HomeMy WebLinkAboutRTFY - DW Ktchn & Bldg Xpnsn Contractor Pre-qulfctn List-E E
PALM DESERT REDEVELOPMENT AGENCY
STAFF REPORT
REQUEST: RATIFY THE CONTRACTOR PRE -QUALIFICATION LIST FOR THE
DESERT WILLOW KITCHEN AND BUILDING EXPANSION
PROJECT
SUBMITTED BY: Martin Alvarez, Redevelopment Manager
DATE: June 24, 2010
CONTENTS: General Contractor Prequalification Application
Recommendation
By Minute Motion: Ratify the Executive Director's approval of the contractor
pre -qualification list for the Desert Willow Kitchen and Building expansion.
The list of contractors deemed qualified will be provided to the Agency Board
on June 24, 2010.
Background
The Desert Willow Kitchen and Building expansion project is in plan check, and bidding is
anticipated to commence at the end of June. As a high profile project with an aggressive
construction timeline, it is critical that the Agency secure bidders who can demonstrate the
proper experience, qualifications, and ability to complete a project with similar scope and
schedule. In order to achieve this goal, a contractor pre -qualification process is required.
On June 3, 2010, staff published a notice seeking qualifications from general contractors
interested in bidding the Desert Willow Kitchen and Building expansion project. The pre -
qualification application requested specific information from contractors possessing a valid
and current California contractor's license (Class B-General Contracting) and in good
standing.
The information requested included, but was not limited to, the contractors' ability to
demonstrate that they are regularly engaged in the business of constructing renovation
and hospitality projects with new or renovated commercial kitchens. In addition, the
contractor was requested to demonstrate that they have successfully completed a
minimum of four similar projects in the last five years with the ability to provide proper
insurance and bonding capacity to meet the Agency's standards (see attached pre -
qualification application).
On June 14, 2010, staff received seven contractor's qualification applications. Below is a
summary table of the applications:
Staff Report
Ratification of Pre -qualified Contractors List for Desert Willow Kitchen/Building Expansion
June 24, 2010
Page 2 of 2
Pre -Qualified Contractor Applications Submitted
Davis Reed, San Diego, CA
Doug Wall Construction, Inc., Bermuda Dunes, CA
Inland Building Construction, San Bernardino, CA
Orr Builders, Palm Desert, CA
Penta Building Group, Palm Desert, CA Desert, CA
Roel Construction, Palm Desert, CA
W.D. Gott Construction, Upland, CA
Agency staff, our construction manager, and legal counsel are currently reviewing the
qualifications. After review of the applications, staff will provide a pre -qualified contractors
list to the Executive Director for approval on June 18, 2010.
Our legal counsel has recommended that the Agency Board formally ratify the pre -qualified
contractors list, and set up an appeals panel consisting of City staff to hear any appeals
filed to the pre -qualified contractors list.
If the pre -qualified contractors list is ratified and the appeals period ends (June 23, 2010)
without a challenge, staff will solicit sealed bids from the pre -qualified contractors list for the
construction of the Desert Willow Kitchen and Building expansion project. The estimated
construction period is August to December 2010. Staff recommends that the Agency Board
ratify the attached pre -qualified contractor list.
Fiscal Analvsis
The estimated construction cost for the project is $3.95 million, including the lobby remodel.
The preliminary construction cost has been considered. Additional revenues produced as a
result of the expansion may augment future General Fund revenues. Design and project
costs can be funded by the Redevelopment Agency; therefore, there is no immediate fiscal
impact to the General Fund.
Submitted By:
MaIvarez, Redevel pment Manager
Paul S. Gibson, Director of Finance
Approval:
M. Wohlmuth, Executive Director
Department Head:
a
ust n MMcCarthy, CM or Redevelopment
^ed' R -
j� 11)C1 C'
VERIFIED BY POK- 14,Y)7
Original on file with City Clerk's Office
* By Minute Motion: 1) Ratify the Excutive Director's
approval of the contractor pre -qualification
list for the Desert Willow Kitchen and Building
Expansion project; 2) authorize staff to set
up an appeals panel consisting of City staff
to hear any appeals. 5-0
Alvarez\2010\SR\6-24-10 DW Pre-Qualificahon2 dou
e x t pa a S .a . 0 'b s i. }< 9. 3 .`y %
PALM DESERT REDEVELOPMENT AGENCY
DESERT WILLOW GOLF RESORT — KITCHEN/BUILDING EXPANSION
General Contractor Prequalification Process
Palm Desert Redevelopment Agency ("Agency") has determined that contractors bidding on the
Desert Willow Golf Resort — Kitchen/Building Expansion project ("Project") must be
prequalified prior to submitting a bid on the Project. Contractors who intend to submit a bid
must be prequalified.
The purpose of this prequalification process is to develop a list of qualified general contractors
who can demonstrate the ability to complete the project on an aggressive schedule with a high
degree of workmanship and with quality service. The general scope of work for the Project
includes but is not limited to:
o Demolition and remodel of the existing lobby/bar area to accommodate an expanded bar
area with the relocation of two offices;
o Expansion of the lobby/ballroom hallway to eliminate the pinch point adjacent to the
ballroom;
o Enclosure of the existing ballroom to reduce noise; and
o Modification to the ballroom audio visual, window shading, and lighting; and
o A 5,200 square foot remodel and expansion to the kitchen/building at east end of
clubhouse including, but not limited to restroom expansion, installation of kitchen
equipment, refrigeration, storage, and offices.
The contractor will be required to supply all materials and expertise to complete the renovation
per the Project plans and specifications. The existing facility will remain operational during the
construction and contractor will be required to develop and maintain a schedule to complete the
Project in 140 calendar days.
The Project is subject to all laws pertaining to public works, including but not limited to
prevailing wages. Contractors seeking prequalification must have successfully completed
similar projects, as defined herein, for public agency owners.
To be deemed prequalified, the Contractor must be regularly engaged in the business of
construction and renovation of hospitality projects which include a commercial kitchen and shall
have successfully completed a minimum of four (4) similar projects in the last five (5) years.
1 of 15
d3 1'1 i 1`ii'.0 AI ad,ii .s'dit \
For purposes of this prequalification package, a "similar project" is defined as follows:
1. Construction cost at the bid date was a minimum of 3M;
2. Scope of work included expansion of building footprint, renovation of existing facilities,
demolition, and a commercial kitchen (of particular interest are projects where the facility
remained operational during construction);
3. Contractor seeking prequalification must have been the general contractor on the project,
using the same license number as that seeking prequalification. (Note: Projects
completed by present employees of the Contractor for former employers are not
acceptable); and
4. At least two (2) of the four (4) projects must have been a public work, owned and
administered by a public agency.
Contractor must possess a valid and current California Contractor's license (Class B — General
Contracting) and the license must be in good standing at the time of submittal of the
prequalification package.
As provided in Public Contract Code Section 20101, completed prequalification packages and
financial information are not public records and will not be open to public inspection. All
information provided will be kept confidential to the extent permitted by law.
Each prequalification package must be completed with all information requested and be signed
under penalty of perjury by an individual who has the legal authority to bind the Contractor on
whose behalf that person is signing.
Pre -qualification packages must be received by Heather Buck, in the offices of the
Redevelopment Agency located at 73-510 Fred Waring Drive, Palm Desert, CA 92260 before
4:00 p.m. on Monday, the 141" day of June 2010.
Prequalification packages received after that time will be returned unopened, and the Contractor
will not be eligible to participate in bidding for the contract to construct the Project. Incomplete
or unsigned prequalification packages will be returned without review and the Contractor will
not be eligible to participate in bidding for the contract to construct the Project.
Where a timely and completed prequalification package results in a determination of non-
prequalification, an appeal can be made. An appeal is begun by the Contractor delivering written
notice to the Agency's Project Coordinator, Heather Buck, of its appeal of the decision with
respect to its prequalification rating, no later than five (5) calendar days after adoption by the
Agency of the qualified bidders list for the Project. Without a timely appeal, the Contractor
waives any and all rights to challenge the decision of the Agency, whether by administrative
process, judicial process or any other legal process or proceeding.
If the Contractor gives the required notice of appeal and requests a hearing, the hearing shall be
2of15
„''I P Y 4 I”. s . • k0, iti ,-,-, pi Al !F"' ., f l �N
conducted so that it is concluded no later than five (5) calendar days after the Agency's receipt of
the notice of appeal. The hearing shall be an informal process conducted by a panel (the
"Appeals Panel"). At or prior to the hearing, the Contractor will be advised of the basis for the
Agency's prequalification determination. The Contractor will be given the opportunity to
present information and present reasons in opposition to the determination. Within two (2)
business days after the conclusion of the hearing, the Agency shall give the Contractor written
notice of the outcome of the Appeals Panel decision which will be final and binding.
The prequalification package, its completion and submission by the Contractor, and its use by the
Agency, shall not give rise to any liability on the part of the Agency to the Contractor or any
third party or person. This is not a solicitation for bid. No guarantees are made or implied that
the Project will be constructed, either in part or whole. The Agency does not guarantee that the
preliminary scope of work identified in the prequalification package will be the same or similar
to that scope of work in the actual bid package. The Contractor accepts all risk and cost
associated with the completion of the prequalification package without financial guarantee.
All pre -qualified contractors will have the option to receive plans and specifications on the
proposed project and submit a sealed bid at a future date. Pre -qualified contractors who seek to
participate in the bidding process will be required to participate in a mandatory pre -bid meeting
and site inspection.
The prequalification of prospective bidders will be determined by evaluation of the information
submitted by prospective bidders. The Agency may verify any or all information provided in
completed prequalification package, consider information provided by sources other than the
prospective bidder, and conduct such investigations as the Agency deems appropriate to assist in
the evaluation of contractor's responsibility, qualifications and financial capacity.
The contract for construction of the Project may be awarded, if at all, to the responsible, pre -
qualified Contractor submitting the lowest responsive bid. Neither issuing the Notice nor any
other activity related to the pre -qualification process, obligates the Agency to award a contract
for construction of the Project to a particular Contractor, or at all.
The Agency reserves the right to reject any or all prequalification packages and to waive any
irregularities in any prequalification package submittal. The Agency reserves the right to
determine that any Contractor is not qualified at any time before or after the prequalification
packages are received and evaluated if it finds that any information it provided is inaccurate or
false, or upon evidence of collusion or other illegal practices on the part of a contractor. The
Agency, in its sole discretion, expressly reserves the right to cancel the prequalification process
at any time, including but not limited to, after the deadline for the receipt of prequalification
packages, reject any prequalification packages received by the Agency and competitively bid the
Contract without first prequalifying the bidders.
Any objection to the prequalification materials, or explanation desired by a prospective
Contractor regarding the meaning or interpretation of the prequalification package and related
materials, must be requested in writing by e-mail or facsimile and received before 5:00 p.m.,
June 8, 2010. Oral explanations or instructions will not be binding unless issued as a formal
addendum to the prequalification package. Any information provided to any prospective
3of15
Contractor concerning a solicitation will be furnished to all prospective contractors who
requested a prequalification package. By submitting a completed Pre -qualification Package, the
prospective Contractor waives any and all objections to the form and content of the Pre -
qualification Package.
To be considered for prequalification the following form must be filled out entirely and all
information requested in the form must be attached to the Contractor's submittal. A
determination of qualification shall be made on a "Pass/No Pass" basis.
By my signature below, I acknowledge receipt of this document and agree to be bound by its
terms and agree to submit it as part of the Pre -qualification Package.
Date
Signature
Name of contractor on whose behalf this document is signed:
4of15
GENERAL CONTRACTOR PRE -QUALIFICATION APPLICATION
PALM DESERT REDEVELOPMENT AGENCY
DESERT WILLOW GOLF RESORT — KITCHEN/BUILDING EXPANSION
Please type or print in black ink. All information must be complete and three copies must be
submitted.
COMPANY INFORMATION
Company Name:
Mailing Address:
City/State/ZIP:
Contractor's License Number:
Contact Name: Title:
Phone: Fax:
Cell: Email:
Federal Tax ID or SS No:
Type of Business (Sole Proprietor, Corp., Joint Venture, etc.):
Years of Operation Under this License Number:
PRE -QUALIFICATION REQUIREMENTS:
(Checking the box affirms that your company can meet or exceed the pre -qualification
statement.)
❑ 1. The company is regularly engaged in the business of the construction/renovation of
commercial kitchen and building structures, including the construction of public
facilities.
❑ 2. The company has successfully performed similar work type work in the hospitality
industry within a similar schedule.
5of15
❑ 3. Contractor shall have successfully completed a minimum of four (4) similar
construction/renovation projects in the last five (5) years.
For purposes of this prequalification package, a "similar project" is defined as follows:
A. Construction cost at the bid date was a minimum of 3M;
B. Scope of work included expansion of building footprint, renovation of existing
facilities, demolition, and a commercial kitchen (of particular interest are projects
where the facility remained operational during construction);
C. Contractor seeking prequalification must have been the general contractor on the
project, using the same license number as that seeking prequalification. (Note:
Projects completed by present employees of the Contractor for former employers
are not acceptable); and
D. At least two (2) of the four (4) projects must have been a public work, owned and
administered by a public agency.
❑ 4. The company has the following General Contracting — Class B license in the State of
California which are currently active and in good standing with the California
Contractor's State License Board (CSLB).
License Classification:
Name of License Holder:
License Number:
Date Issued: Expiration Date:
A. Has this license been suspended or revoked by the California Contractor's State
License Board within the last 5 years?
B. Please list all additional licenses that any personnel who will be assigned to the
Project maintain. Licenses outside of California should also be listed.
6of15
❑ 5. The company has completed the following four similar projects as defined in this
prequalification package. the following references that directly pertain to this scope of
work:
Reference No. 1
Project Name:
Is This Project a Public Work?
Yes No
Contact Name:
Telephone:
Company:
Title:
Fax:
Email Address:
Owner Name:
Telephone:
Fax:
Email Address:
Architect/Engineer of Record:
Contact Name: Telephone:
Fax: Email Address:
Location:
Size of Project (Interior s.f.): (Exterior s.£):
Construction Start Date: Date of Completion:
Did your firm act as the General Contractor during the entire project?
Amount of Contract (Cost at bid):
No. of Change Orders:
Total Amount of Change Orders: $
Name of Project Manager:
Name of Project Superintendent:
Brief Description of Work:
7of15
PALM DESERT REDEVELOPMENT AGENCY
INTEROFFICE MEMORANDUM
To: Agency Board
From: Martin Alvarez, Redevelopment Manager
Heather Buck, Project Coordinator,
Date: June 24, 2010
Subject: Desert Willow Kitchen/Building Expansion: Pre -qualified Contractors List —
Recommendation for January 28, 2010, Agency Board Meeting
Staff recommends the following action:
By Minute Motion:
1. Ratify the Executive Director's approval of the contractor pre -qualification
list for the Desert Willow Kitchen and Building expansion; and
2. Authorize staff to set up an appeals panel consisting of City staff to hear
any appeals.
Staff has conducted a pre -qualification process for the Desert Willow Kitchen project to
qualify general contractors to bid on the above -mentioned project. The pre -qualification
application required that general contractors provide four similar scope projects in excess of
$3 million that have been completed in the last five years. Two of these projects must be
public works projects.
We have reviewed the pre -qualification process and selection with our legal counsel and
construction manager and recommend that the following contractors be deemed pre -
qualified to bid on the Desert Willow Kitchen/Building project:
Firm
Davis Reed
Doug Wall Construction
Inland Building Construction Companies
Orr Builders
The Penta Group
Roel Construction
W.D. Gott
Location
Pre -qualified
(Yes/No)
La Quinta, CA
Y
Bermuda Dunes, CA
Y
San Bernardino, CA
N
Palm Desert, CA
N
Palm Desert, CA
Y
Palm Desert, CA
N
Upland, CA
Y
G:Uda\Heather BucklDesertWillow\Prequalification\Staff Report\Memo-Desert Willow Prequal Update 062410.doc
Pre -qualified Contractors List for the Desert Willow Kitchen and Building Expansion
June 24, 2010
Page 2 of 2
The Executive Director approved the above list on June 24, 2010. Staff requests that the
Agency Board ratify the pre -qualified contractors list as recommended by our legal counsel
and authorize staff to set up an appeals board to hear any appeals that may be received. A
final staff report will be brought before the Agency Board on July 8, 2010, with the results of
the hearing(s), if applicable.
cc: Rachelle D. Klassen, Secretary
John M. Wohlmuth, Executive Director
Justin McCarthy, ACM for Redevelopment