HomeMy WebLinkAboutSR - R22600A CO6 - Henderson Cmnty BldgPALM DESERT REDEVELOPMENT AGENCY
STAFF REPORT
REQUEST: APPROVE CONSTRUCTION CHANGE ORDER NO. 6 TO STETON
CONSTRUCTION GROUP (CONTRACT NO. R22600A) IN THE
CUMULATIVE AMOUNT OF ($8,532) FOR THE HENDERSON
COMMUNITY BUILDING
SUBMITTED BY: MARTIN ALVAREZ, REDEVELOPMENT MANAGER
CONTRACTOR: STETON CONSTRUCTION GROUP
145 S. STATE COLLEGE BLVD., SUITE 450
BREA, CA 92821-5818
DATE: SEPTEMBER 25, 2008
CONTENTS: CHANGE ORDER NO. 6 (C.O.R. NOS. 93, 115, 123, 128, 137, 138, 103,
140, 142, 143, 144, 145)
Recommendation:
By Minute Motion, that the Agency Board:
1. Approve Change Order No. 6 to Contract No. R22600A with Steton
Construction Group in the cumulative amount of ($8,532) for items not
included in the original contract; and
2. Authorize the Chairman to execute the said documents.
Executive Summarv:
The Henderson Community Building is complete. Approval of staff's recommendation will
authorize Change Order No. 6 in the cumulative amount of ($8,532) to address minor
unforeseen site and building modifications, including a credit to the contract. Below please find
a summary table with itemized costs:
Unforeseen Site and Building Modifications:
COR#93: Additional AV scope per ACD #35R2
COR#115: Rerouting conduit for the installation of door portals per
RFI# 149
COR#123: Relocate light fixture in restrooms
COR#128: Electrical Ballasts for the Tumtobel light fixture
COR#137: Onyx supports for entry counter
COR#138: Soffit modifications per AFR 20
COR#103: Concrete add under sliding door
COR#140: Modifications to restroom tops
COR#142: Relocate strobe for Fire Alarm per Fire Marshall
COR#143: Onyx Lighting revisions
Cost
$ 1, 446
$ 2,622
$ 339
$12,341
$ 7,4171
$ 1,500
$ 2,100
$ 921
$ 5741
$ 1,853 1
Staff Report
Approve Change Order No. 6 to Contract No. R22600A — Henderson Community Building
Page 2 of 2
September 25, 2008
COR#144: Added drywall @ soffit to hide sprinkler pipe 1 $ 3,091
COR#145: Insulating exterior HVAC duct work j $ 1,264
Credit: Deductive amount for $44,000 for deletion of insulating ($44,000)
concrete per ACD #47
Cumulative Total: L ($ 8,532)
Discussion:
The Henderson Community Building is complete and the grand opening is scheduled for
October 11, 2008. Change Order No. 6 is a closeout change order, which brings the project
and contract to a close. The change order addresses the unforeseen site and building
modifications required to complete the building and a credit due to the Agency.
Unforeseen Site and Building Modifications:
The above unforeseen site and building modifications are required to address minor
modifications that were not addressed in the construction plans. The additions will address
building code requirements and modifications necessary to complete the project. The total cost
to address these unforeseen site and building modifications is ($8,532).
Based on review by the Construction Manager, Architect and staff, Change Order No. 6 and a
zero day calendar extension is recommended for approval to allow the construction of the
Henderson Community Building to move forward towards completion. If Change Order No. 6 is
approved, the project will have $251,438.61 remaining as contingency.
Submitted by:
Martin Alvar z
Redevelop ent Manager
Department Head:
Dave Yrigoyen
Director of Re elopment/Housing
Carlos L. Ortega xecutive Director
Approval:
Paul S. Gibson, Director of Finance
BY RDA
ON
VERIFIED BY___L_ �
Original on file with City Clerk's Office
GArda\Heather Beck\Henderson\HendC06.doc
Vl O M L0) l(0 000
j U 0 LO 0)Ln ODc0
C� U O O LO Lo � M
j C N N r- a) co LO U')
j f C 0 v c) N N N
j O (0 U
z / U m
z 0i
D U % Ocl U)
LL p= c <j joO c2H
@ . F- o F-
C ,N 0 F- 'p / OO OO C ,0
Q 5)O NQ 1U0) QF-
o 0CL8 �� aa"o
N a<0 Q<=
w U j 6q E»
t
Z O j cu O L0 OM M
O
~ O%C 0) O- c cM cV ((0 L O
cn U U O/ 0 0"T � LO L() N qlr
(1) F- LO LO c0 c0 ti ti
(' � a Z 0 % T tt ct �
00 V U% D
0 Ed
m Z? M O O I� O.Cc = 0 0 O O O
4-
o
U Z
Lr q 0 o
F_ j
V z V j o (0 Lo 00 C) rn 0
z
OV O 0) co= / 0 Ln 4 O N
O / 0 O 't v) � M
N L!. F- / E O N � rn cO h rn Ln
Z / Q LO f- (0 c0
WO O / 0 v v It ao It
0 } U
z� U
Qz
_ O Q
LLIH
cl)� 0 o 'Sou
C
V X (6 n
O U7 v- U Y C -O
O Q .0 C f6 0)7 ( O�pp
L U> w T m vE w E
m c Q -_ 16 o o a
H c m m E
U c
Z M a) a) -0 On
0 F- W Op ui a o 'o a io E a a� io c
U C7 0 vo v C 0 o t o S v
O o M m C' a) o c o rn
a� w Z N c v>_ m c 'o m
F- F- CT -O O cOp" p Vl U to �c �_ O c
z z C f� y > O N N rn N V 7
L O C O .y N 3 N
J J U c O@ c N �O N N O U O
Q Q a� L a o E c c
z z J t5 50 �u� o m m v c N .O O
O O c N
• CO o UNOC a E "O
�c0 0 F- U ° cd oO_ _2 0
lt
0 N M It LO c0 I�
0
O
c'M
6
N
O
r-
0)
M
6
N
O
v
rn
J
F-
0
F-
0)
0
0
U
0
0
0
a
d
m
N
C
l0
E
0)
0
t
a
MW
PALM DESERT REDEVELOPMENT AGENCY
CONSTRUCTION CHANGE ORDER
Contract Purpose Construction of Henderson Community Building
Consultant's Name Steton Construction Group
Address: 145 South State College, Suite 450
Brea, CA 92821
Contract # / P.O. # R22600A
Change Order No. 6
Contingency: YES I NO
Account No. 850-4358-433-4001
Project No.
Vendor No. 1 9494
You are hereby requested to comply with the following changes from the contract plans and specifications:
13386
x
DESCRIPTION OF CHANGES
DECREASE INCREASE
(Supplemental Plans, Specifications, and Directives dated Attached)
In Contract Price In Contract Price
COR # 93: Additional AV scope per ACD #35R2
1,446.00
COR #115: Rerouting conduit for installation of door portals per RFI #149
2,622.00
COR #123: Relocate light fixture in restrooms
339.00
COR #128: Electrical ballasts for Tumtobel light fixture
12,341.00
COR #137: Onyx supports for entry counter
7,417.00
COR #138: Soffit modifications per AFR 20
1,500.00
COR #103: Concrete add under sliding door
2,100.00
COR #140: Modifications to restroom tops
921.00
COR #142: Relocate strobe for fire alarm per Fire Marshall
574.00
COR #143: Onyx lighting revisions
1,853.00
COR #144 Added drywall @soffit to hide sprinkler pipe
3,091.00
COR #145: Insulating exterior HVAC duct work
1,264.00
Deductive amount fordeletion of insulating concrete perACD #47
44,000.00
TOTALS: 44.000.00
NET CHANGE IN CONTRACT PRICE:
JUSTIFICATION:
TOTAL BUDGET FOR PROJECT: + 4,742,561.39
Less: Expend. & Encumb. To Date: - 4,742,561.39
Less: This Change Order Amount - (8,532.00)
BALANCE OF BUDGET
REMAINING FOR PROJECT: 8,532.00
CONTINGENCY:
Amount Approved by Board:
Less: Prior Change Order(s):
Less: This Change Order:
Balance Remaining of Contingency.
35.468.00
(8.532.00)
+ 454, 0 00.00
155, 6 44.46
- 46,916.00
251,439.54
The amount of the Contract will be (Decreased)'nGr-eased by the Sum of: Eiqht Thousand Five Hundred
Thirtv-two and 00/100 Dollars ($8,532.00).
G:\rda\Beth Longman\Staff Reports\Grisa\Steton CO 6 Form.doc See reverse
Contract R22600A Change Order No. 6 Continued from front
This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish
equipment and materials, and perform all work as necessary or required to complete the Change Order items for a
lump sum price agreed upon between the Contractor and the Palm Desert Redevelopment Agency, otherwise referred
to as Owner.
Contract Time Extension -0- Days.
Revised Contract Total $4,734,029.39
The undersigned Contractor approves the foregoing Change Order # 6 as to the changes, if any, in the contract
price specified for each item including any and all supervision costs and other miscellaneous costs relating to the
change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said
Change Order # 6 . The Contractor agrees to furnish all labor and materials and perform all other necessary work,
inclusive of that directly or indirectly related to the approved time extension, required to complete the Change Order
items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood
that the Change Order shall be effective when approved by the Owner.
Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies,
waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of
or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and
indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as
any and all consequential damages.
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above
must have required signatures as per the purchase resolution.
REQUESTED BY:
3. CERTIFIED
FUNDS AVAILABLE:
EXECUTIVE DIRECTOR
FINANCE DIRECTOR
NOTE: No payments will be made
prior to Executive Director and
Agency Board approval
2. ACCEPTED BY:
CONTRACTOR Date Accepted
4. APPROVED BY:
JEAN M. BENSON, CHAIRMAN
SECRETARY
9/25/08
9/25/08
G:\rda\Beth Longman\Staff Reports\Gfta\Steton CO 6 Form.doc
See reverse
ar rt, 'inc
September 16, 2008
Martin Alvarez
RDA Manager
City of Palm Desert, Redevelopment Agency
73-510 Fred Waring Drive
Palm Desert, CA 92260-2578
Subject: deb Project #6016
Henderson Community Building
Entrada del Paseo
72-559 Highway l 11, Palm Desert
Re: Change Order Six and Recommendation for awards of
Change Order Request # 93,103, 115,123,128,137,138,140,142,143,144,145 and
Deductive Amount for $44,000.
Mr Alvarez,
We have reviewed the attached documentation received from Steton Construction Group. For
Change Order Request # 93,1 15,123,128,137,138,140,142,143,144,145 and
Deductive Amount for $44,000. we recommend approval as follows:
1. COR#93: Additional AV scope per ACD #35R2. Cost
2. COR#I 15: Rerouting conduit for the installation of door portals per RFI# 149 Cost
3. COR#123: Relocate light fixture in restrooms. Cost
4. COR#128: Electrical Ballasts for the Tumtobel light fixture. Cost
5. COR#137: Onyx supports for entry counter. Cost
6. COR#138: Soffit modifications per AFR 20. Cost
Post Office Box 270399, San Diego, California 92198-2399, (858) 385-8200, FAX (858) 385-8201
www.debinc.com
$1,446
$2,622
$339
$12,341
$7,417
$1,500
7. COR# l 03: Concrete add under sliding door, Cost $2,100
8. COR#140: Modifications to restroom tops. Cost $921
9. COR#142: Relocate strobe for Fire Alarm per Fire Marshall. Cost $574
10. COR#143: Onyx Lighting revisions. Cost $1,853
11. COR#144: Added drywall @soffit to hide sprinkler pipe. Cost $3,091
12. COR#145: Insulating exterior HVAC duct work. Cost $1,264
13. Deductive amount for $44,000 for deletion of insulating concrete per ACD # 47 $44,000
Total amount of this Change Order is $-8,532 with no calendar days.
Change Order Requests that are denied: COR#19rl,52,56,69,99,,105,109,116,130,133,141.
All COR that have not been previously identified in Change Order# 1-5 as approved or identified
in Special Services Account have been and are denied. No COR are pending other than the above
lists.
Sincerely,
Michael Lugo -Thompson
Project Manager
Barnhart, Inc. A Herry International Co.
Attachment: CO 46 LOG
Post Office Box 270399, San Diego, California 92198-2399, (858) 385-8200, FAX (858) 385-8201
www.debinc.com