COMMERCIAL / INDUSTRIAL PLAN SUBMITTAL
(Minimum Requirements)
Plan Review Procedures
The City strives to assist the public in understanding the plan review process by outlining the
timelines for the different projects, and to offer some guidelines to assist in the types of
information that is needed to conduct a plan review. The extent of the review required to issue
permits for a project depends upon the use or occupancy type of the structure, as well as its
location and the impact of its construction on the environment. The goal of the Building and
Safety Department is to complete all initial plan reviews wi thin 10 to 15 working days, and 8 to
10 working days for re-submittals. Small additions and minor interior improvements of
commercial space may be reviewed and permits issued in a short turnaround time. However,
this depends on the current daily workload o f the Plans Examiners.
All new construction projects are required to submit two (2) one-sided complete sets of plans,
plus one additional site plan and dimensioned floor plan for plan review. Plans shall be a
minimum of 11” x 17” and maximum of 24” x 36” with a minimum font of 10 pt.
Plot Plan:
The Plot Plan must be drawn to scale with setbacks identified between the property lines and
any existing structures. Show the location of all existing structures on the property. Provide a
north arrow. Show the locations of utility meters, driveway locati ons, drainage path, right-of-
ways and easements. All disabled access parking, walkways, drop off areas and path of travel
from the right-of-way for every structure on the site. An information box should be placed in the
bottom right corner indicating the s treet address, owner's name and address, and the name of
the person preparing the plans.
Foundation Plan:
Provide a plan view of the foundation slab, and cross section of footing details. Note soil type
and all allowable soil bearing pressure used for building design. Indicate all steel reinforcement
size and location, all hold down hardware locations, anchor bolt sizes and spacing, vapor
barrier thickness, etc.
City of Palm Desert
Department of Building and Safety
73-510 Fred Waring Dr., Palm Desert, CA 92260
(760) 346-0611
Fax (760) 776-6392
Floor Plan:
Fully dimension and identify all occupied office space, storage, etc. on flo or plan. Show width,
distance to, and direction of all exits. Show location of panic hardware. Indicate width and
distance of all corridors and type of fire resistive construction when required. Show all fixed
elements of construction such as walls, partitions, cabinets, etc., on the floor plan. Identify
area/occupancy separation walls and fire resistive rating of each on floor plan. Show complete
fully dimensioned elevations. Indicate roof pitch and type of roofing. Show details of special or
unusual construction or materials. Show details of fire rated construction and include item
number of assembly. Provide fully dimension and detailed disable access information.
Roof Plan:
Truss calculations are required for proposed trussed roof. Truss calculations must be reviewed
by the project engineer/architect for compliance with his/her design. If conventionally framed,
indicate size, spacing and direction of rafters. Identify roof finish material and sheathing
underlayment.
Exterior Elevations:
Provide four (4) exterior elevations identified as front, back, left and right sides. Show doors,
windows, finished floor line, exterior finish, and indicate roof pitch. Additionally, if the project
was subject to Design Review, indicate all applicable colors and other requirements of the
Planning Department.
Required Details:
Provide a cross section (cut view) of proposed job. Show foundation, wall studs, ceiling joists,
rafters, roof pitch, etc. Indicate size, spacing, and materials proposed. If ceiling is vaulted,
show cross section and structural connections.
Finish Materials:
Finish materials must be outlined or noted to indicate the ceiling, wall, and floor finish materials
and types, also the proposed glazing materials including the frame.
Engineering (Structural) Plans and Calculations:
If required, the location, size and grade of all framing members and specification must be
noted on the plans. Plans are required to be stamped and wet signed by the professional
responsible for their particular expertise and plan preparation. Include the structural design
criteria design load for, wind, seismic, etc. on the plans. Two (2) complete sets of structural
calculations and truss calculations (if applicable) with the architect's or engineer's original wet
signature and stamp on both sets of calculations and plans. Calculations must be complete
and cross-referenced to plans to provide a clear correlation with each other.
Seismic and Wind Design Requirements
Architects and engineers most common questions are r elated to the basic requirements for
seismic and wind. The City of Palm Desert is located within Seismic Design Category D for
projects designed using the CBC and D2 for projects designed using the CRC. Palm Desert is
located in a Special Wind Region. Therefore wind speed is site specific and must be designed
by the design professional. If you have any questions regarding these requirements, please
call a Plans Examiner at (760) 776 -6420, Ext. 420.
Plumbing and Mechanical Plans:
Provide plumbing isometri c and schematic showing sewer, soil, waste vents, and clean out
sizes and material. Show water piping system; pipe sizes, pipe material, to be installed on
plumbing floor plans. Show location of all gas meters and all gas piping, including size. Show
location of heating and air conditioning equipment including manufacturer's name, model
number and weight of equipment. Show all duct locations, material and sizes. Provide the
location of all fire dampers in walls, ceilings and equipment. Provide seismic ancho rage
methods and materials.
Electrical Plans:
Provide a one-line diagram showing service, feeder panel, conductors, disconnect, over
current sizes, grounding methods and service load calculation. Provide panel schedule with
circuit identification, description of circuits, walls and voltage. Provide fixture schedule and
method of support. Detail suspended fixtures. Provide seismic anchorage methods and
materials.
State Energy Conservation Information:
All new and existing structures with condition space are required to provide energy calculations
that will reduce energy consumption. All required forms shall be on the plans.
Green Building Code:
Plans shall indicate method of verification of compliance with all CALGreen requirements.
Third party or other methods shall demonstrate satisfactory conformance with mandatory
measures. Include City’s Mandatory Measures Checklist copies onto plans.
Other Requirements:
Additional information may be required by other City or County Agencies in order to convey
needed information relative to construction projects. Please feel free to contact a Building and
Safety Plans Examiner at (760) 776 -6420 for additional assistance with projects here in the
City of Palm Desert.