NOTICE TO GRADING PERMIT APPLICANTS
New Dust Control Ordinance Requirements
On November 13, 2003, the City Council of the City of Palm Desert unanimously passed
Ordinance 1056 which revised Title 24, Chapter 12 of the Palm Desert Municipal Code,
more commonly known as the Dust Control Ordinance. This ordinance was enacted
December 13, 2003, to comply with requirements from the South Coast Air Quality
Management District (AQMD), and has created new requirements for all applicants for
grading permits.
1. All projects disturbing more than 5,000 sq. ft. of earth must complete a PM10
plan. Providing PM10 notes on the grading plan will no longer be adequate.
Consult the AQMD Dust Control Handbook for additional requirements on
larger projects.
2. The PM10 plan wil l need to be prepared per the instructions in the AQMD
Dust Control Handbook. Form templates for preparing the plan are available
from the City or the AQMD.
3. Any individual responsible for preparing a PM10 plan must possess a
certificate of attendance for the Coachella Valley Fugitive Dust Control Class.
4. Any person performing any site grading, whether contractor or owner, must
possess a certificate of attendance for the Coachella Valley Fugitive Dust
Control Class or designate an individual who has a cert ificate of attendance to
represent them by completing a Owner Designee form.
If you have not yet attended the class you will need to contact the AQMD Tuesday
through Friday between the hours of 7:00 AM and 5:30 PM. To register, contact:
Sharon Fujimoto
South Coast Air Quality Management District
(866) 861-3878
dustcontrol@aqmd.gov
Classes are held monthly in the CVAG building in the Palm Desert Civic Center.*
Contact the AQMD for the exact dates and times of the classes.
There is no fee to take the class.
PM10 PLAN
(FORM I)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
PAGE #1
PM10 (FORM I) PAGE 1
Instructions For Preparing a PM10 Plan
Projects Less Than 10 Acres In Size
1. If you have not yet attended the Coachella Valley Fugitive Dust Control Class and received a
certificate of completion, and you are not designating a certified individual to act in your behalf, contact
the AQMD to register for the class. Contact Sharon Fujimoto at (866) 861-3878. The class if offered
monthly free of charge.
2. Fill out the 4 pages of the Palm Desert Fugitive Dust Control Plan Application Form - (FORM A).
When completing Form “A” follow instructions to complete a vicinity map and site exhibit.
3. If you are designating a certified individual to act on your behalf, complete the Ownership Designee
Form - (FORM OD).
4. Fill out the 5 pages of the Palm Desert Fugitive Dust Control Plan for Projects less than 10 Acres –
(FORM DCP). In each source category place an ‘X’ next to the best available control measure(s) you
intend to use. If a source category is not applicable to your project, write “N/A” over the bo x.
5. Submit the PM10 Plan Packet to the department of Public Works with your grading plan submittal.
6. At the time of grading permit issuance, obtain a PM10 sign per the attached drawing, and post at the
site entrance prior to starting any grading operations. The sign may be removed only after all grading
activities have ceased, any exposed areas have been stabilized, and the grading has received a final
inspection signoff.
PM10 PLAN
(FORM A)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
PAGE #1
PM10 (FORM A) PAGE 1 OF 4
Fugitive Dust Control Plan Application Form
(Form A - Page 1 of 4)
Please print in ink or type. Blank spaces must be completed for the application to be processed. If an item is not
applicable, please enter N/A.
1. Form Preparer: Property Owner q Developer q Prime Contractor q Other q*
*(If Other, attach Owner Designee Form OD) *
CONTACT PERSON NAME
COMPANY NAME
COMPANY ADDRESS
CITY, STATE, ZIP CODE
TELEPHONE NUMBER
FACSIMILE NUMBER
24-HOUR, M ANNED
AFTER HOURS PHONE
NUMBER
AQMD DUS T CLASS
CERTIFICATE #
2. Project Address or Location
PROJECT NAME
PROJECT ADDRESS
CITY, STATE, ZIP CODE
NEAREST M AJOR CROSS
STREETS
PARCEL NUMBERS
PM10 PLAN
(FORM A)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
PAGE #2
PM10 (FORM A) PAGE 2 OF 4
Fugitive Dust Control Plan Application Form
(Form A - Page 2 of 4)
3. Project Acreage (total land to be disturbed)
(include project site and associated unpaved access roads, stockpiles, and staging areas)
PROJECT SIZE (ACRES )
WATER SOURCE (GPM)
4. Project Owner (if Fugitive Dust Control Plan preparer is not the property owner)
NAME
COMPANY NAME (IF
APPLICABLE)
ADDRESS (INCLUDE
CITY, STATE, & ZIP
CODE)
TELEPHONE NUMBER
FACSIMILE NUMBER
5. The Person(s) responsible for dust control measures and to whom official notices should be sent if necessary
RESPONSIBLE P ERSON
COMPANY NAME
ADDRESS (INCLUDE
CITY, STATE, & ZIP
CODE)
TELEPHONE NUMBER
24-HOUR, M ANNED
AFTER-HOURS
TELEPHONE NUMBER
FACSIMILE NUMBER
AQMD DUST CLASS
CERTIFICATE #
PM10 PLAN
(FORM A)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
PAGE #3
PM10 (FORM A) PAGE 3 OF 4
Fugitive Dust Control Plan Application Form
(Form A - Page 3 of 4)
6. On -Site Superintendent/Supervisor/Foreman contact
NAME
COMPANY NAME
ADDRESS (INCLUDE
CITY, STATE, & ZIP
CODE)
TELEPHONE NUMBER
24-HOUR, M ANNED
AFTER-HOURS
TELEPHONE NUMBER
AQMD DUST CLASS
CERTIFICATE #
7. Site Mapping
Provide a map showing the vicinit y of the project clearly identifying the closest major cross streets or other landmarks
and the project location. Label this map “Vicinity Map”. Required map size is 8 ½” by 11”.
Provide an 8 ½” by 11” or larger Site Exhibit for the property(s) on which the project will be occurring. Identify the
affected parcels. Identify location of site entrances, internal unpaved haul routes, wind fencing, areas to be
chemically stabilized and other proposed and required dust control mitigations. Projects that are only installing or
constructing linear features such as roads, pipelines or other utilities that border or cross more than one Assessor’s
parcel do not require a Site Exhibit, but must provide a detailed vicinity map adequately depicting the entire project
area. If the project is divided into construction phases (separate physical project areas), provide an exhibit clearly
identifying the phases.
8. Attach a Fugitive Dust Control Plan
ü Projects with less than 10 acres of disturbed surfaces must complete a nd attach a Fugitive Dust Control
Plan (Form DCP) or equivalent.
ü Projects with 10 acres or more of disturbed surfaces must complete and attach a Site-Specific Fugitive
Dust Control Plan. Guidance for preparation of a Site-Specific Fugitive Dust Control P lan is available
upon request.
PM10 PLAN
(FORM A)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
PAGE #4
PM10 (FORM A) PAGE 4 OF 4
Fugitive Dust Control Plan Application Form
(Form A - Page 4 of 4)
9. Project notifications
For projects with 10 acres or more of disturbed surfaces, the dust control ordinance requires notification to the local
permitting authority and to the AQMD prior to project initiation and at project completion. (Refer to Chapter 4 of the
Coachella Valley Fugitive Dust Control Handbook for specific requirements and forms).
10. Project Signage
Construction signage must be installed on-site prior to construction. Guidelines for construction signage are found
attached to this packet.
11. Owner Agreement
A signature on this application constitutes an agreement by the owner to be the person with authority to
enforce compliance by all contractors and subcontractors of the Dust Control Ordinance, Fugitive Dust
Control Plan conditions, and any supplements identified by the permitting authority. Once approved, this
application is incorporated by reference and becomes a part of the approved site grading plan.
Owner or Owner Designee Signature Date
Printed Name Title and Company
AQMD Coachella Valley Fugitive Dust Control Class Certificate #
PM10 PLAN
(FORM OD)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
PAGE #1
PM10 (FORM OD) PAGE 1 OF 1
Ownership Designee Form
(Form OD)
An owner’s designee form is required if a Fugitive Dust Control Plan is not prepared/implemented by the property
owner, developer or prime contractor.
PROJECT INFORMATION PLEASE ENTER INFORMATION BELOW
DESIGNEE’S NAME
COMPANY NAME
ADDRESS /LOCATION
PHONE NUMBER
AFTER-HOURS PHONE
NUMBER
AQMD DUST CLASS
CERTIFICATE #
PROPERTY OWNER
INFORMATION PLEASE ENTER INFORMATION BELOW
PROPERTY OWNER’S NAME
ADDRESS /LOCATION
PHONE NUMBER
24-HOUR, M ANNED AFTER-
HOURS PHONE NUMBER
OWNER STATEMENT
I hereby authorize the person listed as my designee to act on my behalf in all matters regarding the issuance and requirements
of the Fugitive Dust Control Plan for construction activities. The designee is responsible for project duration. The designee
has successfully completed the AQMD Coachella Valley Fugitive Dust Control Class. Furthermore, the designee is
responsible for ensuring the contractor(s), subcontractor(s), and all other persons associated with the project are in
compliance with the approved Fugitive Dust Control Plan, dust control ordinance requirements, and AQMD regulations.
Owner’s Signature Date
Printed Name
PM10 PLAN
(FORM DCP)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
INSTRUCTIONS
PM10 (FORM DCP) INSTRUCTIONS
N/A P
P
P
FUGITIVE DUST CONTRO L PLAN PREPARATION G UIDANCE FOR
SMALLER CONSTRUCTION PROJECTS
(LESS THAN 10 ACRES)
The following instructions have been prepared to assist project operators in preparing a Fugitive Dust
Control Plan for construction activities with les s than 10 acres of disturbed surfaces. Submitting a
complete Fugitive Dust Control Plan is essential in expediting the process, so please read and follow the
instructions carefully.
Fugitive Dust Control Plan Guidance
Use the attached pages (Form DCP) to designate the dust control actions to be implemented on-site.
Separate the actions to be implemented during the various project phases (e.g., clearing/grubbing and
mass grading, finish grading, and site construction, etc.). If applicable, describe the additional control
actions to be implemented on-site.
Please remember the following when preparing a Fugitive Dust Control Plan:
ü A complete copy of the Fugitive Dust Control Plan and all maps must be on-site prior to
beginning construction activity and must be retained on-site at all times during project
construction.
ü Construction signage must be installed on-site prior to construction. Guidelines for construction
signage are found in this packet.
ü Dust control is required 24 hours a day, 7 days a week for the duration of the project regardless
of wind conditions or construction project status.
ü Daily recordkeeping of dust control actions is required to be compiled and retained during
project duration and for three years after project completion.
ü Grading plans must include a statement that incorporates the approved fugitive dust control plan
into the approved grading plan.
Example
Backfilling
Stabilize backfill material:
q 01 -1 when not actively handling;
q 01 -2 during handling;
q 01 -3 at completion of activity.
Stabilize backfill material:
q 01 -1 when not actively handling; &
q 01 -2 during handling; &
q 01 -3 at completion of activity.
Stabilize backfill material:
q 01 -1 when not actively handling; &
q 01 -2 during handling; &
q 01 -3 at completion of activity.
PM10 PLAN
(FORM DCP)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
PAGE #1
PM10 (FORM DCP) PAGE 1 OF 5
Fugitive Dust Control Plan
For Projects < 10 Acres (Form DCP, Page 1 of 5)
Project Name: _____________________________________ Water Source ___ ________________
Permit Number (if applicable): _______________________ No. Water Trucks ______________________
Owner Name: _____________________________________ No. Water Towers _________________________
Anticipated Start Date: __________________ Anticipated Completion Date: _______________
Total Earth-Movement (Cubic Yards): _____________________________________
Note: Complete entire form by checking applicable boxes. Write “N/A” over box if not applicable.
Project Phases
Source
Category
Clearing, Grubbing, & Mass Grading
(Describe Control Actions)
Finish Grading
(Describe Control Actions)
Site Constructio n
(Describe Control Actions)
Backfilling
Stabilize backfill material:
q 01 -1 when not actively handling;
q 01 -2 during handling;
q 01 -3 at completion of activity.
Stabilize backfill material:
q 01 -1 when not actively handling; &
q 01 -2 during handling; &
q 01 -3 at completion of activity.
Stabilize backfill material:
q 01 -1 when not actively handling; &
q 01 -2 during handling; &
q 01 -3 at completion of activity.
Clearing and
Grubbing
q 02 -1 Maintain soil stability by
pre -watering of site prior to
activities;
q 02 -2 Stabilize soil during activities;
q 02 -3 Stabilize soil immediately
after activities.
q 02 -1 Maintain soil stability by
pre -watering of site prior to
activities;
q 02 -2 Stabilize soil during activities;
q 02 -3 Stabilize soil immediately
after activities.
q 02 -1 Maintain soil stability by
pre -watering of site prior to
activities;
q 02 -2 Stabilize soil during activities;
q 02 -3 Stabilize soil immediately
after activities.
Clearing
Forms
q 03 -1 water spray to clear forms; or
q 03 -2 sweeping and water
spray to clear forms; or
q 03 -3 vacuum system to
clear forms.
q 03 -1 water spray to clear forms; or
q 03 -2 sweeping and water
spray to clear forms; or
q 03 -3 vacuum system to
clear forms.
q 03 -1 water spray to clear forms; or
q 03 -2 sweeping and water
spray to clear forms; or
q 03 -3 vacuum system to
clear forms.
Crushing
q 04 -1 Stabilize surface soils prior to
operation of support equip.
q 04 -2 Stabilize mater. after crushing.
q 04 -1 Stabilize surface soils prior to
operation of support equip.
q 04 -2 Stabilize mater. after crushing.
q 04 -1 Stabilize surface soils prior to
operation of support equip.
q 04 -2 Stabilize mater. after crushing.
PM10 PLAN
(FORM DCP)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
PAGE #2
PM10 (FORM DCP) PAGE 2 OF 5
Fugitive Dust Control Plan
For Projects < 10 Acres (Form DCP, Page 2 of 5)
Project Phases
Source
Category
Clearing, Grubbing, and Mass Grading
(Describe Control Actions)
Finish Grading
(Describe Control Actions)
Site Construction
(Describe Control Actions)
Cut and Fill
q 05 -1 Pre -water soils prior to cut
and fill activities; and.
q 05 -2 Stabilize soil during and
after cut and fill activities.
q 05 -1 Pre -water soils prior to cut
and fill activities; and.
q 05 -2 Stabilize soil during and
after cut and fill activities.
q 05 -1 Pre -water soils prior to cut
and fill activities; and.
q 05 -2 Stabilize soil during and
after cut and fill activities.
Demolition
mechanical
/manual
q 06 -1 Stabilize wind erodible
surfaces to prevent dust; and
q 06 -2 Stabilize surface soil where
support equipment and
vehicles will operate; and
q 06 -3 Stabilize loose soil and
demolition debris; and
q 06 -4 Comply with AQMD Rule
1403.
q 06 -1 Stabilize wind erodible
surfaces to prevent dust; and
q 06 -2 Stabilize surface soil where
support equipment and
vehicles will operate; and
q 06 -3 Stabilize loose soil and
demolition debris; and
q 06 -4 Comply with AQMD Rule
1403.
q 06 -1 Stabilize wind erodible
surfaces to prevent dust; and
q 06 -2 Stabilize surface soil where
support equipment and
vehicles will operate; and
q 06 -3 Stabilize loose soil and
demolition debris; and
q 06 -4 Comply with AQMD Rule
1403.
Disturbed
soil
q 07 -1 Stabilize disturbed soil
throughout the construction
site; and
q 07 -2 Stabilize disturbed soil
between structures
q 07 -1 Stabilize disturbed soil
throughout the construction
site; and
q 07 -2 Stabilize disturbed soil
between structures
q 07 -1 Stabilize disturbed soil
throughout the construction
site; and
q 07 -2 Stabilize disturbed soil
between structures
Ea rth-
moving
activities
q 08 -1 Pre -apply water to depth of
proposed cuts; and
q 08 -2 Re -apply water as necessary
to maintain soils in a damp
condition; and
q 08 -3 Stabilize soils once earth-
moving activities are
complete.
q 08 -1 Pre -apply water to depth of
proposed cuts; and
q 08 -2 Re -apply water as necessary
to maintain soils in a damp
condition; and
q 08 -3 Stabilize soils once earth-
moving activities are
complete.
q 08 -1 Pre -apply water to depth of
proposed cuts; and
q 08 -2 Re -apply water as necessary
to maintain soils in a damp
condition; and
q 08 -3 Stabilize soils once earth-
moving activities are
complete.
Importing/
exporting
of bulk
materials
q 09 -1 Stabilize material while
loading to prevent fugitive
dust emissions; and
q 09 -2 Maintain at least six inches
of freeboard on haul
vehicles; and
q 09 -3 Limit vehicular speeds to
15 miles per hour while
traveling on-site; and
q 09 -1 Stabilize material while
loading to prevent fugitive
dust emissions ; and
q 09 -2 Maintain at least six inches
of freeboard on haul
vehicles; and
q 09 -3 Limit vehicular speeds to
15 miles per hour while
traveling on-site; and
q 09 -1 Stabilize material while
loading to prevent fugitive
dust emissions; and
q 09 -2 Maintain at least six inches
of freeboard on haul
vehicles; and
q 09 -3 Limit vehicular speeds to
15 miles per hour while
traveling on-site; and
PM10 PLAN
(FORM DCP)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
PAGE #3
PM10 (FORM DCP) PAGE 3 OF 5
Fugitive Dust Control Plan
For Projects < 10 Acres (Form DCP, Page 3 of 5)
Project Phases
Source
Category
Clearing, Grubbing, and Mass Grading
(Describe Control Actions)
Finish Grading
(Describe Control Actions)
Site Construction
(Describe Control Actions)
Importing/
exporting
of bulk
materials
(cont.)
q 09 -4 Stabilize material while
tra nsporting to prevent
fugitive dust emissions;
and
q 09 -5 Stabilize material while
unloading to prevent
fugitive dust emissions;
and
q 09 -6 Comply with Vehicle
Code Section 23114.
q 09 -4 Stabilize material while
transporting to prevent
fugitive dust emissions;
and
q 09 -5 Stabilize material while
unloading to prevent
fugitive dust emissions;
and
q 09 -6 Comply with Vehicle
Code Section 23114.
q 09 -4 Stabilize material while
transporting to prevent
fugitive dust emissions;
and
q 09 -5 Stabilize material while
unloading to prevent
fugitive dust emissions;
and
q 09 -6 Comply with Vehicle
Code Section 23114.
Landscap-
ing
q 10 -1 Stabilize soils, materials,
slopes
q 10 -1 Stabilize soils, materials ,
slopes
q 10 -1 Stabilize soils, materials,
slopes
Road
shoulder
maint.
q 11 -1 Apply water to unpaved
shoulders prior to clearing;
and
q 11 -2 Apply chemical dust
suppressants and/or washed
gravel to maintain a
stabilized surface after
completing road shoulder
maintenance.
q 11 -1 Apply water to unpaved
shoulders prior to clearing;
and
q 11 -2 Apply chemical dust
suppressants and/or washed
gravel to maintain a
stabilized surface after
completing road shoulder
maintenance.
q 11 -1 Apply water to unpaved
shoulders prior to clearing;
and
q 11 -2 Apply chemical dust
suppressants and/or washed
gravel to maintain a
stabilized surface after
completing road shoulder
maintenance.
Screening
q 12 -1 Pre -water ma terial prior to
screening; and
q 12 -2 Limit fugitive dust emissions
to opacity and plume length
standards; and
q 12 -3 Stabilize material
immediately after screening.
q 12 -1 Pre -water material prior to
screening; and
q 12 -2 Limit fugitive dust emissions
to opacity and plume length
standards; and
q 12 -3 Stabilize material
immediately after screening.
q 12 -1 Pre -water material prior to
screening; and
q 12 -2 Limit fugitive dust emissions
to opacity and plume length
standards; and
q 12 -3 Stabilize material
immediately after screening.
Staging
Areas
q 13 -1 Stabilize staging areas during
use; and
q 13 -2 Stabilize staging area soils at
project completion.
q 13 -1 Stabilize staging areas during
use; and
q 13 -2 Stabilize staging area soils at
project completion.
q 13 -1 Stabilize staging areas during
use; and
q 13 -2 Stabilize staging area soils at
project completion.
PM10 PLAN
(FORM DCP)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
PAGE #4
PM10 (FORM DCP) PAGE 4 OF 5
Fugitive Dust Control Plan
For Projects < 10 Acres (Form DCP, Page 4 of 5)
Project Phases
Source
Category
Clearing, Grubbing, and Mass Grading
(Describe Control Actions)
Finish Grading
(Describe Control Actions)
Site Construction
(Describe Control Actions)
Stockpiles/
bulk
materials
handling
q 14 -1 Stabilize stockpiled
materials; or
q 14 -2 Install and maintain wind
barriers with no less than 50
percent porosity on three
sides of the pile, such that
the barrier is equal to or
greater than the pile height.
q 14 -3 Stockpiles within 100 yards
of occupied buildings must
not be greater than eight feet
in height; or
q 14 -4 Stockpiles greater than eight
feet in height and not
covered must have a road
bladed to the top to allow
water truck access or must
have an operational water
irrigation system that is
capable of complete
stockpile coverage.
q 14 -1 Stabilize stockpiled
materials; or
q 14 -2 Install and maintain wind
barriers with no less than 50
percent porosity on three
sides of the pile, such that
the barrier is equal to or
greater than the pile height.
q 14 -3 Stockpiles within 100 yards
of occupied buildings must
not be greater than eight feet
in height; or
q 14 -4 Stockpiles greater than eight
feet in height and not
covered must have a road
bladed to the top to allow
water truck acces s or must
have an operational water
irrigation system that is
capable of complete
stockpile coverage.
q 14 -1 Stabilize stockpiled
materials; or
q 14 -2 Install and maintain wind
barriers with no less than 50
percent porosity on three
sides of the pile, such that
the barrier is equal to or
greater than the pile height.
q 14 -3 Stockpiles within 100 yards
of occupied buildings must
not be greater than eight feet
in height; or
q 14 -4 Stockpiles greater than eight
feet in height and not
covered must have a road
bladed to the top to allow
water truck access or must
have an operational water
irrigation system that is
capable of complete
stockpile coverage.
Traffic
areas for
const.
activities
q 15 -1 St abilize all off -road traffic
and parking areas; and
q 15 -2 Ensure that on-site vehicular
traffic does not exceed 15
miles per hour; and
q 15 -3 Stabilize all haul routes; and
q 15 -4 Direct construction traffic
over established haul routes.
q 15 -1 St abilize all off -road traffic
and parking areas; and
q 15 -2 Ensure that on-site vehicular
traffic does not exceed 15
miles per hour; and
q 15 -3 Stabilize all haul routes; and
q 15 -4 Direct construction traffic
over established haul routes.
q 15 -1 St abilize all off -road traffic
and parking areas; and
q 15 -2 Ensure that on-site vehicular
traffic does not exceed 15
miles per hour; and
q 15 -3 Stabilize all haul routes; and
q 15 -4 Direct construction traffic
over established haul routes.
Trenchin g
q 16 -1 Stabilize surface soils where
trencher or excavator and
support equipment will
operate; and
q 16 -2 Stabilize soils at the
completion of trenching
activities .
q 16 -1 Stabilize surface soils where
trencher or excavator and
support equipment will
operate; and
q 16 -2 Stabilize soils at the
completion of trenching
activities .
q 16 -1 Stabilize surface soils where
trencher or excavator and
support equipment will
operate; and
q 16 -2 Stabilize soils at the
completion of trenching
activities .
Truck
loading
q 17 -1 Pre -water material prior to
loading; and
q 17 -2 Ensure that freeboard does
not exceed six inches
q 17 -1 Pre -water material prior to
loading; and
q 17 -2 Ensure that freeboard does
not exceed six inches
q 17 -1 Pre -water material prior to
loading; and
q 17 -2 Ensure that freeboard does
not exceed six inches
PM10 PLAN
(FORM DCP)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
PAGE #5
PM10 (FORM DCP) PAGE 5 OF 5
Fugitive Dust Control Plan
For Projects < 10 Acres (Form DCP, Page 5 of 5)
Project Phases
Source
Category
Clearing, Grubbing, and Mass Grading
(Describe Control Actions)
Finish Grading
(Describe Control Actions)
Site Construction
(Describe Control Actions)
Turf
overseed -
ing
q 18 -1 Apply sufficient water
immediately prior to
conducting turf vacuuming
activities to meet opacity and
plu me length standards; and
q 18 -2 Cover haul vehicles prior to
exiting the site.
q 18 -1 Apply sufficient water
immediately prior to
conducting turf vacuuming
activities to meet opacity and
plume length standards; and
q 18 -2 Cover haul vehicles prior to
exiting the site.
q 18 -1 Apply sufficient water
immediately prior to
conducting turf vacuuming
activities to meet opacity and
plume length standards; and
q 18 -2 Cover haul vehicles prior to
exiting the site.
Unpaved
roads/
parking lots
q 19 -1 Stabilize soils to meet the
applicable performance
standards; and
q 19 -2 Limit vehicular travel to
established unpaved roads
(haul routes) and unpaved
parking lots
q 19 -1 Stabilize soils to meet the
applicable performance
standards; and
q 19 -2 Limit vehicular travel to
established unpaved roads
(haul routes) and unpaved
parking lots
q 19 -1 Stabilize soils to meet the
applicable performance
standards; and
q 19 -2 Limit vehicular travel to
established unpaved ro ads
(haul routes) and unpaved
parking lots
Vehicular
track-out,
clean-up
q 19 -3 Use wheel washes at
construction entrances
q19-4 Use street sweeping as
required.
q 19 -3 Use wheel washes at
construction entrances
q19-4 Use street sweeping as
required.
q 19 -3 Use wheel washes at
construction entrances
q19-4 Use street sweeping as
required.
Weather
monitoring/
work
practices
q 20 -1 Monitor current weather
conditions predictions from
the AQMD’s wind forecast
system (800) CUT -SMOG
[Press 1, then Press 5] or the
National Weather Service; &
q 20 -2 Cease all construction
activities if fugitive dust
emissions exceed 20 percent
opacity or if 100 foot visible
plume restriction cannot be
met. Control measures must
continue to operate unless
operation of such equipment
cannot reduce emissions or if
visibility is limited to such an
extent that it is hazardous to
operate such equipment.
q 20 -1 Monitor current weather
conditions predictions from
the AQMD’s wind forecast
system (800) CUT -SMOG
[Press 1, then Press 5] or the
National Weather Service; &
q 20 -2 Cease all construction
activities if fugitive dust
emissions exceed 20 percent
opacity or if 100 foot visible
plume restriction cannot be
met. Control measures must
continue to operate unless
operation of such equipment
cannot reduce emissions or if
visibility is limited to such an
extent that it is hazardous to
operate such equipment.
q 20 -1 Monitor current weather
conditions predictions from
the AQMD’s wind forecast
system (800) CUT -SMOG
[Press 1, then Press 5] or the
National Weather Service; &
q 20 -2 Cease all construction
activities if fugitive dust
emissions exceed 20 percent
opacity or if 100 foot visible
plume restriction cannot be
met. Control measures must
continue to operate unless
operation of such equipment
cannot reduce emissions or if
visibility is limited to such an
extent that it is hazardous to
operate such equipment.
Other
(describe)
PM10 PLAN
(FORM BACM)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
PAGE #1
PM10 (FORM BACM) PAGE 1 of 5
PM10 - BEST AVAILABLE CONTROL MEASURES (BACM)
Source Category Control Measure Guidance
Backfilling 01-1
01-2
01-3
Stabilize backfill material when not actively
handling; and
Stabilize backfill material during handling;
and
Stabilize soil at completion of activity.
ü Mix backfill soil with water prior to
moving
ü Dedicate water truck or high
capacity hose to backfilling
equipment
ü Empty loader bucket slowly so that
no dust plumes are generated
ü Minimize drop height from loader
bucket
Clearing and
grubbing
02-1
02-2
02-3
Maintain stability of soil through pre-
watering of site prior to clearing and
grubbing; and
Stabilize soil during clearing and grubbing
activities; and
Stabilize soil immediately after clearing and
grubbing activities.
ü Maintain live perennial vegetation
and desert pavement where possible
ü Apply water in sufficient quantity to
prevent generation of dust plumes
Clearing forms 03-1
03-2
03-3
Use water spray to clear forms; or
Use sweeping and water spray to clear
forms; or
Use vacuum s ystem to clear forms.
ü Use of high pressure air to clear
forms may cause exceedance of
opacity/plume length restrictions
Crushing 04-1
04-2
Stabilize surface soils prior to operation of
support equipment; and
Stabilize material after crushing.
ü Follow permit conditions for
crushing equipment
ü Pre-water material prior to loading
into crusher
ü Monitor crusher emissions opacity
ü Apply water to crushed material to
prevent dust plumes
Cut and fill 05-1
05-2
Pre-water soils prior to cut and fill activities;
and
Stabilize soil during and after cut and fill
activities.
ü For large sites, pre-water with
sprinklers or water trucks and allow
time for penetration
ü Use water trucks/pulls to water soils
to depth of cut prior to subsequent
cuts
PM10 PLAN
(FORM BACM)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
PAGE #2
PM10 (FORM BACM) PAGE 2 of 5
Source Category Control M easure Guidance
Demolition –
mechanical/
manual
06-1
06-2
06-3
06-4
Stabilize wind erodible surfaces to prevent
dust; and
Stabilize surface soil where support
equipment and vehicles will operate; and
Stabilize loose soil and demolition debris;
and
Comply with AQMD Rule 1403.
ü Apply water in sufficient quantities
to prevent the generation of visible
dust plumes
Disturbed soil 07-1
07-2
Stabilize disturbed soil throughout the
construction site; and
Stabilize disturbed soil between structures
ü Limit vehicular traffic and
disturbances on soils where possible
ü If interior block walls are planned,
install as early as possible
ü Apply water or a stabilizing agent in
sufficient quantities to prevent the
generation of visible dust plumes
Earth-moving
activities
08-1
08-2
08-3
Pre-apply water to depth of proposed cuts;
and
Re -apply water as necessary to maintain
soils in a damp condition; and
Stabilize soils once earth-moving activities
are complete.
ü Grade each project phase separately,
timed to coincide with construction
phase
ü Upwind fencing can prevent
material movement on site
ü Apply water or a stabilizing agent in
sufficient quantities to prevent the
generation of visible dust plumes
Importing/
exporting of bulk
materials
09-1
09-2
09-3
09-4
09-5
09-6
Stabilize material while loading to prevent
fugitive dust emissions; and
Maintain at least six inches of freeboard on
haul vehicles; and
Limit vehicular speeds to 15 miles per hour
while traveling on-site; and
Stabilize material while transporting to
prevent fugitive dust emissions; and
Stabilize material while unloading to
prevent fugitive dust emissions; and
Comply with Vehicle Code Section 23114.
ü Use tarps or other suitable
enclosures on haul trucks
ü Check belly-dump truck seals
regularly and remo ve any trapped
rocks to prevent spillage
ü Comply with track-out
prevention/mitigation requirements
ü Provide water while loading and
unloading to prevent visible dust
plumes
PM10 PLAN
(FORM BACM)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
PAGE #3
PM10 (FORM BACM) PAGE 3 of 5
Source Category Control Measure Guidance
Landscaping 10-1 Stabilize soils, materials, slopes ü Apply water to materials to stabilize
ü Maintain materials in a crusted
condition
ü Maintain effective cover over
materials
ü Stabilize sloping surfaces using soil
binders until vegetation or ground
cover can effectively stabilize the
slopes
ü Hyd roseed prior to rain season
Road shoulder
maintenance
11-1
11-2
Apply water to unpaved shoulders prior to
clearing; and
Apply chemical dust suppressants and/or
washed gravel to maintain a stabilized
surface after completing road shoulder
maintenance.
ü Installation of curbing and/or paving
of road shoulders can reduce
recurring maintenance costs
ü Use of chemical dust suppressants
can inhibit vegetation growth and
reduce future road shoulder
maintenance costs
Screening 12-1
12-2
12-3
Pre-water material prior to screening; and
Limit fugitive dust emissions to opacity and
plume length standards; and
Stabilize material immediately after
screening.
ü Dedicate water truck or high
capacity hose to screening operation
ü Drop material through the screen
slowly and mini mize drop height
ü Install wind barrier with a porosity
of no less than 50% upwind of
screen to the height of the drop point
Staging areas 13-1
13-2
Stabilize staging areas during use; and
Stabilize staging area soils at project
completion.
ü Limit size of staging area
ü Limit vehicle speeds to 15 miles per
hour
ü Limit number and size of staging
area entrances/exists
PM10 PLAN
(FORM BACM)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
PAGE #4
PM10 (FORM BACM) PAGE 4 of 5
Source Category Control Measure Guidance
Stockpiles/
Bulk Material
Handling
14-1
14-2
14-3
14-4
Stabilize stockpiled materials; or
Install and maintain wind barriers with no
less than 50 percent porosity on three sides
of the pile, such that the barrier is equal to or
greater than the pile height.
Stockpiles within 100 yards of occupied
buildings must not be greater than eight feet
in height; or
Stockpiles greater than eight feet in height
and not covered must have a road bladed to
the top to allow water truck access or must
have an operational water irrigation system
that is capable of complete stockpile
coverage.
ü Add or remove materia l from the
downwind portion of the storage pile
ü Maintain storage piles to avoid steep
sides or faces
Traffic areas for
construction
activities
15-1
15-2
15-3
15-4
Stabilize all off-road traffic and parking
areas; and
Ensure that on-site vehicular traff ic does not
exceed 15 miles per hour; and
Stabilize all haul routes; and
Direct construction traffic over established
haul routes.
ü Apply gravel/paving to all haul
routes as soon as possible to all
future roadway areas
ü Barriers can be used to ensure
vehicle s are only used on established
parking areas/haul routes
Trenching 16-1
16-2
Stabilize surface soils where trencher or
excavator and support equipment will
operate; and
Stabilize soils at the completion of trenching
activities.
ü Pre-watering of soils prior to
trenching is an effective preventive
measure. For deep trenching
activities, pre-trench to 18 inches
soak soils via the pre-trench and
resuming trenching
ü Washing mud and soils from
equipment at the conclusion of
trenching activities can prevent
crusting and drying of soil on
equipment
Truck loading 17-1
17-2
Pre-water material prior to loading; and
Ensure that freeboard does not exceed six
inches
ü Empty loader bucket such that no
visible dust plumes are created
ü Ensure that the loader bucket is close
to the truck to minimize drop height
while loading
PM10 PLAN
(FORM BACM)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
PAGE #5
PM10 (FORM BACM) PAGE 5 of 5
Source Category Control Measure Guidance
Turf overseeding 18-1
18-2
Apply sufficient water immediately prior to
conducting turf vacuuming activities to meet
opacity and plume length standards; and
Cover haul vehicles prior to exiting the site.
ü Haul waste material immediately
off-site
Unpaved
roads/parking lots
19-1
19-2
Stabilize soils to meet the applicable
performance standards; and
Limit vehicular travel to established unpaved
roads (haul routes) and unpaved parking lots.
ü Restricting vehicular access to
established unpaved travel paths and
parking lots can reduce stabilization
requirements
Weather
monitoring/work
practices
20-1
20-2
Monitor current weather conditions and
weather predictions from the AQMD’s toll
free wind forecast system (800) CUT-
SMOG [Press 1, then Press 5] and / or the
National Weather Service; and
Cease all construction activities if fugitive
dust emissions exceed 20 percent opacity or
if 100 foot visible plume restriction cannot
be met. Control measures (e.g., water
trucks/pulls) must continue to operate unless
operation of such equipment cannot reduce
fugitive dust emissions or if visibility is
limited to such an extent that it is hazardous
to continue operating such equipment.
ü Documentation of weather (e.g.,
wind) conditions can facilitate
compliance determinations when
using an affirmable defense to dust
control ordinance and Fugitive Dust
Control Plan requirements
SUMMARY OF DUST CONT ROL ORDINANCE REQUIREMENTS
The Coachella Valley dust control ordinances require:
ü at least one of the Coachella Valley Best Available Control Measures (CV BACM) is required to be
implemented for each fugitive dust source category.
ü CV BACM must be implemented such that the applicable performance standards (e.g., visible
emissions not to exceed 100 feet or 20 percent opacity, or cross any property line, etc.) are met.
A description of the performance standards and applicable test methods is included in Chapter 8 of the
Coachella Valle y Fugitive Dust Control Handbook.
I hereby certify that I have read and understand the foregoing requirements.
Signature ____________________________________________ Date ___________________________
Print Name ____________________________________________ Dust Certificate # ________________
PM10 PLAN
(FORM BOND)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
PAGE #1
PM10 (FORM BOND) PAGE 1 OF 1
Surety Bond or Certificate of Deposit
(Form BOND)
The City Council of the City of Palm Desert shall require a bond, a cash Certificate of Deposit, or an equivalent form
approved by the City, in an amount equal to at least two thousand dollars ($2,000.00) per acre or portion thereof. Such
funds shall be in an amount sufficient to completely stabilize all disturbed areas in the event that the Operator fails to
adequately control dust, or abandons the site in lieu of mitigating fugitive dust problems; and shall be easily accessible
to the City in order to initiate stabilization measures without a significant delay.
FORM OF PAYMENT PARCEL SIZE IN ACRES $2,000.00/ACRE AMOUNT OF BOND
Cash Deposit $2,000.00
Certificate of Deposit $2,000.00
Letter of Credit $2,000.00
Other (specify) $2,000.00
Parcel Size x $2,000.00 Per Acre = Amount of Bond
PM10 PLAN
DAILY LOG
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
DATE: ______________
PM10 DAILY LOG AM HOURS
Daily Self-Inspection Recordkeeping Form – AM HOURS
Elements
Monitored 12am 1am 2am 3am 4am 5am 6am 7am 8am 9am 10am 11am Comments
Forecasted high
winds
Wind speed
Wind direction
# Water trucks
operating
# Water trucks
available
Roads
moist/watered
Unstabilized areas
moist/watered
Dry areas
observed
Irrigation working
Water tanks filled
Water pumps
working
Chemical
stabilization used
Track-out
observed
Blow sand
observed on-site
Blowing dust
observed on-site
Blowing dust
observed off -site
Wind/snow
fencing maintained
# Complaints
received
Corrective action
taken
N= No or none Y = Yes N/A = Not applicable Name: ___________________ Date: ______________________
Additional Comments:
PM10 PLAN
DAILY LOG
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
DATE: ______________
PM10 DAILY LOG PM HOURS
Daily Self-Inspection Recordkeeping Form – PM HOURS
Elements
Monitored 12pm 1pm 2pm 3pm 4pm 5pm 6pm 7pm 8pm 9pm 10pm 11pm Comments
Forecasted high
winds
Wind speed
Wind direction
# Water trucks
operating
# Water trucks
available
Roads
moist/watered
Unstabilized areas
moist/watered
Dry areas
observed
Irrigation working
Water tanks filled
Water pumps
working
Chemical
stabilization used
Track-out
observed
Blow sand
observed on-site
Blowing dust
observed on-site
Blowing dust
observed off -site
Wind/snow
fencing maintained
# Complaints
received
Corrective action
taken
N= No or none Y = Yes N/A = Not applicable Name: ___________________ Date: ______________________
Additional Comments:
PM10 PLAN
(FORM CDS)
CITY OF PALM DESERT
73-510 FRED WARING DRIVE
PALM DESERT, CALIFORNIA 92260-2578
TEL: (760) 776-6450
FAX: (760) 341-7098
DATE: ______________
PM10 CHEMICAL DUST SUPPRES SANT RECORD (FORM CDS)
Chemical Dust Suppressant Recordkeeping Form
(Form CDS)
The dust control ordinance requires activities that utilize chemical dust suppressants must retain records indicating the
type of product applied, vendor name, and the method, frequency, concentratio n, quantity and date of application. A
copy of invoices for chemical dust suppressant products or application services is also required. These records must
be retained for at least three years after project completion.
PROJECT INFORMATION PLEASE ENTER INFORMATION BELOW
PLAN /PERMIT NUMBER
(IF APPLICABLE)
PROPERTY OWNER N AME/PHONE
CONSTRUCTION PROJECT NAME
PROJECT ADDRESS/L OCATION
DUST SUPPRESSANT
PRODUCT INFORMATION PLEASE ENTER INFORMATION PLEASE ENTER INFORMAT ION BELOW
DATE/T IME OF APPLICATION
NAME OF PRODUCT
DILUTION RATE
APPLICATION RATE
ACREAGE/SQUARE FOOTAGE T REATED
TRAFFIC OR NON-TRAFFIC AREA
DUST SUPPRESSANT
APPLICATOR INFORMATION
APPLICATOR N AME
CONTACT
PHONE
WARRANTEE T ERMS
(IF APPLICABLE)
Signature of Form Preparer: ____________________________________________ Date: ____________________
J' (IVIN.)
0 GRADING PERMIT XX=XXX
SITE ADDRESS OR PRJ. NM & CASE #
01F YOU SEE DUST COMING
FROM THIS PROJECT CALL
CONTRACTOR
0 ### m ### m ####
IF YOU DO NOT GET A RESPONSE WITHIN ONE HOUR,
�5 PLEASE CALL PUBLIC WORKS AT 760-776-6450 (DAY)
OR CALL A.Q.M.D. AT 1-800-CUT-SMOG
5000 SF TO 1 ACRE PM 10 SIGN
4' (MIN.)
10GRADING PERMIT (GR. PMT. #)
ADDRESS OR PRJ. NM & CASE #
CIF YOU SEE DUST COMING
oFROM THIS PROJECT CALL
eCONTRACTOR
e###m###m####
<, IF YOU DO NOT GET A RESPONSE WITHIN ONE HOUR,
PLEASE CALL PUBLIC WORKS AT 760-776-6450 (DAY) OR
OR CALL A.Q.M.D. AT 1-800-CUT-SMOG
9 ACRE TO 10 ACRE PM 10 SIGN
8' (MIN.)
g I
ADDRESSGRADING
OR PROJ. NAME &CASP#
• IF YOU SEE DUST COMING
• FROM THIS PROJECT CALL
sCONTRACTOR
###M###M####
IF YOU DO NOT GET A RESPONSE WITHIN ONE HOUR,
PLEASE CALL PUBLIC WORKS AT 760-776-6450 (DAY) OR
OR CALL A.Q.M.D. AT 1-800-CUT-SMOG
10+ ACRE PM 10 SIGN