Expedited Permitting Process for Electric Vehicle Charging Stations
Commercial Facilities and Public Accommodations
Purpose and application steps
Purpose: This document provides all of the needed links to forms and checklists necessary to utilize the City of Palm Desert expedited permitting process for Electric Vehicle Charging
Stations (EVCS). This process provides an expedited and streamlined permitting process for qualifying EVCS systems. Once all of the documentation is correctly and fully completed and
submitted, a permit will be processed and approved for issuance in a timely manner, usually 1 to 3 business days for residential permits and 5 to 10 business days for commercial permits.
Download, review, and complete the Electric Vehicle Charging Stations (EVCS) checklist below. Submit all information requested on the checklist.
Fully complete and sign a Building Permit Application form.
Submit all required documentation through the
https://palmdesert.my.site.com/s/City of Palm Desert's Online Permit Portal, Clariti. The Permit Center will notify you when the documents have been uploaded, which fees are required,
and when the permit has been approved and is ready to be issued.
Submittal Requirements Checklist for Permitting of Electric Vehicle Charging Stations (EVCS)
This checklist is provided to guide applicants through a streamlined permitting process for Electric Vehicle Charging Stations (EVCS).
1. Approval requirements
Building and Safety Division is responsible for plan review and inspections for all EVCS installations.
Planning Department plan review approval is not required for EVCS installations unless the Building Official determines that the proposed EVCS will have a specific, adverse impact upon
the public health or safety.
Fire Marshal's Office plan review and inspection approval is not required for EVCS installations unless the system includes an energy storage system as defined in the California Fire
Code.
2. Submittal information
All forms and checklists described in this handout are available on the Palm Desert Permit Center website under documents on EV chargers, available through the
https://www.palmdesert.gov/build-develop/formsCity of Palm Desert - Permit Forms & Handouts.
A Building Permit Application is required for all EVCS installations.
This checklist must be completed and submitted to the Palm Desert Permit Center along with the Building Permit Application. Please provide an explanation for any checklist items not
completed or not met.
Provide a digital set of plans for the proposed EVCS project. Document properties shall be no less than 11 inches by 17 inches and in landscape orientation, with 10-point minimum font.
Plan submittals shall include, but not be limited to:
A title page.
A site plan.
An electrical floor plan. (Not required for exterior EVCS equipment installations.)
A single-line electrical diagram. (Not required for Level 1 charging station installations.)
EVCS manufacturer installation details and specifications.
Electrical service load calculations.
3. General requirements for EVCS to be shown and noted on plans
Use the following checklist items for preparation and submittal of your plans. The level of detail and the specific plan requirements will depend upon the extent, nature, and complexity
of the work to be done. All applicable checklist items must be noted or specified on the plans. Indicate the plan sheet number where the applicable requirement is shown or specified.
4. Type of EVCS Type of EVCS proposed (please check one) Check one Type of charging station(s) proposed Power levels (proposed circuit rating) Level 1 110/120 volt alternating
current (VAC) at 15 or 20 amps Level 2 - 3.3 kilowatt (kW) (low) 208/240 VAC at 20 or 30 amps Level 2 - 6.6 kW (medium) 208/240 VAC at 40 amps Level 2 - 9.6 kW (high) 208/240
VAC at 50 amps Level 2 - 19.2 kW (highest) 208/240 VAC at 100 amps DC Fast Charging 440 or 480 VAC Other (specify and provide details) 5. Submittal requirements checklist
for EVCS Permit application requirements and technical checklist Permit application requirements Yes No 1. The permit application is complete with the following information:
Project address and parcel number,
Owner name, address and phone number;
Contractor name, address, and phone number and contractor's license number; and
Electrical load calculation worksheet Yes No 2. An electrical load calculation is included with the permit application. Code reference: CEC 220. Yes No 3. Based on the required
load calculation, an electrical service panel upgrade is required. If yes, plans show and specify the electrical service panel upgrade. Yes No 4. EVCS branch circuit conductor is appropriately
sized for a continuous load of 125 percent of the EVCS equipment plus any other non-continuous loads. Code reference: CEC 210.19. Plans - General Yes No 5. The Digital drawings are
Drawings are to scale or fully dimensioned
Document properties are no less than 17 inches wide by 11 inches high (36 inches by 24 inches preferred)
Landscape orientation
No hand-drawn plans
Yes No 6. The plans include a Title Page with property information including, but not limited to:
Address of property
Name, address, and phone number of the property owner
Name, address, phone number, and license number of the person responsible for the EVCS system design, signed and stamped if a licensed design professional is used
2022 California model codes applicable to the project
Occupancy and use of the facilities
Narrative description and scope of the proposed work
Yes No N/A 7. A Site Plan is included with the permit application and includes the following information:
Location and name of structure(s) on the site
Property lines, streets, lot dimensions, north arrow, and distances from property lines to structures and proposed EVCS equipment
Dimensioned parking improvements, driveways, and similar site features
EVCS equipment, main electric service panel, disconnects, and overcurrent protection locations
Underground conduit locations and routing
Location of additional meter, if applicable
All site-related accessibility requirements prescribed by CBC Sections 11B-228 and 11B-812 are shown and fully specified
Detailed and specific site plan of all related proposed work
Yes No N/A 8. An Electrical Floor Plan is included with the permit application and includes the following information (Not required for exterior installations):
Plan view of the location of the proposed EVCS equipment including the use of the space or area where the EVCS will be installed
All applicable electrical plan requirements of CEC Article 625 are shown or specified on the plan
All electrical plan accessibility requirements prescribed by CBC Sections 11B-228 and 11B-812 are shown and fully specified
Detailed and specific plan of all related proposed work
Yes No N/A 9. A Single-Line Electrical Diagram is included with the permit application and includes the following information (Not required for Level 1 charging installations):
All EVCS supply equipment listed and labeled
Conductor and conduit size, type, and location
Size of the overcurrent device (circuit breaker) supplying the EVCS
Size and location of the main electric panel, distribution panels (subpanels), overcurrent protection, disconnects, additional meters, and EVCS equipment
Type (level), voltage, and ampacity for each charging station
All equipment labeling requirements per CEC 625.15
Yes No 10. A digital set of the EVCS Manufacturer Installation Details and Specifications are included with the permit application Yes No N/A 11. A digital set of Electrical Service
Load Calculations are provided for sizing the electrical service panel pursuant to CA Electrical Code (CEC) Article 220. (Note: include 125 percent of the EV charging station load in
the calculation.) Yes No N/A 12. If the EVCS equipment is listed for charging electric vehicles that require ventilation for indoor charging, a mechanical plan showing and specifying
all ventilation requirements prescribed by CEC 625.52 is included with the permit application. Yes No 13. The Project site is located outside of a 100-year flood hazard zone. Note:
if the charging equipment is located within a 100-year flood hazard zone, the EVCS equipment shall be elevated above the base flood elevation. The base flood elevation must be determined
and an elevation certificate submitted by a registered land surveyor. Plans - 2022 California Electrical Code minimum plan requirements Yes No Sheet#_____14. The Plans indicate that
the installation will meet all requirements of 2022 California Electrical Code - Article 625 for Electric Vehicle Charging Systems. Yes No Sheet#_____15. The Plans identify the amperage
and location of the existing (or new) electrical service panel, and the service panel is sized in accordance with electrical service load calculations? (CEC 220) Yes No Sheet#_____16.
The plans indicate the size of the service entrance conductors? Yes No Sheet#_____17. The plans indicate that charging equipment shall have a Nationally Recognized Testing Laboratory
(NRTL) approved listing mark? (UL 2202/UL2200) Yes No Sheet#_____18. The single-line electrical diagram shows and specifies the required overcurrent protection for the proposed EVCS?
Yes No Sheet#_____19. Conduit and conductor size and type are specified and the routes and requirements for their installation (i.e. within framing, mounted to structures, underground,
etc.) are shown? Yes No Sheet#_____20. The plans specify that the electric vehicle charging system shall be installed in accordance with manufacturer's installation instructions and
shall be suitable for environment (indoor or outdoor) in which it will be installed? Yes No Sheet#_____21. The plans specify where the labeling of the EVCS equipment (i.e. "For Use
With Electric Vehicles,” “Ventilation Not Required,” and “Ventilation Required.”, etc.) is required? (CEC 625.15) Yes No N/A 22. An approval letter from SCE is provided to the building
department if a dedicated electrical meter is to be installed for the electric vehicle charging system? Yes No N/A Sheet#_____23. If the EV charging equipment is rated more than 60
amps or more than 150 volts to ground, the plans specify that the disconnecting means shall be lockable open and shall be provided in a readily accessible location? (CEC 625.42) Yes
No Sheet#_____24. The plans specify that the EVCS equipment disconnecting means shall be identified with a durable label stating “Emergency Power Off - Electric Vehicle Charging Station.”?
(CEC 110.21.) Yes No Sheet#_____25. The plans specify that main service conductors and equipment for protection of electrical service, (i.e. disconnecting means, overcurrent protection,
etc.) will be installed in accordance with CEC Article 230? Yes No N/A Sheet#_____26. If trenching is required, a trenching detail is provided on the plans showing compliance with
minimum cover requirements pursuant to CEC 300.5?(Note: trenching for electrical feeders from structure to structure must comply with CEC 225.) Yes No N/A Sheet#_____27. Physical
protection such as a bollard is shown and detailed on the plans when vehicle impact protection for EVCS equipment is required? (CEC 110.27(B).(Note: typically not required for Level
1 EVCS. The source document notes that physical protection from damage is often a 4-inch diameter steel pipe filled with concrete, a minimum of 40 inches above finished floor or grade,
installed in a footing measuring 12 inches in diameter and 3 feet deep.) Yes No Sheet#_____28. The plans show and specify the mounting height for the charging coupling (the connector
nozzle) and the operable controls?(Note: If installed indoors, the electric vehicle charging coupling shall be located between 18 inches and 48 inches above the finished floor. If installed
outdoors, the coupling shall be located between 24 inches and 48 inches above the finished grade. (CEC 625.50 and CBC 11B-309)) Yes No N/A Sheet#_____29. If the EVCS is installed
within a building containing an R residential occupancy, plans show and specify the location for all required smoke and carbon monoxide alarms within the dwelling unit or units. (CBC
907.2.11, CBC 915, CRC R314, and CRC R315).(Note: In lieu of showing and specifying these locations, a Smoke and Carbon Monoxide Alarm Self Verification Form, available on the City
of Palm Desert website, may be completed, signed, and submitted with the application.) Plans - 2022 CalGreen requirements Yes No N/A 30. Does the number of proposed electric vehicle
charging spaces conform to Tier 1 requirements of California Green Building Code (CGBC)? (CGBC A4.106.8.2 and A5.106.5.3)(Only applies to newly constructed multi-family residential
and newly constructed non-residential projects) 2022 California Building Code accessibility requirements Accessibility requirements are required for public and common use areas, public
accommodations, commercial facilities, and public housing as defined in the California Building Code. Accessibility items to be shown and specified on the plans Plans Accessibility
requirement Yes No N/A Plans show and specify all applicable CBC Chapter 11B requirements, including but not limited to the sections listed below Yes No N/A Sheet # _____ 11B-202.4
- Path of Travel Requirements in Alterations, Additions and Structural Repairs Sheet # ______ 11B-228.3 - Electric Vehicle Charging Stations Sheet # ______11B-302 - Floor or Ground
Surfaces Sheet # ______11B-303 - Changes in Level Sheet # ______11B-305 - Clear Floor or Ground Space Sheet # ______11B-308 - Reach Ranges Sheet # ______11B-309 - Operable Parts Sheet
# ______11B-402 - Accessible Route Sheet # ______11B-703.3 - Braille Sheet # ______11B-703.7 - Symbols of Accessibility Sheet # ______11B-703.7.2.1 - International Symbol of Accessibility
Sheet # ______11B-707.2 - Clear Floor or Ground Space Sheet # ______11B-707.3 - Operable Parts Sheet # ______11B-707.7.2 - Characters Sheet # ______11B-707.9 - Point-of-Sale Devices
Sheet # ______11B-812 - Electric Vehicle Charging Stations
Electrical plans shall be completed, stamped, and signed by a California Licensed Electrical Engineer or a C-10 electrical contractor.
Project addressName of person completing the checklist (please print)SignatureElectrical Engineer or Contractor's License Number and Type Sample Electric Vehicle Charging Station Configuration
for Commercial Facilities or Public Accommodations (click here) Electric Vehicle Charging Station (1 - 4 Spaces)
The color of border lines, hatched lines, and letters shall contrast the surface of the access aisle. The blue color required for accessible parking shall not be used, except where accessible
EVCS and parking spaces share a common access aisle. Code reference: CBC 11B-812.7.2.
Access aisles shall be at the same level as the vehicle space they serve and shall not overlap the vehicular way. Access aisles shall not have changes in level or slopes exceeding 1:48
(2.08%). Code reference: CBC 11B-812.3.
Access aisles shall be on the passenger side of van accessible spaces. Where four or fewer total EVCS are provided in a facility, the access aisle for non-angled van accessible spaces
may be located on either side of the vehicle space. Access aisles are permitted on either side of standard spaces. Access aisles shall extend the full required length of the spaces
they serve. Code reference: CBC 11B-812.7.1.
Where required, signs shall be permanently posted either immediately adjacent to the vehicle space or within the projected vehicle space width at the head end of the vehicle space. Signs
may also be permanently posted on a wall at the interior end of the vehicle space. Code reference: CBC 11B-812.8.7.
Where vehicle spaces and access aisles are marked with lines, measurements shall be made to the centerline of the markings. When not adjacent to another vehicle space, parking space,
or access aisle, measurements may include the full width of the marking. Code reference: CBC 11B-812.1 including exception.
Vehicle spaces, access aisles, and vehicular routes serving them shall provide a vertical clearance of 98 inches minimum. Code reference: CBC 11B-812.4.
All EV chargers shall have accessible operable parts. Code reference: CBC 11B-812.2.
Sample Multiple Electric Vehicle Charging Stations Configuration for Commercial Facilities or Public Accommodations (click here)Electric Vehicle Charging Station (5 - 25 Spaces)
The color of border lines, hatched lines, and letters shall contrast the surface of the access aisle. The blue color required for accessible parking shall not be used, except where accessible
EVCS and parking spaces share a common access aisle. Code reference: CBC 11B-812.7.2.
Access aisles shall be at the same level as the vehicle space they serve and shall not overlap the vehicular way. Access aisles shall not have changes in level or slopes exceeding 1:48
(2.08%). Code reference: CBC 11B-812.3.
Access aisles shall be on the passenger side of van accessible spaces. Where four or fewer total EVCS are provided in a facility, the access aisle for non-angled van accessible spaces
may be located on either side of the vehicle space. Access aisles are permitted on either side of standard spaces. Access aisles shall extend the full required length of the spaces
they serve. Code reference: CBC 11B-812.7.1.
Where required, signs shall be permanently posted either immediately adjacent to the vehicle space or within the projected vehicle space width at the head end of the vehicle space. Signs
may also be permanently posted on a wall at the interior end of the vehicle space. Code reference: CBC 11B-812.8.7.
Where vehicle spaces and access aisles are marked with lines, measurements shall be made to the centerline of the markings. When not adjacent to another vehicle space, parking space,
or access aisle, measurements may include the full width of the marking. Code reference: CBC 11B-812.1 including exception.
Vehicle spaces, access aisles, and vehicular routes serving them shall provide a vertical clearance of 98 inches minimum. Code reference: CBC 11B-812.4.
All EV chargers shall have accessible operable parts. Code reference: CBC 11B-812.2.
Plan review, inspections, and contact information 6. Plan review
Permit applications must be submitted electronically through the
https://palmdesert.my.site.com/s/City of Palm Desert's Online Permit Portal, Clariti. Permit applications eligible for the expedited permitting process will receive a high priority and
be reviewed as early as practical, with a processing goal of 3 to 5 business days following receipt of the submittal and payment of all necessary plan review fees.
7. Inspections
Once all permits to construct the EVCS have been issued and the system has been installed, it must be inspected before final approval.
On-site inspections can be scheduled in the
https://palmdesert.my.site.com/s/City of Palm Desert's Online Permit Portal, Clariti.
Permit holders must provide the inspector with the printed approved plans, the Building Permit Inspection Record, and access to the location of the work. The permittee must be prepared
to show conformance with all technical requirements in the field at the time of inspection. The inspector will verify that the installation is in conformance with applicable code requirements
and the approved plans.
8. Departmental contact information
For additional information regarding this permitting process, visit our website at
https://www.palmdesert.gov/build-developCity of Palm Desert Building and Safety or contact the Building and Safety Division at (760) 777-6420.