agency 73-510 Fred Waring Drive Palm Desert, CA 92260-2578 Subject: deb Project #6016 PDRDA # 967-06 Entrada del Pasco Phase It Civil Improvements Highway 111, Palm Desert Re: Recommendation for award of Change Orders — Jacobsson Engineering Construction Inc. Ms. Grisa, We have reviewed the attached documentation received for Change Order # 4 from Jacobsson Engineering Construction Inc. for the above named project. Based on our review, we recommend award as follows: 1. Jacobsson Engineering COR # PO19 for $32,000 Revised line items # 4, 5, 6, 7, 8, 22,23 2. Jacobsson Engineering COR # P021 for $8,400.00 Revised storm drain to accommodate Handicap Access infront of the Henderson Community Center. 3. Jacobsson Engineering C004: No cost request for additional time to complete City requested parking lot extension and storm drain revision. Completion date to be revised to May 16, 2008. Regards, y � Michael Lugo -Thompson Project Manager douglas a barnhart, inc. APR-14-2008 13:20 From:JACOBSSON 17603401574 CHANGE ORDER REQUEST From; Jacobsson Engineering Construction, Tnc. P.O. Box 14430 Palm Desert, CA 92255-4430 (760) 340-0194 Fax (760) 340-1574 t_i cense : 650389 To- Palm Desert Red. Agency 73510 gyred Waring Drive Palm Desert. CA 977_60-2578 To:barnhart inc P.1/1 Page 1 Request No.: C004 Request Date: 04 / 1. 4 / 08 Project: Entrada Del Pasea Ilwy 111 & E1 Paseo Palm desert. CA 92260 We hereby requesL that the Original Construction Agreement be modified and amended by the following deviations from original plans and specilic:at'ions: Change contractural erld date to May 16. 2008 due to revised scope of work (additional parking lot and revised storm inlet). It is mutually agreed that for such change the contract price is decreased by $0.00 (). Time for completion of the above cited work is hereby extended 0 days beyond any completion date set forth in LhP original contract for such work. All other provisions of the original contract and agreement shall remain in full force and effec"L without change because of the above deviations. JACOBSSON FNGINEERIIN�G CONSTRUCTION, INC. 5lgned: Dated: Title: CHANGE ORDER REQUEST From: Jacobsson Engineering Construction, Inc. P.O. Box 14430 Palm Desert, CA 92255-4430 (760) 340-0194 Fax (760) 340-1574 License: 650389 To: Palm Desert Red. Agency 73510 Fred Waring Drive Palm Desert. CA 92260-2578 Page 1 Request No.: P021 Request Date_ 03/20/08 Project: Entrada Del Paseo Hwy 111 & El Paseo Palm Desert. CA 92260 We hereby request that the Original Construction Agreement be modified and amended by the following deviations from original plans and specifications: CATCH BASIN Demo existing ribbon gutter and replace with AC. Install catch basin and storm drain pipe. $8.400.00 It is mutually agreed that for such change the contract price is increased by $8,400.00 (Eight Thousand Four Hundred and 00/10o) payable with the payments due under the original construction agreement. Time for completion of the above cited work is hereby extended 0 days beyond any completion date set forth in the original contract for such work. All other provisions of the original contract and agreement shall remain in full force and effect without change because of the above deviations. JACOBSSON ENGINEERING CONSTRUCTION. INC. Signed: Dated: Title: P. A4. CHANGE ORDER REQUEST From: Jacobsson Engineering Construction, Inc. P.O. Box 14430 Palm Desert. CA 92255-4430 (760) 340-0194 Fax (760) 340-1574 License: 650389 i U.wag nnai 1n1, r.l'C Page I Request No.: P019 Request Hate: 12/31/07 To: Project: Palm Desert Red. Agency Entrada Del Paseo 73510 Fred Waring Drive Hwy 111 & E1 Paseo Palm Desert. CA 92260 2578 Palm Desert. CA 92260 We hereby request that the Original Construction Agreement be modified and amended by the following deviations from original plans and specifications: Item 4: 3" AC over 4" AB 1060 SF Item 5: Modified Wedge Curb 47 LF Item 6: Modified Curb w/ Gutter -142 LF Item 7: 3' Valley Gutter 186 LF Item 8: 4" sidewalk -2725 SF Item 22: Interlocking Pavers 2653 SF Item 23; Concrete Bands 114 Sr Added Item: Mow 5tri p 129 LF $ 3.30/SF $ 3.498.00 $22.00/1•F $ 1.034.00 $25. 00/LF $ -3, 550.00 &e"C� 330.00/LF $ 5.550.00 $ 9.05/SF $-24.661.25 M6U(U *18.00/5f $ 47.754.00 $13.00/sf 1,48L.QO $11.50/lf $ 1.483.50 TOTAL: $ 32.590.25 It 'is mutually agreed that for such change the contract price is increased by $32,590.25 (Thirty -Two Thousand Five Hundred Ninety and 75/100) payable with the payments due under the original construction agreement. Time for completion of the above cited work is hereby extended 0 days beyond any completion date set forth it) the original contract for such work. All other provisions of the original contract and agreement shall remain in full force and effect without change because of the above deviations. JACOBSSON ENGINEERING CONSTRUCTION. INC. Signed: Dated: Title: f � r• Jjf -. .yip'^�� 1 Y�'SJ•.•'.:^ +y )W S fY, =1'' J r� • .� 1ti �i. ' I '�"` : S'' spa •,.:- :}k.:, y_, r:�,•; ':? y � �. ,,,. F ' y� r ' ,/ i t ,;•�';'- ?� "'"'crew>. rJ �• ,,Z 'n rr•...S:Y .-.9,� �."•''t �' ^•s.; s.�.x....t•.:r4i'y ,• iAKy >' � ':•S'i�'•'�' •' 14rp.•`�-" �'x}� � tit ,// ;.f.i y�.y._;, {r�a °'i.�:..1 : •j . � �':! y� ^:aE:.�rt ~'ram' :I � �'w ' ._+.`:=, !'�;�:7r;Sir fr.•r*„'fri�i"-`'° 2; '= 'r r ✓rC* ?�fr,•.s: tiF7 ' - C'. ,,,,.��' \ :L' ^i W�s:.�.ii• :. '�"�y,:'1'' rut.:. r;, �` ox it p � ;ice' , � � `«'��..,r-. .:�; rr^„� .r• �. �� r,, ':i;°" ��$" ,^,, . c.s} t-;.n°.'rt+ fill. �' .�_ '�-.'•4,,�;C ,^'�'4.� >'f� 's�y, ,.. <`^y� i+',I ��fl ice':_ 1 • - �.... .. � vi ��.1::>}0 �'Sy�:� , r,�! +�''i,, :j��i2: Q� �? 't.�:::.G:.<">:, N �`>j G} 'K COPCJ oo- 70 ell � o .z •� w cn cl rat n C� � �� � Q � � � 5•ri z'i � ?D • � '-,;'4`; *�„y � � � � �+' .+t�,7 � � yet C3 r- r% t� G p G r r N Michael Lugo -Thompson From: Cowie, Eric [eric.cowle@stantec.comj Sent: Friday, October 19, 2007 9:17 AM To: Michael Lugo -Thompson Cc: Mark Chappell; mwightman@ci.palm-desert.ca.us; Weiss, Monica Subject: RE: ENTRADA PAVERS Mike, Our take -off was only for the circle drive in front of La Spiga. If you could stop by and review the plans with us, we could probably save some time. Eric Eric V. Cowie Senior Associate Stantec 73733 Fred Waring Drive Suiie 100 Palm Desert CA 92260.2590 Ph: (760) 346-9844 Fx: (760) 346-9368 Eric.Cot.ijle@Stantec.com stantec.c0171 The content of this email is the confidential property of Stantec and should not be copied, modified, retransmitted, or used for any purpose except with Stantec's written authorization. If you are not the intended recipient, please delete all copies and notify us immediately. ',t*jj' Please consider the environment before printing this email. From: Michael Lugo -Thompson [mailto:mlugo@debinc.com] Sent: Thursday, October 18, 2007 4:50 PM To: Cowie, Eric Cc: Mark Chappell; mwightman@ci.paim-desert.ca.us; Weiss, Monica Subject: ENTRADA PAVERS Eric, The precise grading plan shows a quantity of 2225 sf of interlocking pavers. The drawings scale out to be a lot more along with the actual measurement of the area. The contractor estimates 4200 sf to cover the area infront of La Spiga and near the Henderson Building. Unfortunately the Contractor only bid on 2230 sf.( per the bid documents). Please clarify the bust in square footage, if that's the case. Regards, Michael S. Lugo -Thompson Project Manager douglas e. barnhart, Inc. 41-945 Boardwalk, Suite D Palm Desert, CA 92211 760-309-8874 e-fax 858-521-4958 4/2/2008 ITEM ITEM DESCRIPTION NO. 4. Construct PAC over 4" AB pavement 5 Construct modified wedge curb 6- Construct modified wedge curb with gutter 7. Construct 3' valley gutter per City of Palm Desert Standard 1 I2 8. Construct sidewalk and concrete drive. 4" thick sidewalk. 6" thick fire lane. Colored concrete L.M. Scofield C-25 Sombrero Buff 9. Sawcut existing pavement 10. Remove AC pavement and base 11. Paint 4" double white parking stripes 12. Install 18"x 18" Brooks box 13. Install 18" HDPE storm drain pipe 14. Install 18" flared end storm drain pipe ESTIMATED UNIT UNIT TOTAL QUANTITY PRICE 17,091 S.F. $ 3 n $ 5G , ` f 00 ,3 O 465 L.F. $ Z-Z , 00 $ 10, 7-30 -- 621 L.F. $ 2-15' ° C' $ /5, �S -- 495 L.F. $ �b. G o $- 5150 S.F. $ 170 L.F. $ .Z.. 00 $ 3 4-O -- 4,475 S.F. $ O .'7 d $ 31 13 2 , S0 305 L.F. $ $ 76,2 . SO 150 L.F. $ 5S' $ ► 5'© I L.F. $ C-3 \\Scrvcr2\DATA\991-New Email Planwell labs\003-PW AND PRODUCTION I-ANWELDtky orpalm desert-00419900cs\O6-10- 12 Final Encrada 11 bid specs.dm ITEM NO. 15. 16. 17. 18. 19. 20. 21 22. I 23 ITEM DESCRIPTION Constrict ADA curb ramp Remove concrete curb and gutter Remove concrete cross gutter Modify existing concrete catch basin: Protect in place existing inlet and outlet pipes, and catch basin bottom; construct modified manhole #1 per RCFCD Std. Dwg. No. MH251. Relocate existing light fixture, vault, and conduit Install HC parking pavement legend Concrete accent paving colored concrete with exposed aggregate 3/8-l" Parchment Pebble color to be L.M. Scofield C-32 Quarry Red. 6" thick at fire lane. Interlocking Pavers by Acker - Stone or approved equal pattern to Bishops Hat 8x8's Santa Barbara Sandstone with Antique Red inter - squares. 6" thick fire lane. Colored Concrete Bands L.M. Scofield C-35 Santa Barbara Brown. 6" thick fire lane. ESTIMATED UNIT UNIT QUANTITY PRICE TOTAL 5 Ea. $ �?g O - $ 14, 100 — 314 L.F. $ 7. �5 O $ 102 L.F. $ lo. 0O $ 1102,O -- 1 Ea. $ q-, 000 — $ `i t OOQ — 2 Ea. $ LO -oo ~— $ c7,44 oo 4 Ea. $ SO O --- $ ;?- .1 OO O -- -- 315 Sqft $ 1B, 00 $ S (,70 2230 Sqft $ 1 Q' . 00 $ `�) I qo_-.- 400 Sqft $ (5.00 $ S 2'po -� SUB -TOTAL BID PRICE $ q o 3 ,z �6t• v {Precise Grading} ' C-4 N5erver2lDATA1001-New Email Planwell Inbs1003-P W AND PROD LICTIOMPLAMVELLkity of palm dmert-I3041991Dnct10fr-10- 12 Final Entrada 11 bid spccs.dm